The disclosure relates to a leakage current calculation device and a leakage current calculation method for calculating a leakage current.
Examples of techniques for calculating a leakage current in a load such as a three-phase motor are disclosed in Non-Patent Document 1 and Patent Document 1. The technique of Non-Patent Document 1 is intended to precisely measure a ground insulation resistance component leakage current in a facility in which an inverter is not used in driving a load such as a three-phase motor. On the other hand, the technique of Patent Document 1 is intended to precisely measure a ground insulation resistance component leakage current in a facility in which an inverter is used in driving a load.
[Non-Patent Document 1] Eikichi Osaki, “Thorough Examination of Trouble in Electric Fields”, published in the February 2000 issue of Shin-denki (New electricity), Ohmsha, Ltd., p. 46 to 51
[Patent Document 1] Japanese Patent Laid-Open No. 2014-228519 (published in Dec. 8, 2014)
As disclosed in Non-Patent Document 1 and Patent Document 1, in the past, the configurations of devices that calculate a ground insulation resistance component leakage current have differed depending on the presence or absence of an inverter. Therefore, the related art has a problem in that different leakage current calculation devices need to be used depending on whether an inverter is used in a facility. The related art further has a problem in that, in a case where an inverter is newly added to a facility in which an inverter is not used for the purpose of energy saving or the like, a leakage current calculation device needs to be changed accordingly.
The disclosure was contrived in order to solve the above problem. The disclosure provides a leakage current calculation device and a leakage current calculation method that make it possible to precisely calculate a ground insulation resistance component leakage current regardless of the presence or absence of an inverter.
According to an aspect of the disclosure, in order to solve the above problem, there is provided a leakage current calculation device including: a voltage measurement unit that measures at least one of line voltages in a three-phase AC type commercial power system to which one of three different phases is grounded; a ground voltage calculation unit that calculates a ground voltage between a neutral point and an earth of the commercial power system from the at least one line voltage measured by the voltage measurement unit; a leakage current measurement unit that measures a leakage current that flows between a load connected to the commercial power system and the earth; a frequency component extraction unit that extracts a frequency component that is synchronized with a system frequency of the commercial power system from the measured leakage current; a phase difference decision unit that decides a phase difference between the calculated ground voltage and the extracted frequency component; an insertion determination unit that determines whether an inverter is inserted between the commercial power system and the load; and a leakage current calculation unit that calculates a ground insulation resistance component leakage current of the system frequency portion that flows between the load and the earth through ground insulation resistance of the load on the basis of a calculation procedure corresponding to a result of determination of the insertion determination unit.
According to an aspect of the disclosure, in order to solve the above problem, there is provided a leakage current calculation method including: a voltage measurement step of measuring at least one of line voltages in a three-phase AC type commercial power system to which one of three different phases is grounded; a ground voltage calculation step of calculating a ground voltage between a neutral point and an earth of the commercial power system from the measured at least one line voltage; a leakage current measurement step of measuring a leakage current that flows between a load connected to the commercial power system and the earth; a frequency component extraction step of extracting a frequency component that is synchronized with a system frequency of the commercial power system from the measured leakage current; a phase difference decision step of deciding a phase difference between the calculated ground voltage and the extracted frequency component; an insertion determination step of determining whether an inverter is inserted between the commercial power system and the load; and a leakage current calculation step of calculating a ground insulation resistance component leakage current of the system frequency portion that flows between the load and the earth through ground insulation resistance of the load on the basis of a calculation procedure corresponding to a result of determination in the insertion determination step.
According to the disclosure, it is possible to precisely calculate a ground insulation resistance component leakage current regardless of the presence or absence of an inverter.
Embodiment 1 according to the disclosure will be described below with reference to
(First Configuration Example)
The commercial power system 2 is a three-phase AC type alternating-current power source in which an S-phase of three different phases (an R-phase, an S-phase, and a T-phase) is grounded to the earth E. The three phases are connected to the input sides of the three-phase motor 5, respectively, through an R-line, an S-line, and a T-line. The three-phase motor 5 operates using a voltage supplied from the commercial power system 2.
A zero-phase current transformer 4 surrounding the R-line, the S-line, and the T-line is provided between the commercial power system 2 and the three-phase motor 5. The zero-phase current transformer 4 measures a three-phase synthesized ground zero-phase current I0 that flows between the commercial power system 2 and the three-phase motor 5. Although this will be described later in detail, this zero-phase current I0 is equal to a leakage current that flows between the three-phase motor 5 and the earth E.
(Second Configuration Example)
The commercial power system 2 is a three-phase AC type alternating-current power source in which an S-phase of three different phases (an R-phase, an S-phase, and a T-phase) is grounded to the earth E. The three phases are connected to the input sides of the inverter 3, respectively, through the R-line, the S-line, and the T-line.
The inverter 3 generates predetermined control voltages from three-phase power that is supplied from the commercial power system 2, and outputs the generated control voltages to the three-phase motor 5 through three lines (a U-line, a V-line, and a W-line) corresponding to three phases (a U-phase, a V-phase, and a W-phase) on the output sides. The three-phase motor 5 is connected to the output sides of the inverter 3, and operates using each of the supplied control voltages.
The zero-phase current transformer 4 surrounding the U-line, the V-line, and the W-line is provided between the inverter 3 and the three-phase motor 5. The zero-phase current transformer 4 measures the three-phase synthesized ground zero-phase current I0 that flows between the inverter 3 and the three-phase motor 5. Although this will be described later in detail, this zero-phase current I0 is equal to a leakage current that flows between the three-phase motor 5 and the earth E.
In the configuration shown in
(Configuration of Leakage Current Calculation Device 1)
The voltage measurement unit 11 measures at least one of line voltages of the commercial power system 2. In the configuration shown in
The ground voltage calculation unit 13 calculates a ground voltage between a neutral point and the earth E of the commercial power system 2 from at least one of the line voltages measured by the voltage measurement unit 11. In the present embodiment, a ground voltage is calculated from the line voltage between R-S.
The leakage current measurement unit 12 measures a leakage current (a zero-phase current) that flows between the three-phase motor 5 and the earth E through the zero-phase current transformer 4. The leakage current measurement unit 12 may have a low-pass filter or a bandpass filter for removing a high-frequency component or extracting a system frequency component from the measured leakage current.
The frequency component extraction unit 14 extracts at least one frequency component including a frequency component synchronized with the system frequency of the commercial power system 2 (that is, a frequency component of the same frequency as the system frequency) from the measured leakage current. A DFT, an FFT or the like, for example, may be used in this extraction process.
The phase difference calculation unit 15 calculates a phase difference between the measured line voltage or the calculated ground voltage and the extracted frequency component of the system frequency. The calculation of a phase difference is performed by, for example, an arithmetic operation process, but instead, a phase difference may be decided by measuring a phase difference using a predetermined measurement circuit.
The insertion determination unit 16 determines whether the inverter 3 is inserted between the commercial power system 2 and the three-phase motor 5. In the present embodiment, the insertion determination unit 16 determines the presence or absence of the insertion of the inverter 3 on the basis of the at least one frequency component extracted from the leakage current by the frequency component extraction unit 14. The details of determination will be described later.
The circle center calculation unit 17 calculates the central point of a circle that is drawn by each point specified by the frequency components of the system frequency calculated at at least three different points in time and the decided phase difference.
The resistance component leakage current calculation unit 18 calculates a current that flows between the three-phase motor 5 and the earth E through the ground insulation resistance of the three-phase motor 5 (a ground insulation resistance component leakage current of a system frequency portion) on the basis of the calculated central point of the circle.
The insulation resistance calculation unit 19 calculates the ground insulation resistance of the three-phase motor 5 using the calculated ground insulation resistance component leakage current of a system frequency portion and the measured line voltage or the calculated ground voltage. In the insulation resistance calculation unit 19, a line voltage is used in a case where the inverter 3 is not inserted, and a ground voltage is used in a case where the inverter is inserted.
The insulation failure determination unit 20 determines the presence or absence of an insulation failure of the three-phase motor 5 on the basis of the calculated ground insulation resistance component leakage current of a system frequency portion or the ground insulation resistance.
The output unit 21 outputs the result of determination of the insulation failure in a desired form to the outside of the leakage current calculation device 1. This output is performed as, for example, screen display, communication output, or contact signal output.
(Calculation of Line Voltage, Leakage Current and Ground Insulation Resistance in First Configuration)
In a case where the inverter 3 is not inserted, in the leakage current calculation device 1, a value measured by the voltage measurement unit 11 is used as a line voltage, and a value measured by the current measurement unit 12 is used as a leakage current. The leakage current calculation device 1 further calculates a resistance component leakage current I0r using a method disclosed in Non-Patent Document 1 or a method disclosed in Japanese Patent Laid-Open No. 2013-195023. The leakage current calculation device 1 can calculate ground insulation resistance R0=Vrs/I0r by using the calculated line voltage Vrs and resistance component leakage current I0r.
(Calculation of Ground Voltage in Second Configuration)
The ground voltage that is applied to the ground insulation resistance of the three-phase motor 5 is equal to a voltage between a neutral point (an N-phase) of the commercial power system 2 and the earth E. In the commercial power system 2, as shown in (a) of
On the other hand, as shown in (b) of
Here, the voltage Vu of the U-phase, the voltage Vv of the V-phase, and the voltage Vw of the W-phase are mutually phase-shifted by 120°, and thus have characteristics in which the sum of all the voltages of the respective phases is zero. That is, a relation of Vu+Vv+Vw=0 is established. Therefore, the voltage Vs∠180° is a ground voltage of the system frequency portion of the commercial power system 2 that is applied to the ground insulation resistance of the three-phase motor 5.
As shown in (a) of
(Leakage Current in Second Configuration)
The ground insulation resistance and ground floating capacitance of the three-phase motor 5 are impedance components located between the wiring or coil of the three-phase motor 5 and the earth E. These are connected in parallel to each other. Therefore, as shown in (a) of
Similarly, both ground insulation resistance Rv and ground floating capacitance Cv located between the V-phase and the earth E are components constituting impedance Zv located between the V-phase and the earth E. In addition, both ground insulation resistance Rw and ground floating capacitance Cw located between the W-phase and the earth E are components constituting impedance Zw located between the W-phase and the earth E.
As shown in (b) of
When attention is focused on the system frequency component, the ground voltage Vs∠180° is applied in the same phase to the respective phases (U, V, W) on the output side of the inverter 3. For this reason, relations of Iu=Vs∠180°/Zu, Iv=Vs∠180°/Zu, and Iv=Vs∠180°/Zu are established. Therefore, a relation of I0=Vs∠180°/(1/Zu+1/Zv+1/Zw) is established.
As described above, the zero-phase current I0 that is measured through the zero-phase current transformer 4 is equal to a leakage current that flows through the synthetic impedance of the three-phase motor 5. Therefore, hereinafter, a leakage current may be denoted by a leakage current I0.
(Ground Insulation Resistance in Second Configuration)
When attention is focused on the system frequency component, the ground voltage Vs∠180° is applied in the same phase to the respective phases (U, V, W) on the output side of the inverter 3. This can be considered to amount to Zu, Zv, and Zw being connected in parallel to a common bus to which the ground voltage Vs∠180° is applied. Therefore, when the synthetic impedance between the three-phase motor 5 and the earth E is set to Z0, a relation of 1/Z0=1/Zu+1/Zv+1/Zw is established. Rearranging this expression forms a relation of I0=Vs∠180°/Z0, and thus a relation of Z0=Vs∠180°/I0 is established.
The ground synthetic impedance ZO includes, as components, the ground insulation resistance and the ground floating capacitance of the three-phase motor 5 that are connected in parallel to each other. Therefore, when a phase difference between the zero-phase current I0 and the ground voltage Vs∠180° is set to θ, a current I0r that flows through the ground insulation resistance of Z0 is I0×cos θ. On the other hand, a current I0c that flows through the ground floating capacitance of Z0 is I0×sin θ.
Thereby, the ground insulation resistance R0 of the three-phase motor 5 is calculated as R0=Vs∠180°/I0r. On the other hand, the capacitive reactance C0 of the ground floating capacitance of the three-phase motor 5 is calculated as C0=Vs∠180°/I0c.
(Process Flow)
In step S1, the voltage measurement unit 11 measures a line voltage between the R-phase and the S-phase. In step S2, the ground voltage calculation unit 13 calculates a ground voltage on the basis of the measured line voltage. In step S3, the leakage current measurement unit measures a leakage current through the zero-phase current transformer 4. In step S4, the frequency component extraction unit 14 extracts at least one frequency component including the frequency component of the system frequency from the measured leakage current. In a case where the inverter 3 is not inserted, the frequency component extraction unit 14 extracts only the frequency component of the system frequency of the commercial power system 2 from the leakage current. On the other hand, in a case where the inverter 3 is inserted, the frequency component of the system frequency, the frequency component of an operating frequency, and the frequency component of a frequency that is the integral multiple of the operating frequency are extracted. An FFT or a DFT, for example, is used in a process of extracting these frequency components.
In steps S6 to S10, the insertion determination unit 16 automatically determines a calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency. In other words, the insertion determination unit 16 does not require, for example, a user's input from the outside of the leakage current calculation device 1 (input of information for designating a calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency) in order to determine the calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency. Therefore, it is possible to determine a calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency without a user spending much time or effort to use the leakage current calculation device 1. Meanwhile, the insertion determination unit 16 can also determine a calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency on the basis of input from the outside of the leakage current calculation device 1. In this case, the leakage current calculation device 1 can also accurately determine a calculation procedure corresponding to the presence or absence of insertion of an inverter and the consistency/inconsistency of a frequency.
In step S6, the resistance component leakage current calculation unit 18 determines the presence or absence of the leakage current I0 measured at any point in time and a change in the calculated phase difference θ. In the case of NO in step S6, the resistance component leakage current calculation unit 18 selects, in step S7, a calculation procedure for calculating a ground insulation resistance component leakage current which corresponds to the presence of insertion of an inverter and the consistency of a frequency.
In the case of YES in step S6, the insertion determination unit 16 determines, in step S8, the presence or absence of frequencies other than a frequency that is the integral multiple of the system frequency. In the case of NO in step S8, the insertion determination unit 16 selects, in step S9, a calculation procedure for calculating a ground insulation resistance component leakage current which corresponds to the absence of insertion of an inverter. In a case where the system frequency is 60 Hz, the insertion determination unit 16 selects a calculation procedure corresponding to the absence of insertion of an inverter, for example, in a case where each frequency component of 60 Hz, 120 Hz, and 180 Hz is extracted. Frequencies extracted in this case are not limited to these three, and other frequencies such as, for example, 240 Hz, 300 Hz, . . . can also be extracted. On the other hand, in the case of YES in step S8, the insertion determination unit 16 selects, in step S10, a calculation procedure for calculating a ground insulation resistance component leakage current which corresponds to the presence of insertion of an inverter and the inconsistency of a frequency. The insertion determination unit 16 selects a calculation procedure corresponding to the presence of insertion of an inverter and the inconsistency of a frequency, for example, in a case where each frequency component of 50 Hz, 60 Hz, 100 Hz, 120 Hz, 150 Hz, and 180 Hz is extracted.
In step S11, the resistance component leakage current calculation unit 18 calculates a ground insulation resistance component leakage current on the basis of a calculation procedure selected in any of steps S7, S9, or S10. In step S12, the insulation failure determination unit 20 calculates the ground insulation resistance of the three-phase motor 5 on the basis of the calculated ground insulation resistance component leakage current.
(Calculation Procedure in Case of Absence of Insertion of Inverter 3)
A calculation procedure of a ground insulation resistance component leakage current which is selected in a case where the inverter 3 is not inserted is a calculation procedure based on the relational expression of I0R=I0×(cos θ+1/√3×sin θ). In this expression, I0R is a ground insulation resistance component leakage current. I0 is a frequency component extracted from the leakage current. In addition, θ is a phase difference. The resistance component leakage current calculation unit 18 can accurately calculate a ground insulation resistance component leakage current by selecting this expression in step S9 in a case where the inverter 3 is not inserted. The insulation failure determination unit 20 calculates the ground insulation resistance of the three-phase motor 5 by dividing the R-S line voltage by the ground insulation resistance component leakage current. Thereby, it is possible to accurately calculate ground insulation resistance in a case where the inverter 3 is not inserted.
(Calculation Procedure in Case of Presence of Insertion of Inverter 3 and Inconsistency of Frequency)
A calculation procedure of a ground insulation resistance component leakage current which is selected in a case where the inverter 3 is inserted and the system frequency and the operating frequency are not coincident with each other is, for example, as follows.
In the drawings, (a) of
The leakage current I0 that is measured by the leakage current measurement unit 12 includes a component (I0_sys) that is synchronized with the system frequency of the commercial power system 2 and a component (I0_inv) that is synchronized with the operating frequency of the inverter 3. In order to calculate the ground insulation resistance of the three-phase motor 5, it is necessary to extract only the leakage current I0_sys that is a leakage current component synchronized with the system frequency from the leakage current I0.
In (a) of
In this case, the system frequency component extraction unit 14 extracts only the leakage current I0_sys of the system frequency component from the measured leakage current I0 by executing an arithmetic operation process of extracting a leakage current having the same frequency as the system frequency. Since the system frequency and the operating frequency are different from each other, in this extraction process, a component that is synchronized with the system frequency is extracted, but a component that is synchronized with the operating frequency is not extracted. Thereby, the extracted leakage current I0_sys does not include the leakage current I0_inv that is synchronized with the operating frequency component of the inverter 3.
The impedance between the three-phase motor 5 and the earth E includes both the ground insulation resistance and the ground floating capacitance. The ground voltage Vs∠180° is applied to both the ground insulation resistance and the ground floating capacitance, whereby the phase of the leakage current I0 to be measured is shifted from the phase of the ground voltage Vs∠180° due to the influence of the ground floating capacitance. Therefore, the phase difference θ of the leakage current I0_sys that is extracted from the leakage current I0 is also shifted from the phase of the ground voltage Vs∠180°.
As shown in (a) of
Therefore, as shown in (a) of
As described above, in a case where the system frequency of the commercial power system 2 and the operating frequency of the inverter 3 are different from each other, the leakage current calculation device 1 can precisely calculate the leakage current I0_sys of the system frequency portion by extracting a component that is synchronized with the system frequency from the measured leakage current I0. As a result, it is also possible to precisely calculate the ground insulation resistance of the three-phase motor 5 by using the ground voltage Vs∠180° and the leakage current I0R_sys.
(Calculation Procedure in Case of Presence of Insertion of Inverter 3 and Consistency of Frequency)
In a case where the inverter 3 is inserted, and the system frequency and the operating frequency are coincident with each other, the resistance component leakage current calculation unit 18 calculates a ground insulation resistance component leakage current on the basis of a series of calculation procedures to be described below.
(Calculation Principle of Leakage Current)
In the drawings, (b) of
In a case where the inverter 3 is inserted between the commercial power system 2 and the three-phase motor 5, the leakage current I0 that is measured by the leakage current measurement unit 12 includes the component (I0_sys) that is synchronized with the system frequency of the commercial power system 2 and the component (I0_inv) that is synchronized with the operating frequency of the inverter 3. In order to calculate the ground insulation resistance of the three-phase motor 5, it is necessary to extract only the leakage current I0_sys that is a frequency component synchronized with the system frequency from the leakage current I0. As shown in (b) of
In a case where settings of the system frequency and the operating frequency are coincident with each other, the frequency component extraction unit 14 is not able to discriminate between a component that is synchronized with the system frequency included in the leakage current I0 and a component that is synchronized with the operating frequency. Therefore, when the frequency component extraction unit 14 executes a process of extracting a component that is synchronized with the system frequency from the leakage current I0, a leakage current I0_mix in which the leakage current I0_sys synchronized with the system frequency and the leakage current I0_inv synchronized with the operating frequency are mixed is extracted as a result.
In this case, as shown in (b) of
Therefore, in a case where the system frequency and the operating frequency are coincident with each other, the terminal point of the vector is not determined as one point unlike (a) of
(Reason for Drawing Circle)
Even if the system frequency and the operating frequency are set to have the same value, the frequencies are strictly slightly different from each other. For example, even in a case where each of the frequencies is set to 60 Hz, a slight shift therebetween occurs as if the system frequency is 60.00 Hz, while the operating frequency is 60.01 Hz. As shown in (a) of
As described above, in a case where the system frequency and the operating frequency are coincident with each other, the leakage current I0_mix extracted from the leakage current I0 includes the leakage current I0_sys of the system frequency portion and the leakage current I0_inv of the operating frequency portion. In this case, since the phase difference 8 to be decided is a phase difference between the ground voltage Vs∠180° and the leakage current I0_mix, a shift occurs between the waveform of I0_sys included in the leakage current I0_inv and the waveform of I0_inv, whereby the value of the phase difference θ is shifted with a time. Thereby, the position of a terminal point of the leakage current I0_mix expressed using vector notation changes with a time. For example, the positions of the terminal points (specific points) P1 to P3 of the leakage current I0 change in response to shifts of the waveforms of P1 to P3 in (a) of
The terminal point of I0_sys is coincident with a central point 94 of the circle 93. Therefore, the leakage current calculation device 1 of the present embodiment calculates this central point 94, and precisely calculates I0R_sys and I0C_inv by further projecting the central point 94 onto the horizontal axis and the vertical axis of the plane coordinate axis.
There are various methods of calculating the central point of a circle that is drawn by the terminal point of the leakage current I0_mix. Hereinafter, three methods among them will be described.
(First Method)
In the example of
The circle center calculation unit 17 calculates the circumcenter of a triangle 101 with vertices at the points P1 to P3 instead of directly calculating a circle 102 passing through the points. This circumcenter is coincident with a central point 103 of the circle 102 that is circumscribed about the triangle 101. In this manner, in the example of
The circle center calculation unit 17 outputs the calculated central point 103 to the resistance component leakage current calculation unit 18. As shown in
The resistance component leakage current calculation unit 18 outputs calculated I0R_sys to the insulation resistance calculation unit 19. The insulation resistance calculation unit 19 calculates the ground insulation resistance of the three-phase motor 5 using the leakage current I0R_sys and the ground voltage Vs∠180°.
In this method, the central point 103 is calculated using only the three points P1 to P3. That is, since it may be sufficient to measure the leakage current I0 at three different points in time in order to calculate I0R_sys, it is possible to calculate I0R_sys at high speed.
(Second Method)
In the example of
The circle center calculation unit 17 calculates the equation of a circle 111 passing through each of the points Pn. A central point 112 of the circle 111 is calculated using this equation. In the example of
An error E is specified by E=Σ((x−a)2×(y−b)2=r2). However, when the error E is calculated using this expression, a, b, and r are all becomes a quartic function, which results in very complicated calculation. Consequently, first, a relational expression in which a, b, and r are replaced by parameters A, B, and C is obtained as follows.
E=Σ(x2+y2+Ax+By+C)
Here, relations of A=−2a, B=−2b, and C=a2+b2−r2 are established. When this relational expression is differentiated partially, the following expression is obtained.
When these expressions are solved by a matrix operation, the following determinant is obtained.
When this determinant is developed, the following determinant is obtained.
The parameters A, B, and C are decided by solving this determinant. The coefficients a, b, and r can be decided by substituting the decided parameters A, B, and C into the above-described relational expression. Thereby, since the equation of the circle 111 is calculated, the central point 112 is calculated using this equation. The calculation of the ground insulation resistance component leakage current I0_sys based on the central point 112 and the calculation of the ground insulation resistance of the three-phase motor 5 based on the leakage current I0_sys and the ground voltage Vs∠180° are no different than the above-described example.
In this method, since the least squares method of a circle is used in the calculation of the circle 11, it is possible to precisely calculate the central point 112 of the circle 111. Therefore, it is possible to precisely calculate the leakage current I0_sys and the ground insulation resistance.
An example of the actual calculation result of I0_sys is shown in (b) of
(Third Method)
In the example of
In this method, the frequency component extraction unit 14 extracts I0_mix at each point in time over within a certain period of time (a long time more than 60 seconds is preferable), that is, until points of the circumference or more of a circle are calculated.
Similarly, the phase difference calculation unit 15 calculates the phase difference θ at each point in time until points of the circumference or more of a circle are calculated. In this method, the circle center calculation unit 17 does not calculate the center of a circle. Instead, the insulation resistance calculation unit 19 calculates a ground insulation resistance component leakage current I0R_mix in the leakage current I0_mix at each point in time using the leakage current I0_mix and the phase difference θ which are obtained at each point in time. This is obtained by multiplying I0_mix by cos θ. That is, a relation of I0R_mix=I0_mix×cos θ is established.
The insulation resistance calculation unit 19 executes the calculation of I0R_mix at each point in time over a long time (more than 60 seconds). The value of I0R_mix is coincident with the value of the horizontal axis at a point where a terminal point of I0_mix expressed using vector notation is projected onto the horizontal axis. Since this terminal point draws a circle as described above, the point where the terminal point is projected onto the horizontal axis is located within a line obtained by projecting the entire circle onto the horizontal axis. Therefore, a minimum value 131 and a maximum value 132 corresponding to each end of a line are determined in I0R_mix to be calculated.
Since the minimum value 131 and the maximum value 132 correspond to each end in a horizontal axis direction in a circle that is drawn by the terminal point of I0_mix, the intermediate value 132 between the minimum value 131 and the maximum value 132 corresponds to the central point of the circle. As described above, since the value obtained by projecting the central point of the circle onto the horizontal axis corresponds to I0R_sys, the resistance component leakage current calculation unit 18 can calculate I0R_sys by calculating the intermediate value 132.
Meanwhile, the calculation of the ground insulation resistance of the three-phase motor 5 based on I0R_sys and the ground voltage Vs∠180° is no different than the above-described example.
In this method, since the center of a circle is not required to be obtained using a complicated equation in order to calculate I0R_sys, it is possible to obtain I0R_sys through simple calculation.
An example of the actual calculation result of I0R_sys based on the third method shown in (b) of
(Advantage of the Present Embodiment)
As described above, the leakage current calculation device 1 determines whether the inverter 3 is inserted between the commercial power system 2 and the three-phase motor 5. The leakage current calculation device 1 further calculates the ground insulation resistance component leakage current of the system frequency portion that flows between the three-phase motor 5 and the earth E through the ground insulation resistance of the three-phase motor 5 on the basis of the calculation procedure corresponding to the result of determination. Specifically, in a case where the inverter 3 is not inserted, the leakage current calculation device 1 calculates the ground insulation resistance component leakage current on the basis of the calculation procedure corresponding thereto. On the other hand, in a case where the inverter 3 is inserted, the ground insulation resistance component leakage current is calculated on the basis of the calculation procedure corresponding thereto. Therefore, even in a case where the inverter 3 is present in a facility or is not present, the presence of the leakage current calculation device 1 is sufficient to calculate the ground insulation resistance component leakage current. In other words, a device for measuring the ground insulation resistance component leakage current is not required except the leakage current calculation device 1. Therefore, the leakage current calculation device 1 according to the present embodiment can precisely calculate the ground insulation resistance component leakage current regardless of the presence or absence of an inverter.
Embodiment 2 according to the disclosure will be described below with reference to
(Schematic Configuration)
The three-phase motors 5a and 5b are driven by inverters 3a and 3b, respectively. All the input sides of the inverters 3a and 3b are connected to the common commercial power system 2. The output side of the inverter 3a is connected to the three-phase motor 5a, while the output side of the inverter 3b is connected to the three-phase motor 5b.
In addition, a zero-phase current transformer 4a is disposed between the inverter 3a and the three-phase motor 5a, while a zero-phase current transformer 4b is disposed between the inverter 3b and the three-phase motor 5b. Both the zero-phase current transformers 4a and 4b are connected to the leakage current measurement unit 12 of the leakage current calculation device 1.
(Calculation Procedure)
In the present embodiment, the leakage current calculation device 1 calculates a ground insulation resistance component leakage current and ground insulation resistance corresponding to the three-phase motors 5a and 5b, respectively. The procedure will be described below.
The voltage measurement unit 11 measures at least one of line voltages on one input side of a plurality of inverters 3a and 3b. Since the input side of each of the inverters 3a and 3b is connected to the common commercial power system 2, for example, the voltage Vrs of the inverter 3a between the R-phase and the S-phase is completely equal to the voltage Vrs of the inverter 3b between the R-phase and the S-phase. In this manner, in the present embodiment, since the voltage Vrs may be measured at only one point, it is possible to further simplify the configuration of the leakage current calculation device 1.
The ground voltage calculation unit 13 calculates the ground voltage Vs∠180° on the basis of the voltage Rs measured from the input side of the inverter 3a. Since the voltage Vrs is common to the inverters 3a and 3b, the leakage current calculation device 1 uses the voltage Vs∠180° in the following process as a ground voltage common to the three-phase motor 5a and the three-phase motor 5b.
The leakage current measurement unit 12 measures the leakage current of the three-phase motor 5a through the zero-phase current transformer 4a, and measures the leakage current of the three-phase motor 5b through the zero-phase current transformer 4b. That is, the leakage current calculation device 1 includes one leakage current measurement unit 12 common to the three-phase motors 5a and 5b.
Meanwhile, the leakage current calculation device 1 may include a plurality of leakage current measurement units 12a and 12b corresponding to the three-phase motors 5a and 5b, respectively. In this configuration, the leakage current measurement unit 12a is connected the zero-phase current transformer 4a, while the leakage current measurement unit 12b is connected to the zero-phase current transformer 4b. The leakage current measurement unit 12a measures the leakage current of the three-phase motor 5a through the zero-phase current transformer 4a, while the leakage current measurement unit 12b measures the leakage current of the three-phase motor 5b through the zero-phase current transformer 4b.
The frequency component extraction unit 14 extracts a frequency component corresponding to the three-phase motor 5a from the leakage current of the three-phase motor 5a. On the other hand, a frequency component corresponding to the three-phase motor 5b is extracted from the leakage current of the three-phase motor 5b.
The phase difference calculation unit 15 calculates a phase difference between the calculated ground voltage and the frequency component of the three-phase motor 5a. Further, a phase difference between the calculated ground voltage and the frequency component of the three-phase motor 5b is calculated.
The resistance component leakage current calculation unit 18 calculates the ground insulation resistance component leakage current of the three-phase motor 5a on the basis of the central point of a circle corresponding to the three-phase motor 5a. In addition, the ground insulation resistance component leakage current of the three-phase motor 5b is calculated on the basis of the central point of a circle corresponding to the three-phase motor 5b.
The insulation resistance calculation unit 19 calculates the ground insulation resistance of the three-phase motor 5a from the ground voltage Vs∠180° and the ground insulation resistance component leakage current of the three-phase motor 5a. In addition, the ground insulation resistance of the three-phase motor 5b is calculated from the ground voltage Vs∠180° and the ground insulation resistance component leakage current of the three-phase motor 5b.
(Determination Based on Degree of Deviation)
The insulation failure determination unit 20 can determine the degree of insulation deterioration in each of the three-phase motors 5a and 5b by comparing the ground insulation resistance component leakage current of the system frequency portion of the three-phase motor 5a with the ground insulation resistance component leakage current of the system frequency portion of the three-phase motor 5b. For example, in the example of (a) of
(Determination Based on Threshold)
The insulation failure determination unit 20 can also specify a three-phase motor 5 in which a corresponding ground insulation resistance component leakage current out of the three-phase motors 5a and 5b exceeds a prescribed threshold as the three-phase motor 5a which is in the state of insulation deteriorate. For example, in (a) of
Meanwhile, the determination using the degree of deviation or the threshold described above can also be performed with respect to not only the ground insulation resistance component leakage current, but also the ground insulation resistance of the three-phase motors 5a and 5b as shown in (b) of
(Modification Example)
In a configuration in which the leakage current calculation device 1 includes a plurality of leakage current measurement units 12, the leakage current measurement units 12 for measuring the leakage current of the three-phase motor 5 that is not a target for monitoring are unnecessary. The leakage current calculation device 1 including such unnecessary leakage current measurement units 12 leads to a useless increase in the cost of the leakage current calculation device 1.
In order to prevent this, each of the leakage current measurement units 12 may be an extension unit for measuring a leakage current. In this case, since as many leakage current measurement units 12 as necessary are mounted in the leakage current calculation device 1, or unnecessary leakage current measurement units 12 can be removed from the leakage current calculation device 1, it is possible to suppress the cost of the leakage current calculation device 1. Meanwhile, in order to realize the leakage current measurement unit 12 as such an extension unit, for example, a technique disclosed in Japanese Patent Laid-Open No. 2013-181813 may be used.
(Conclusion)
According to a first aspect of the disclosure, in order to solve the above problem, there is provided a leakage current calculation device including: a voltage measurement unit that measures at least one of line voltages in a three-phase AC type commercial power system to which one of three different phases is grounded; a ground voltage calculation unit that calculates a ground voltage between a neutral point and an earth of the commercial power system from the at least one line voltage measured by the voltage measurement unit; a leakage current measurement unit that measures a leakage current that flows between a load connected to the commercial power system and the earth; a frequency component extraction unit that extracts a frequency component that is synchronized with a system frequency of the commercial power system from the measured leakage current; a phase difference decision unit that decides a phase difference between the calculated ground voltage and the extracted frequency component; an insertion determination unit that determines whether an inverter is inserted between the commercial power system and the load; and a leakage current calculation unit that calculates a ground insulation resistance component leakage current of the system frequency portion that flows between the load and the earth through ground insulation resistance of the load on the basis of a calculation procedure corresponding to a result of determination of the insertion determination unit.
According to the above configuration, the leakage current calculation device determines whether the inverter is inserted between the commercial power system and the load. The leakage current calculation device further calculates the ground insulation resistance component leakage current of the system frequency portion that flows between the load and the earth through the ground insulation resistance of the load on the basis of a calculation procedure corresponding to a result of determination. Specifically, in a case where the inverter is not inserted, the leakage current calculation device calculates the ground insulation resistance component leakage current on the basis of the calculation procedure corresponding thereto. On the other hand, in a case where the inverter is inserted, the ground insulation resistance component leakage current is calculated on the basis of the calculation procedure corresponding thereto. Therefore, even in a case where the inverter is present in a facility or is not present, the presence of the leakage current calculation device is sufficient to calculate the ground insulation resistance component leakage current. In other words, a device for measuring the ground insulation resistance component leakage current is not required except the leakage current calculation device.
As described above, the leakage current calculation device according to the first aspect of the disclosure can precisely calculate the ground insulation resistance component leakage current regardless of the presence or absence of an inverter.
In the leakage current calculation device according to a second aspect of the disclosure in the first aspect, the insertion determination unit determines whether the inverter is inserted on the basis of input from the outside of the leakage current calculation device.
According to the above configuration, it is possible to accurately determine whether the inverter is inserted.
In the leakage current calculation device according to a third aspect of the disclosure in the first aspect, the insertion determination unit automatically determines whether the inverter is inserted.
According to the above configuration, it is possible to determine whether the inverter is inserted without a user spending much time or effort to use the leakage current calculation device.
In the leakage current calculation device according to a fourth aspect of the disclosure in the third aspect, the insertion determination unit determines whether the inverter is inserted on the basis of the leakage current measured at any given time and a change of the phase difference decided, and the frequency component extracted from the leakage current.
According to the above configuration, it is possible to accurately determine whether an inverter is inserted.
According to a fifth aspect of the disclosure, in order to solve the above problem, there is provided a leakage current calculation method including: a voltage measurement step of measuring at least one of line voltages in a three-phase AC type commercial power system to which one of three different phases is grounded; a ground voltage calculation step of calculating a ground voltage between a neutral point and an earth of the commercial power system from the measured at least one line voltage; a leakage current measurement step of measuring a leakage current that flows between a load connected to the commercial power system and the earth; a frequency component extraction step of extracting a frequency component that is synchronized with a system frequency of the commercial power system from the measured leakage current; a phase difference decision step of deciding a phase difference between the calculated ground voltage and the extracted frequency component; an insertion determination step of determining whether an inverter is inserted between the commercial power system and the load; and a leakage current calculation step of calculating a ground insulation resistance component leakage current of the system frequency portion that flows between the load and the earth through ground insulation resistance of the load on the basis of a calculation procedure corresponding to a result of determination in the insertion determination step.
According to the above configuration, it is possible to precisely calculate a ground insulation resistance component leakage current regardless of the presence or absence of an inverter.
The disclosure is not limited to each of embodiments described above, and can be changed variously in the scope shown in the claims. Embodiments obtained by appropriately combining technical means disclosed in each of the different embodiments are also included in the technical scope of the disclosure. A new technical feature can be formed by combining technical means disclosed in each of the embodiments.
11 Voltage measurement unit
12 Leakage current measurement unit
13 Ground voltage calculation unit
14 Frequency component extraction unit
15 Phase difference calculation unit (phase difference decision unit)
16 Insertion determination unit
17 Circle center calculation unit
18 Resistance component leakage current calculation unit (leakage current calculation unit)
19 Ground insulation resistance calculation unit
20 Insulation deterioration determination unit (insulation deterioration load specification unit, insulation deterioration determination unit)
21 Output unit
Number | Date | Country | Kind |
---|---|---|---|
2017-084357 | Apr 2017 | JP | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/JP2018/005804 | 2/19/2018 | WO | 00 |