Claims
- 1. A management system for a power station installation having a number of power station blocks, comprising:
- a computer unit determining reference variables for at least one power station block by using a genetic algorithm;
- an optimization module connected to said computer unit; and
- a number of neural networks each connected to said optimization module and each assigned to a respective power station block.
- 2. The management system according to claim 1, wherein said computer unit determines a set point for a proportion of power for an overall nominal load to be covered, as the reference variable for each power station block for a predefinable time interval.
- 3. The management system according to claim 1, wherein said optimization module includes a coarse optimization stage connected to said neural networks and a fine optimization stage connected to said coarse optimization stage.
- 4. The management system according to claim 3, wherein said fine optimization stage carries out an analytical process simulation.
- 5. The management system according to claim 1, including another neural network connected to said computer unit for generating starting values for the genetic algorithm.
Priority Claims (1)
Number |
Date |
Country |
Kind |
44 23 897.5 |
Jul 1994 |
DEX |
|
CROSS-REFERENCE TO RELATED APPLICATION
This application is a Continuation of International Application Ser. No. PCT/DE95/00875, filed Jul. 7, 1995.
US Referenced Citations (1)
Number |
Name |
Date |
Kind |
5524175 |
Sato et al. |
Jun 1996 |
|
Foreign Referenced Citations (1)
Number |
Date |
Country |
4200260A1 |
Jul 1993 |
DEX |
Non-Patent Literature Citations (1)
Entry |
Japanese Patent Abstract No. 5143757 (Toru), dated Jun. 11, 1993. |