This application claims priority to Chinese Patent Application No. 202211017639.1, filed Aug. 24, 2022, and all the benefits accruing therefrom under 35 U.S.C. § 119, the contents of which in its entirety are herein incorporated by reference.
The present invention relates to the field of elevator hoistway construction, and in particular to the device and method for building steel structure hoistways in the renovation of old residential areas by adding elevators thereto.
Nowadays, the demand for adding elevators in the renovation of old residential areas is increasing day by day. When adding elevators to a building, it is necessary to build an additional hoistway in the exterior zone of the building. For the common six-story residential area, some schemes propose to use two pre-built three-story steel structure hoistways to form a six-story hoistway. Such a scheme requires large mechanical equipment to enter the community. However, for most old communities, the roads are usually narrow, so it is difficult for large mechanical equipment to enter, and it is relatively difficult to transport and assemble the three-story steel structure hoistways.
The object of the present application is to solve or at least alleviate the problems existing in the prior art.
According to one aspect, a lifting device for building a steel structure hoistway is provided, which comprises: a lifting mechanism comprising: a bottom platform, a middle platform and a top platform, wherein the middle platform and the top platform each comprise telescopic brackets so as to be supported on cross beams of a constructed steel structure hoistway, the top platform is connected with the bottom platform by a plurality of columns, and the middle platform moves along the plurality of columns as driven by a driving device; and a crane mechanism arranged on the top platform of the lifting mechanism, the crane mechanism comprising a base and a crane on the base, wherein the base is arranged on the top platform and is rotatable relative to the top platform along a vertical axis, and a hanger frame of the crane is movable between a vertical orientation and an inclined orientation; wherein the lifting mechanism is configured to climb in the constructed steel structure hoistway, and the crane mechanism is configured to lift building materials, such as steel beams, steel columns, connecting pieces, etc., for used in building the steel structure hoistway to designed installation locations of the constructed steel structure hoistway, such as the top of the hoistway, for building higher levels of the hoistway.
Optionally, in an embodiment of the lifting device, the middle platform is movable between a first position close to the top platform and a second position close to the bottom platform. In the first position, the telescopic brackets of the middle platform and the top platform can be supported by the same pair of cross beams, wherein the ends of the telescopic bracket of the middle platform have hooks extending upward, and the ends of the telescopic bracket of the top platform have a straight configuration.
Optionally, in an embodiment of the lifting device, the plurality of columns comprise at least one screw rod and a plurality of guide columns, and the middle platform comprises a nut sleeved on the screw rod and bearings sleeved on the plurality of guide columns.
Optionally, in an embodiment of the lifting device, the driving device comprises a first motor and a first transmission mechanism. The first motor drives the at least one screw rod to rotate through the first transmission mechanism, and the first motor is arranged on the bottom platform or the top platform.
Optionally, in an embodiment of the lifting device, the bottom platform, the middle platform and the top platform are all substantially rectangular. The at least one screw rod is located in the middle of the bottom platform, the middle platform and the top platform, four guide columns are located at four corners of the bottom platform, the middle platform and the top platform, and the middle platform is sleeved on the respective guide columns through linear bearings.
Optionally, in an embodiment of the lifting device, the base of the crane mechanism is connected to the top surface of the top platform of the lifting mechanism through a rotary support bearing. A second motor is provided on the base. The second motor is meshed with the external teeth of the rotary support bearing through a second transmission mechanism, so as to drive the base of the crane mechanism to rotate, wherein the second transmission mechanism comprises a worm and gear mechanism and a pinion.
Optionally, in an embodiment of the lifting device, the crane comprises a hanger frame, wherein a first side of the hanger frame is pivotally connected to a first support on the base, a second side of the hanger frame is pivotally connected to a telescopic mechanism that is pivotally connected to a second support on the base, so that the hanger frame is movable between a vertical orientation and an inclined orientation at an inclined angle a of more than 15 degrees from the vertical direction, wherein the telescopic mechanism is a screw rod lifting device, and the crane can pass through the steel structure hoistway in the vertical orientation.
Optionally, in an embodiment of the lifting device, the base is further provided with a windlass, and the windlass is arranged on a platform above the second motor.
A method of building a steel structure hoistway is further provided, which comprises: building a fundamental steel structure hoistway on ground and placing a lifting device in the steel structure hoistway;
Optionally, the method comprises: extending the telescopic brackets of the middle platform of the lifting device to be supported by cross beams of the Nth story, and elevating the top platform to the N+1th story; lifting beams for construction of the steel structure hoistway to the N+1th story to build cross beams and longitudinal beams of the N+1th story; extending the telescopic brackets of the top platform to be supported by cross beams of the N+1th story, and retracting the telescopic brackets of the middle platform; bringing the middle platform to climb close to the top platform, and extending the telescopic brackets of the middle platform to be supported by the cross beams of the N+1th story; and retracting the telescopic brackets of the top platform, and bringing the top platform to climb to the N+2th story, where N can be any natural number.
Optionally, the method further comprises: orienting the crane of the crane mechanism vertically, lowering the lifting device to ground, detaching the crane and recovering the lifting device, after a steel structure hoistway of a desired height is constructed.
Optionally, the lifting device is the lifting device according to the various embodiments of the present invention.
The device and method according to the embodiments of the present invention realize the construction of elevator hoistways in absence of large mechanical equipment, and lower the requirements for environmental conditions (such as road, construction space, etc.) for building elevator hoistways.
With reference to the accompanying drawings, the disclosure of the present application will become easier to understand. Those skilled in the art would readily appreciate that these drawings are for the purpose of illustration, and are not intended to limit the protection scope of the present application. In addition, in the figures, similar numerals are used to denote similar components, where:
The present application provides a lifting device for building a steel structure hoistway, which is compact in structure and is suitable for building a steel structure hoistway when an elevator is installed in an old residential area with narrow roads. Specifically, referring to
In some embodiments, the plurality of columns 41, 42, 43, 44, 45 comprise at least one screw rod 45 and a plurality of guide columns 41, 42, 43, 44, and the middle platform 12 comprises a nut 122 sleeved on the screw rod 45 and bearings sleeved on the plurality of guide columns, such as the linear bearings 121. The driving device is a first motor 111, which drives the at least one screw rod 45 to rotate through a first transmission device 112, so that depending on the rotation direction of the first motor 111, the middle platform 12 will move along the plurality of columns toward the top platform 13 or the bottom platform 11. In the embodiment shown, the first motor 111 is arranged on the bottom platform 11. Alternatively, the first motor 111 can be arranged on the top platform 13, for example, at the bottom thereof. In an alternative embodiment, at least one screw rod 45 may be fixed, and the first motor 11 may be arranged on the middle platform 12 and drives the nut 122 to rotate. Although in the embodiment shown, the middle platform 12 moves along the plurality of columns by means of a screw rod and nut mechanism, other mechanical mechanisms may also be conceived to drive the middle platform 12 to move, such as a rack and pinion mechanism, a chain mechanism, a belt mechanism, a hydraulic mechanism, and the like.
In some embodiments, the bottom platform 11, the middle platform 12 and the top platform 13 are all substantially rectangular. For example, as shown in
Referring to
In some embodiments, the crane comprises a hanger frame, which may for example consist of a plurality of detachable sections 21, 22. The size of each of the sections 21, 22 is configured, for example, to be removable from the steel structure hoistway, so as to facilitate the recovery of the lifting device upon completion of the steel structure hoistway construction. The hanger frame may consist of three longitudinal columns 211, 212 and several transverse columns 213. As shown in
With continued reference to
According to another aspect of the present invention, a method of building a steel structure hoistway is further provided, which comprises the following steps: building a fundamental steel structure hoistway on ground and placing a lifting device in the steel structure hoistway; bringing the lifting device to climb until the top platform thereof is close to the top of the constructed steel structure hoistway; lifting, using a crane mechanism, building materials, such as steel beams, steel columns (i.e., steel I-beams), and using lifted beams to build higher levels of the steel structure hoistway; and repeating the steps of bringing the lifting device to climb and building higher levels of the steel structure hoistway until a steel structure hoistway of a desired height is constructed.
In some embodiments, as shown in
In some embodiments, after a steel structure hoistway of a desired height is constructed, the crane of the crane mechanism is oriented vertically, the lifting device is lowered to ground, the crane is detached, and the lifting device is recovered. In some embodiments, the lifting device is the lifting device described in detail herein. Alternatively, the structure of the lifting device may differ from what is shown. In addition, it is worth noting that the stories for the cross beams in the present application, such as the Nth story, the N+1th story and the N+2th story, may not be aligned with the original stories of the building. For example, the story height thereof may be smaller than the original story height of the building, e.g., it can be between 2 and 3 meters. In addition, the length of the hanger frame can be less than the height of two stories, for example, around 4 meters, so that the detachable sections 21, 22 of the hanger frame are around 2 meters long.
The specific embodiments of the present application described above are merely intended to describe the principles of the present application more clearly, wherein various components are clearly shown or described to facilitate the understanding of the principles of the present invention. Those skilled in the art may, without departing from the scope of the present application, make various modifications or changes to the present application. Therefore, it should be understood that these modifications or changes should be included within the scope of patent protection of the present application.
Number | Date | Country | Kind |
---|---|---|---|
202211017639.1 | Aug 2022 | CN | national |
Number | Name | Date | Kind |
---|---|---|---|
1023507 | Davison | Apr 1912 | A |
3485384 | Yu | Dec 1969 | A |
3539053 | Hefferin | Nov 1970 | A |
3998029 | James | Dec 1976 | A |
4183440 | Wilkinson | Jan 1980 | A |
4298128 | Gattu | Nov 1981 | A |
9169107 | Wilts | Oct 2015 | B2 |
11724919 | Kalanj | Aug 2023 | B2 |
20020134745 | Jurimae | Sep 2002 | A1 |
20130087679 | Mooney | Apr 2013 | A1 |
20150107186 | Wilts | Apr 2015 | A1 |
20210292134 | Kalanj | Sep 2021 | A1 |
20220185631 | Lanz et al. | Jun 2022 | A1 |
Number | Date | Country |
---|---|---|
112482733 | Jun 2019 | CN |
208996441 | Jun 2019 | CN |
Entry |
---|
European Search Report for Application No. 22207904.8, dated Sep. 7, 2023, 6 Pages. |
Number | Date | Country | |
---|---|---|---|
20240067503 A1 | Feb 2024 | US |