The present invention concerns an integration construction between a steam boiler provided with a combustion chamber and a steam turbine. The steam is conducted from the steam boiler (10) along a connector to the steam turbine (11) for rotating an electric generator (G) producing electricity. The supply water circulated via the steam boiler (10) is vaporized in vaporizer (190) located in the steam boiler (10) and superheated in a superheater (120). The supply water is conducted into the boiler through an economizer (20) acting as a heat exchanger, in which heat is transferred from the flue gases of the boiler into the supply water. The economizer (20) is provided with at least two sections, comprising at least one first economizer section (20a1) and at least one second economizer section (20a2). The supply water preheated with bled steams of the steam turbine is conducted in the steam boiler (10) further from the economizer (20) to the vaporizer and the superheater and therethrough, in the form of steam, to the steam turbine. A connector (19) leading to the economizer sections (20a1, 20a2) comprises a branch point (D1) to a by-pass connector (21) of supply water, whereby the economizer section (20a1) can be bypassed by at least part of the supply water flow. The invention also concerns a method in preheating of the supply water for the steam turbine and in its control.
Description




FIELD OF THE INVENTION




The present invention relates to an integration construction between a boiler and a steam turbine and a method in preheating the supply water for a steam turbine and in its control.




BACKGROUND OF THE INVENTION




The last heat face of a steam boiler before the smoke stack is either a flue-gas/air heat exchanger or an economizer. In the present application, a flue-gas/air heat exchanger is understood as a heat exchanger between flue gas and combustion air, in which the heat is transferred from flue gas to combustion air to preheat the combustion air. In the present application, an economizer is understood as a heat exchanger in which thermal energy is transferred from the flue gases to the supply water.




When a flue-gas/air heat exchanger is used, the supply water for the boiler can be preheated by means of bled steam from the steam turbine, whereby the efficiency of the steam turbine process is improved. A flue-gas/air heat exchanger, i.e. a heat exchanger, in which thermal energy is transferred from the flue gases directly into the combustion air, is usually not used in small steam power plants because of its high cost.




When a flue-gas/air heat exchanger is not used, the flue gases of the steam boiler are cooled before passing into the smoke stack using an economizer. In such case, the supply water cannot be preheated with the aid of the bled steam of the steam boiler because the preheating would raise the ultimate temperature of the flue gases and thereby lower the efficiency of the boiler.




In the economizer of a steam boiler, heat is transferred from the flue gases into the supply water. For a steam boiler, a steam boiler provided with a combustion chamber is used. A change in the temperature of the supply water in the economizer is lower than a change in the temperature of the flue-gas side. The temperature rise in the supply water is usually 40 to 50 percent of the respective lowering of temperature on the flue-gas side. Therefore, a difference in the temperature at the hot end of the economizer is considerably higher than at the cold end. This observation results in that, in addition to the heat obtained from the flue gases, heat from other sources can be transferred into the supply water. In a steam turbine process, it is advantageous to utilize bled steam for preheating the supply water.




The economizer of the steam boiler in a steam power plant is divided into two or more parts, the supply water being preheated in the preheaters of the high-pressure side provided between said economizer parts by the bled steam from the steam turbine.




With the aid of a connection, the integration of the steam boiler and the steam turbine process is made more efficient. By means of such arrangement, the flue gases of the steam boiler can be cooled efficiently simultaneously with enhanced efficiency of the steam turbine process.




The investment cost is lower than in an alternative provided with a flue-gas/air heat exchanger:




improved controllability and boiler efficiency




smaller boiler building




lower cost of the boiler.




When a flue-gas/air heat-exchanger solution is unprofitable, an improved process can be implemented with the structure since the use of bled steam can be increased.




The arrangement is preferred especially in an instance in which the combustion air of the steam boiler is heated in one or more steam/air heat exchanger(s) connected in series and utilizing bled steam.




In a prior FI patent No. 101 163, which corresponds to EP 0724683, of the applicant, the advantageous integration construction between the steam boiler and the steam turbine is known. It has proved to be useful that the temperature of the supply water flown through economizers positioned in the flue-gas duct. An amendment to the integration construction disclosed in the FI patent No. 101 163 is described in the present application.




OBJECTS AND SUMMARY OF THE INVENTION




It is disclosed in the present application that by controlling the by-pass flow of the first economizer of the preheater in a divided economizer and possibly by controlling the amount of bled steam of the preheater of supply water also in a by-pass connector, the integration degree of the steam turbine process can be controlled. The preheating is limited by the boiling temperature of the hottest economizer, and the lower limit is the closing of the bled. The control method exerts an efficient impact on the electricity production while deteriorating slightly the efficiency of the boiler when the use of bled steam exceeds the scheduled value. A change in the degree of integration is of the order 10%. A change in the efficiency of the boiler is 2 to 3% at most.




By controlling the flow portion of the supply water flowing past the economizer it is possible




(a) to control the ultimate temperature of the flue gas of the boiler as the power of the boiler changes and as the quality of the fuel varies




(b) to control the ultimate temperature of the supply water so that the ultimate temperature of the supply water after the economizer is as desired (being e.g. 10 to 20° C. below the boiling temperature).




Particularly when a soda recovery boiler is in question, the flue gases are highly soiling and corroding, and therefore, the soda recovery boilers cannot be provided with a flue-gas/air heat exchanger. The flue gases of the boiler are cooled by supplying supply water at about 120° C. into the boiler. The preheating of the combustion air is important because of the combustion of black lye and therefore, the combustion air is heated with the aid of plant steam, typically to about 150° C.




The above integration is not optimal considering the steam turbine process and therefore, the electricity power obtained from a back-pressure turbine will be low. As regards the boiler, an optimal situation prevails when the temperature of the flue gases exiting the boiler is as low as possible and no excessive soiling and corrosion of the heat faces is taking place yet. When the supply water into the boiler is in constant temperature, the temperature of the flue gases varies in accordance with the power level, the quality of fuel and the soiling situation of the heat faces. An optimal temperature is reached only occasionally on partial powers.




As described above, the optimal manner of driving the boiler is reached by integrating a soda recovery boiler and the steam turbine process as follows. The combustion air is preheated, instead of the plant steam, with bled steams of the steam turbine to about 200° C., and a connector is connected between the economizers positioned in the flue gas duct of the boiler from the supply water preheater using bled steam. By controlling the temperature of the supply water entering into the boiler with the aid of the amount of the bled steam passing through the by-pass duct into the preheater and/or by controlling simultaneously the temperature of the supply water so that the amount of bled steam entering into the preheater is controlled, the ultimate temperature of the boiler flue gases can be controlled as desired in all running situations.




The integration construction between a steam boiler and a steam turbine of the invention in controlling the temperature of the supply water of the steam turbine is characterized in what is presented in the claims.











BRIEF DESCRIPTION OF THE DRAWINGS




The invention is described below referring to the advantageous embodiments of the invention illustrated in the drawings of the accompanying figures, whereto, however, the invention is not intended to be exclusively confined.





FIG. 1

presents as a schematic diagram an integration construction between a boiler and a steam turbine; and





FIG. 2

presents a decrease of the flue-gas temperature in a flue-gas duct and an increase of temperature in the supply water of an economizer in a control of the invention.











DETAILED DESCRIPTION OF TILE INVENTION





FIG. 1

presents an integration construction of the invention between a boiler and a steam turbine, comprising a steam boiler, such as soda recovery boiler, to which fuel is brought as shown by arrow M


1


. The boiler is indicated by reference numeral


10


. The evaporator is indicated by reference numeral


190


and the superheater thereafter in a connector


12




a




1


by reference numeral


120


. The flue gases are discharged during a second draught


10




a


from the boiler


10


into a smoke stack


100


and therethrough into the outside air as shown by arrow L


1


. The second draught


10




a


is the part of the boiler which comprises the heat faces prior to the smoke stack


100


. The superheated steam is conducted to the steam turbine


11


along the connector


12




a




1


and the steam turbine


11


is arranged to rotate a generator G producing electricity. From the steam turbine


11


, connectors


13




a




1


and


13




a




2


are provided for bled steams and a connector


13




a




3


into a condensator


18


for exit steam or back-pressure steam entering into the industrial process. The connector


13




a




1


is branched into branch connectors


13




a




1.1


and


13




a




1.2


, of which the connector


13




a




1.1


conducts the supply water running in the connector


19


to a preheater


14


and the connector


13




a




1.2


conducts the combustion air to a preheater


15




a




1


which is provided with a return connector


13




b




1


to a supply water tank


17


. From the preheater


14


of the supply water, a return connector


13




b




2


is provided into the supply water tank


17


. The combustion air is conducted along a connector or an air duct


16


via combustion air preheaters


15




a




1


and


15




a




2


in series into the combustion chamber K of the boiler.




In the integration construction, the temperature of the supply water is continuously raised in a first economizer section


20




a




1


and from the first economizer section


20




a




1


to a second economizer section


20




a




2


. In the preheater


14


, the supply water is heated with the aid of thermal energy obtained from bled steams.




From the steam turbine


11


, a connector


13




a




2


for bled steam is furthermore provided, being branched into branch connectors


13




a




2.1


,


13




a




2.2


. The connector


13




a




2.1


leads to a second combustion air preheater


15




a




2


. From the air preheater


15




a




2


, a discharge connector


13




b




3


is provided into the supply water tank


17


. The connector


13




a




2.2


leads to the supply water tank


17


. A discharge steam connector


13




a




3


of the steam turbine


11


is lead to a condensator


18


. On the trailing side of the condensator


18


the connector


13




a




3


is provided with a pump P


1


to pump water into the supply water tank


17


from the condensator


18


.




A pump P


2


is connected to a connector


19


leading from the supply water tank


17


to a first economizer section


20




a




1


of the economizer


20


in the flue-gas duct


10




a


, said first economizer section


20




a




1


being further connected to a second economizer section


20




a




2


, which economizer sections


20




a




1


and


20




a




2


are in this manner in series in relation to each other and between which economizer sections


20




a




1


and


20




a




2


, a connector


21


′ is connected, being conducted to a branch point D


2


from the supply water preheater


14


, to provide the energy from the bled steam. The economizer


20


is made at least of two sections. The flow direction of the supply water in the connector


19


is denoted by arrow L


2


. The supply water in the connector


19


is made to flow to the first economizer section


20




a




1


and therefrom to the second economizer section


20




a




2


or via a by-pass connector


21


to the supply water preheater


14


and therefrom into the connector


19


between the first economizer section


20




a




1


and the second economizer section


20




a




2


. The first economizer section


20




a




1


and the second economizer section


20




a




2


are connected in series in relation to each other.




Prior to the economizer section


20




a




1


, the connector


19


includes a branch point D


1


for a by-pass connector or a by-pass duct


21


, wherewith the economizer section


20




a




1


positioned first relative to the supply water flow is by-passed. Thus, said economizer section


20




a




1


is bypassable and the supply water is conductable directly to the second economizer section


20




a




2


and preferably, through the supply water preheater


14


. The branch point D


1


comprises advantageously a distribution valve


22


for the supply water flow, which can be a three-way valve, that is, the flow is controlled therewith between the economizer section


20




a




1


and the by-pass duct, i.e. the by-pass connector


21


. Using the valve


22


, the by-pass flow of the economizer section


20




a




1


can therefore be controlled as desired to conform to the running conditions of the boiler. The connector


19


is in this manner connected to the distribution valve


22


having an outlet to the by-pass connector


21


, which is connected to the preheater


14


, and a second outlet, which is connected to the first economizer section


20




a




1


. The connector


21


′ from the preheater


14


is connected via a branch point D


2


to the connector


19


between the economizer sections


20




a




1


and


20




a




2


.




The valve


22


can be an on/or valve in structure, so that the entire supply water quantity of the connector


19


is made to flow either through the by-pass connector


21


or through the economizer section


20




a




1


, or the valve


22


can be a so-called proportional valve in structure, whereby, when the by-pass flow through the by-pass connector


21


is increased, the flow through the economizer section


20




a




1


is reduced by an equal amount, however, to the extent that some of the flow passes through the economizer section


20




a




1


and other part thereof passes through the by-pass connector


21


.




By controlling the amount of bled steam to the preheater


14


with a valve


23


, the temperature of the supply water can be regulated intensively to be as desired in different parts of the economizer


20


including several portions in different running conditions of the boiler


10


. In the preheater


14


, the thermal energy passes from the led steam directly to the supply water or either indirectly through a medium, for instance via water. The preheater


14


is thus a heat exchanger in which heat energy is transferred into the supply water.




In

FIG. 2

, the ascending angle of the cold economizer changes as a main impact of the control. The by-pass is illustrated by a horizontal graph. The temperature of the supply water can be controlled as desired in different spots of the economizer sections


20




a




1


,


20




a




2


. On the inlet side of the economizer section


20




a




1


and on the outlet side of the flue-gas duct


10




a


, the flue-gas temperature is marked by T


1


′ and the temperature of the supply water by T


1


″. On the outlet side of the second economizer section


20




a




2


and on the inlet side of the flue-gas duct the markings of

FIG. 2

are as follows: the flue-gas temperature is T


2


′ and the supply water temperature is T


2


″. The flue-gas duct


10




a


may comprise temperature sensors: a temperature sensor E


2


, measuring the temperature on the inlet side of the flue-gas duct (viewing in the flow direction L


1


of the flue gas), and a temperature sensor E


1


, measuring the temperature of the flue gas on the outlet side of the flue-gas duct


10




a


. In addition, the apparatus may comprise temperature sensors in the connector of the supply water


19


. Temperature can be measured from the supply water after the first economizer section


20




a




1


before the second economizer section


20




a




2


and from the supply water after the second economizer section


20




a




2


when viewed in the flow direction L


2


of the supply water. The flow direction of the supply water in the connector


19


is marked by arrow L


2


.




In the method, in preheating the supply water of the steam turbine and in its control, the procedure is as follows. The supply water is conducted into an economizer


20


of the steam boiler


10


provided with a combustion chamber K, in which heat is transferred in a heat exchanger from the flue gases into the supply water. The economizer


20


by its heat faces is arranged to be positioned, at least in part, in a flue-gas duct


10




a


of the steam boiler


10


. At least a two-portion economizer


20




a




1


,


20




a




2


is used for heating the supply water, said portions being in series. The supply water preheated with the aid of bled steams is conducted to a second economizer section


20




a




2


and further to a vaporizer


190


and a superheater


120


and further, in the form of steam, to the steam turbine


11


to rotate the electric generator G and to produce electricity. In the method, also the combustion air is heated with the aid of the energy acquired from bled steams. In the method, the by-pass quantity of the supply water of the economizer


20


is controlled with a valve


22


. In addition to the by-pass, the amount of bled steam flow flown into the preheater


14


of the supply water is controlled with a valve


23


. In the method, the valve(s)


22


and/or


23


is/are controlled on the basis of temperature measurement of supply water flown through temperature measurement of flue gases and/or the economizer


20


.



Claims
  • 1. An integration construction between a steam boiler and a steam turbine provided with a combustion chamber, comprising:a connector structured and arranged to conduct steam from the steam boiler(10) to the steam turbine (11) for rotating an electric generator (G) generating electricity, a vaporizer (190) located in the steam boiler (10), said vaporizer (190) is structured and arranged to vaporize a supply water being circulated through the steam boiler (10) and superheated in a superheater (120), an economizer (20) acting as a heat exchanger, in which heat is transferred from the flue gases of the boiler into the supply water, and the supply water is conducted into the boiler through the economizer (20), wherein the economizer (20) is provided with at least two sections, comprising at least one first economizer section (20a1) and at least one second economizer section (20a2), which are in series, wherein the supply water being preheated with bled steams of the steam turbine is conducted in the steam boiler (10) further to the vaporizer (190) and the superheater (120) and therethrough, in the form of steam, to the steam turbine (11), another connector (19) leading to the economizer sections (20a1, 20a2) comprises a first branch point (D1) to a by-pass connector (21) of supply water, so that the at least one first economizer section (20a1) is by-passable, at least concerning part of the supply water flow, and wherein the by-pass connector (21) is connected to a preheater (14) of supply water and that from the preheater (14) a connector (21′) leads through a second branch point (D2) to the another connector (19) between the economizer sections (20a1 and 20a2) and that bled steam is conducted to the preheater (14) of supply water from the steam turbine (11).
  • 2. The integration construction according to claim 1, wherein the first branch point (D1) comprises a distribution valve (22), wherewith the supply water flow can be controlled between the at least one first economizer section (20a1) and the by-pass connector (21).
  • 3. The integration construction according to claim 1, wherein a branch connector (13a1.1) leading to the supply water preheater (14) comprises a second valve (23) for controlling the amount of bled steam flow to the preheater (14).
  • 4. A method in preheating of a supply water for a steam turbine and in its control, comprising the steps of:conducting the supply water into an economizer (20) of a steam boiler (10) provided with a combustion chamber (K), in which heat is transferred in a heat exchanger from the flue gases into the supply water, arranging the economizer (20), at least partly by its heat faces, in a flue-gas duct (10a) of the steam boiler (10), wherein the economizer includes at least two sections (20a1, 20a2) being used for heating the supply water, said sections being in series in relation to each other, heating combustion air with the aid of the energy obtained from bled steams, and controlling an amount of a by-pass flow of the supply water of the economizer (20) with a first valve (22), wherein in addition to the by-pass flow, controlling the amount of bled steam flow made to flow into a supply water preheater (14) in a by-pass flow connector (21) with a second valve (23), and providing a connector (21′) from the preheater (14) being connected via a branch point (D2) to be in the line (19) between the economizer sections (20a1, 20a2).
  • 5. The method according to claim 4, wherein the first valve (22) and/or the second valve (23) is/are controlled on the basis of the temperature measurement of the flue gases and/or of the supply water made to flow through the economizer (20).
Priority Claims (1)
Number Date Country Kind
20002894 Dec 2000 FI
PCT Information
Filing Document Filing Date Country Kind
PCT/FI01/00002 WO 00
Publishing Document Publishing Date Country Kind
WO02/05760 7/25/2002 WO A
US Referenced Citations (8)
Number Name Date Kind
3667217 Vidal et al. Jun 1972 A
3913330 Horlitz, Jr. Oct 1975 A
4057966 Prutkovsky et al. Nov 1977 A
4858562 Arakawa et al. Aug 1989 A
4976107 Korpela Dec 1990 A
5038568 Gounder et al. Aug 1991 A
5365730 Bruckner et al. Nov 1994 A
5840130 Liebig et al. Nov 1998 A
Foreign Referenced Citations (6)
Number Date Country
0037845 Oct 1981 EP
1050667 May 1994 EP
0724683 Oct 1994 EP
77512 Nov 1988 FI
9511370 Apr 1995 WO
101163 Apr 1998 WO