The invention relates to a method of wear-free determination of the overall length of a jib of a crane as well as an apparatus for carrying out this method.
For the operation of a crane, in particular with regard to safety, it is extraordinarily important to know the overall length of a single-part jib or also the overall length of a telescopic jib. The load at which the jib can be operated is dependent upon both the overall length and also the jib angle and optionally further parameters.
For determination of the length of the jib, in particular in the case of telescopic jibs with a plurality of jib elements, it is already known to determine the current overall length of the jib by the length of a cable that is entrained when the jib is retracted or extended. This cable is wound or unwound on a drum, wherein the number of turns is a measure of the wound or unwound length of cable and thus indirectly is also a measure of the overall length of the jib. Although such cable-guided systems have proved successful in practice, they have the disadvantage that during the service life of the crane they are subject to wear and moreover they involve additional weight. If it is to be possible to determine the jib length with sufficient precision, especially in the case of greater jib lengths, it is necessary to implement additional measures (for example in order to prevent sagging of the cable).
A wear-free method of determination of the overall length of a jib of a crane is already known from DE 10 2006 025 002 [U.S. Pat. No. 8,181,798]. In this connection the jib length is determined by wireless technology, in particular by RFID technology. This system does indeed overcome the disadvantages of the cable-guided system, specifically the precision is improved, the weight is reduced and also wear is eliminated. However, the wireless-based system has the disadvantage that it is not interference-free to safety-critical standards without further additional and thus costly provisions, since extraneous interference signals (for example by mobile wireless, radiotelephony and the like) can interfere with the signal transmission. Thus for the safety-related operation of a crane it is not ensured that the jib length can be determined reliably by such a system.
Therefore the object of the invention is to provide a method of wear-free determination of the overall length of a jib of a crane as well as apparatus for carrying out such a method by which the above-described disadvantages are effectively avoided.
This object is in that a signal is fed in at a first point on the jib and is detected at a second point on the jib, and the overall length is determined from the time required for the signal to pass from the first point to the second point. This means that elapsed-time measurement is utilized in order to determine the overall length of the jib, in particular a single-part jib or a plurality of jib elements of a telescopic jib. This elapsed-time measurement is largely interference-free and wear-free and significantly reduces the weight. Moreover it is merely necessary to determine the elapsed-time once for a specific type of jib in order then to know the elapsed-time for jibs of the same type, regardless of whether they are single-part jibs or telescopic jibs, and to determine the jib length therefrom during operation after setting up of the crane.
Whereas a telescopic jib is formed of a plurality of jib elements that are movable relative to one another, in an individual jib element the overall length can vary, depending upon which parts are attached to the jib. As a representative example it may be mentioned here that a latticed mast point is attached to a jib, wherein the length of the attached latticed mast element is also relevant for the overall length of the jib. In this respect the term “jib” is also understood to be such a jib that is not only formed as a single part, but can also be assembled from a plurality of parts. Here too the method offers the possibility of determining the overall length as a function of the assembled parts of the jib (setup state). The method is particularly flexible when the complete jib has been assembled from a plurality of parts and then, before the crane is used, an elapsed-time measurement is carried out in order to ascertain the overall length. This ascertained overall length is then included in the further calculation, in particular a load torque calculation. A further advantage of this elapsed-time measurement can be seen in the fact that when the setup state of the crane, in particular the composition of the jib, has been changed during operation of the crane, the new overall length that results can be ascertained and compared with the previously ascertained overall length. In the event of variations this means that the new overall length has changed, which can be included in the further load torque calculation and this new overall length can be taken into account. Therefore it is a further advantage that the method of wear-free determination of the overall length of the jib is repeated not only before the use of the crane, but also during the operating period. In order to increase the operational security of the crane this repetition advantageously takes place every time when the setup state has changed or alternatively and in addition thereto at specific time intervals.
Further configurations of the method according to the invention for wear-free determination of the overall length of the jib are set out in the subordinate claims and are explained in greater detail in this connection with reference to the figures in which:
In
An indirect determination of the overall length GL of the jib 1 is illustrated in
However, when the telescopic jib is in use as shown in
In order to carry out the method described above, apparatus is provided for wear-free determination of an overall length of a jib of a crane, and the apparatus has means for feeding in a signal at first points 2 and 5 on the jib sections 1 and 4 and means for detecting at second points 3 and 6 on the jib sections 1 and 4. Further means are provided by which the overall length GL is determined from the time required for the signal to pass from the first point 2, 5 to the second point 3, 6.
Number | Date | Country | Kind |
---|---|---|---|
10 2012 208 635.8 | May 2012 | DE | national |
This application is the US-national stage of PCT application PCT/EP2013/059381 filed 6 May 2013 and claiming the priority of German patent application 102012208635.8 itself filed 23 May 2012.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/EP2013/059381 | 5/6/2013 | WO | 00 |