The present invention relates to methods for projecting forthcoming power outage at one or more mobile radio base sites and methods for mitigating the effects of the power outage.
One type of radio communications system is a cellular communications system. In a cellular communications system, the area over which service is provided is divided into a number of smaller areas called cells. Typically each cell is served from a base station which has an antenna or antennas for transmission to and reception from a user station, normally a mobile station and a backhaul connection for routing of communications to and from a fixed base site controller for onward transmission to user terminals or other communications networks. Presently established cellular radio communications systems include Global System for Mobile communications (GSM), Code Division Multiple Access (CDMA), Worldwide Interoperability for Microwave Access (WiMAX), and also the Universal Mobile Telecommunication System (UMTS).
Such base stations and their associated equipment require electrical power to operate. Typically this power has been provided by connection to an electrical grid, or in cases where this is not available through connection to a standalone diesel generator. More recently power generated from renewable means such as wind turbines or photovoltaic (PV) arrays has been used as an alternative or as a supplement to diesel generators for sites without a grid connection. Inclusion of such renewable sources in the power supply mix is attractive because it can reduce or avoid the operational expenditure associated with refueling diesel generators.
By the distributed nature of radio communications systems it is likely that base stations will be operating under differing environmental conditions, will use a variety of power sources (grid, diesel, renewable and hybrid) and may be served by a range of power service providers.
Power supply solutions for mobile radio equipment are distinctive in that they must deliver the required power to the telecommunications equipment with high availability so that the mobile radio network remains operational. Another distinctive feature of mobile radio equipment is that the power drawn by the equipment may be variable over the course of time, with power drawn being dependent for example on the varying volume of telecommunications traffic being carried. In addition the power generated by renewable energy sources will also be variable being dependent on meteorological conditions. Operators of mobile radio equipment and the associated power supply network need to be provided with information to inform them of the risk that mobile radio equipment may need to be switched off over some future period due to a lack of power. An operator could use such information, for example, to expedite the supply of diesel to a site or to actively manage the power drawn by the radio equipment so that radio network capacity/coverage can be provided for longer. Hence there is a need for a network power management solution which integrates knowledge of the projected power which will be generated by the various power sources and knowledge of expected power drawn by the mobile radio equipment in order to compute metrics for the expected time to outage of the Base Transceiver Station (BTS) and/or the backhaul equipment. Such a network power management solution could use this information to mitigate the, effects of such a projected outage.
The existing state of the art solutions do not address these problems. Mechanisms for notifying central management systems of power supply conditions are known, as described for example in EP 1 330 009. Likewise mechanisms for reducing the power consumption of equipment at times of low traffic demand are also known, see for example U.S. Pat. Nos. 6,360,106, 6,584,330. However, these solutions address neither the problem of projecting the time to power outage nor the actions that should be taken given this knowledge.
The present invention addresses some or all of the above disadvantages. According to one aspect of the present invention, a method is provided for: projecting the likelihood that power outage will occur at a mobile radio base site over some future interval, and in the event that power outage is expected, for, invoking actions to prolong the period for which the mobile radio base station provides service.
The present invention is applicable to, but not limited to, radio communication systems such as the Global System for Mobile communications (GSM), Code Division Multiple Access (CDMA), Worldwide Interoperability for Microwave Access (WiMAX), Universal Mobile Telecommunication System (UMTS) and Long Term Evolution (LTE). The present invention is also applicable to, but not limited to, mobile radio base stations powered by one or more types of power supply including wind turbine, Photo-voltaic panel, generator, grid connection, battery and fuel cell.
Further features of the invention are as claimed in the dependent claims. Additional specific advantages are apparent from the following description and figures which relate to exemplary embodiments of the present invention. Other systems, methods, features and advantages of the invention will be or will become apparent to one with skill in the art upon examination of the following figures and detailed description. It is intended that all such additional systems, methods, features and advantages be included within this description, be within the scope of the invention, and be protected by the accompanying claims.
The components in the figures are not necessarily to scale, emphasis instead being placed upon illustrating the principles of the invention. In the figures, like reference numerals designate corresponding parts throughout the different views.
It should be noted that the functionality shown implemented within the OSS (110) in
It is also foreseen that the OSS operative may choose to implement methods for reducing base station power consumption, discussed elsewhere within this invention, even in the absence of projected forthcoming power outage, for example in order to reduce fuel costs. The OSS operative could signal this requirement through the use of the OSS terminal (170).
Another method by which the number of users may be reduced in a cell is to simply refuse admission onto the cell to users with low priority and/or with low revenue generating capability. This priority information is provided during the admission control process using, for example Allocation/Retention Priority (ARP) information which is provided, for example by the Home Location Register, The ARP information may also be used to select which calls should be dropped when the need to switch off a base station card is urgent. In a similar vein, in some base station designs it may also be the case that it is possible to reduce the number of circuit boards in use by reducing the data rates available to packet calls or to voice calls.
There are a number of methods and techniques for computing the likelihood that power outage will occur in some future time interval. One set of methods, an example of which is illustrated in
The power which is expected to be drawn by the loads over some future period may be derived using historical data gathered under similar conditions to the future period under consideration. Where similar conditions in this regard could include but not be limited to time of day, day of week and day of the year. Such historical values may also be optionally modified to account for any changes in average traffic load between the considered future period and the time of the historical record, brought about for example by changes in subscriber numbers, changes in network usage or changes in tariffs.
The projection of power to be generated by renewable energy sources over some future period may be projected using meteorological information obtained from a 3rd party server which supplies regional weather forecast data. One approach would be to use a table which records the amount of power which is generated under each meteorological condition. For example the table might store the amount of usable power generated by the wind turbine over a range of wind speeds and likewise it might store the amount of power generated by Photo-Voltaic panels over a range of solar insolation values. In this way the projected future meteorological conditions (wind speed, solar insolation) may be used as an index into the table to access the corresponding projection for the power which will be generated under the given meteorological condition. The table contents may be obtained through computation or they may be obtained from historical correlation of measurements of given meteorological conditions and the corresponding measurements of power generated under those conditions. The accuracy of the projection of the future meteorological conditions could be enhanced by making use of measurements of meteorological conditions which are made at the base site. For example, the correlation between historical regional weather forecasts and historical weather measurements made at the site could be used to determine offsets that should be applied to the regional weather forecasts, prior to using the meteorological data in the table look up. The computation of power available may, in addition to considering power generated by renewable energy sources, additionally take into account any energy which is already stored in the battery, any energy which may be produced by a generator given the available fuel supplies and any energy that may be available from the grid.
In the example algorithm illustrated in
The time at which load reduction actions are taken may be chosen to coincide with periods when the number of subscribers on the system is typically low and/or when the opportunity for revenue generation is poor. In this way any detrimental effects resulting from the load management actions will affect the lowest number of subscribers and/or will have the minimal impact on profits.
While various embodiments of the invention have been described, it will be apparent to those of ordinary skill in the art that many more embodiments and implementations are possible that are within the scope of this invention. In addition, the various features, elements, and embodiments described herein may be claimed or combined in any combination or arrangement.
Number | Date | Country | Kind |
---|---|---|---|
0921052.7 | Dec 2010 | GB | national |
This application is a continuation of and claims priority and the benefit of PCT Application No. PCT/GB2010/002198 titled Managing Projected Power Outage at Mobile Radio Base Sites, filed Nov. 30, 2010, which claims priority to and the benefit of Great Britain Application No. 0921052.7 filed on Dec. 1, 2009.
Number | Name | Date | Kind |
---|---|---|---|
20020075906 | Cole et al. | Jun 2002 | A1 |
20060182262 | Goldman et al. | Aug 2006 | A1 |
20090131102 | Takahashi et al. | May 2009 | A1 |
20090154384 | Todd et al. | Jun 2009 | A1 |
20100100758 | Houmaidi | Apr 2010 | A1 |
20100286841 | Subbloie | Nov 2010 | A1 |
20110140911 | Pant et al. | Jun 2011 | A1 |
Number | Date | Country |
---|---|---|
2 083 170 | Jul 2009 | EP |
2 271 172 | Jan 2011 | EP |
WO 9422239 | Sep 1994 | WO |
WO 03098387 | Nov 2003 | WO |
WO 2005060287 | Jun 2005 | WO |
WO 2009078764 | Jun 2009 | WO |
WO 2009141651 | Nov 2009 | WO |
WO 2010006308 | Jan 2010 | WO |
Number | Date | Country | |
---|---|---|---|
20120302295 A1 | Nov 2012 | US |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/GB2010/002198 | Nov 2010 | US |
Child | 13485577 | US |