Metal curb installation system and method

Information

  • Patent Grant
  • 6695525
  • Patent Number
    6,695,525
  • Date Filed
    Monday, January 22, 2001
    24 years ago
  • Date Issued
    Tuesday, February 24, 2004
    21 years ago
  • Inventors
  • Examiners
    • Will; Thomas B.
    • Florio; Kristine
    Agents
    • Gerber; Eliot
Abstract
A straight steel curb for the steel curb faced concrete curb of a roadway has a vertical sidewall and a horizontal portion. Two sheet metal or plastic benches, which lie on the floor of the trench, are aligned relative to a string line. Each bench has a bracket which supports a bottom edge of the steel curb at its two ends, to position the steel curb. The front plate and back plate of a bench are welded to the bottom plate by a weak weld which shears under the pressure of the expanding or contracting concrete or has a pleated base which contracts and expands. The bench has front and back flanges which, respectively, hold front and back concrete forms.
Description




FIELD OF THE INVENTION




The present invention relates to sidewalk and road construction and more particularly to systems and methods for installing concrete curb, straight and curved, faced with steel to protect the concrete from damage due to cars, trucks and snow plows.




BACKGROUND OF THE INVENTION




At the present time, in cities and in metropolitan areas, a sidewalk is located at a side of a road, e.g., street or roadway. The sidewalk is elevated typically 7″ above the road (the reveal), and a curb is used to separate the road from the sidewalk. The curb has a nearly vertical face which ranges from 18′ to 27″ depending on the thickness of the road and the reveal of the curb. The bottom of the curb is buried 11″ to 20″ below the road, and has a nearly horizontal portion which lines up with the sidewalk. There is a ½″×6½″×18-27″ premolded bituminous expansion joint filler (EJF) between curb sections and a ¼″ expansion joint between the curb and sidewalk for expansion and contraction. When the curb and sidewalk are poured simultaneously, a ½″ thick expansion joint (EJF)is generally used between the curb and sidewalk.




Plain concrete is most often used for such curbs. In high traffic areas, such as busy city streets, the concrete is rapidly chipped, cracked and broken, so a hard stone, such as granite, is often used. However, the costs of cutting, transporting and installing elongated granite curb members is high and may be prohibitive.




Steel has been used for many years to face concrete curb since it is strong and can resist damage caused by the impact of the truck wheels and snow plows when installed along streets having heavy vehicle traffic. Steel faced concrete curb is less costly than granite but as good as, or superior, in resisting damage. However, steel curb-facing (steel curb) is heavy and, because it is heavy and clumsy to handle, it is costly to install. A typical steel curb is 20 feet long, asymmetrical, and weighs about 340 pounds. It usually requires a four-man crew to lift and install a steel curb or two men with a lifting machine. The curb, during its installation, must be exactly aligned with a string guidance line. The surfaces of adjacent steel curbs must align smoothly where they join each other. If one steel curb extends beyond or above the next, it will present a sharp edge which can cut vehicle tires and present a tripping hazard to pedestrians.




To rebuild an existing road, generally the curb to be replaced is removed. A trench, 11 to 18 inches deep and 18 to 24 inches wide, is then dug. Using surveyor instruments, including a surveyor's level, a continuous guidance string is strung as a guide for the curbs. The string is supported by long steel (primary) stakes, for example, ¾-inch diameter and 36-inch long. The primary stakes are about 50 feet apart and driven into the earth at the bottom of the trench, generally along the back of the future curb. The string is the guide for the line (sidewise location) and grade (elevation) of the new curb. The curb may be straight and may be curved.




The next steps in the conventional method is to drive other stakes 1½″ behind the string line, about 5 feet apart, into the earth at the bottom of the trench. These stakes hold a back (wood) form in its vertical position such that the face of the wood is on the line of the guidance string. The wood form is usually made, for example, from 2×8 (inch) and 2×12 (inch) lumber held together to form a nominal 2″×20″(actually 1½″×19″). The forms (front and back) are the mold for containing the concrete slurry which is later poured into the form. The steel curb is placed in the space between the form, against the front form.




The steel curb has a nearly vertical face, which may be about 11″. Two stacks of bricks are formed, spaced, for example 19 feet apart, on the bottom of the trench. The stacks of brick range in height, typically, from 10″ high for an 18″ deep curb to 19″-27″ for other curbs. The steel curb is lifted into the trench and set on the stacks of bricks. The curb has a series of protruding steel studs for anchoring the steel curb to the concrete curb. The stacks of brick are shifted so they are directly under the end studs (typically 3″ up and 9″ from each end) so they are in the position to support the curb. The stacks are inherently unstable and often topple when the curb is placed upon them. But, even if they were stable, because of the high center of gravity and a asymmetrical shape of the steel curb, the curb will not stand by itself on a stack of brick. To compensate for this when the steel curb is correctly positioned relative to the string, and while two men balance the curb, the wooden forms are placed behind and in front of the steel curb and clamped.




Each steel curb must be lifted, positioned and adjusted so that it is at the correct height relative to the guidance string. Usually wooden shims are placed on top of the stacks of bricks and beneath the steel stud for a finer adjustment. However, the conventional method described for the placement and adjustment of the steel curbs is slow, inexact and labor-intensive. The steel curb must be steadied by two men, one at each end, while 2 or 3 other men place the front and back forms and clamp them together. Wood spacers, 36″ apart, are positioned between the steel curbs and wood forms to keep the steel curb and wood forms from collapsing inwardly. This conventional method is expensive because of the time required, the number of men in the crew, their skill and their relatively high wages and fringe benefits.




SUMMARY OF THE INVENTION




In accordance with the present invention, to lay a line of straight steel curbs, a trench is dug and a guidance string line is positioned in the trench.




In the primary method, in accordance with the present invention, a series of sheet metal or plastic benches, one for each piece (section) of steel curb, is provided to hold and position the straight steel curb. The benches are aligned relative to the string line. The benches are raised, or lowered, by placing or removing dirt beneath their bottom plates, until the benches are at the correct elevation. Each bench has two front plates at ⅜″ apart, for expansion, each bracket having a support shelf to position and support the bottom edge of the steel curb. The benches are formed of sheet metal or plastic and are left in the trench after the concrete slurry has been poured. One bench supports the leading end of the previous steel curb and the trailing end of the next steel curb which is to be set. At that time, or after a series of straight curbs are positioned in the trench, wooden forms are removably placed on the benches. A wood form is positioned at the front (the side toward the road) against the lower 2-3″ of the face of the curb. A wood form is positioned at the back, with the form extending to the height of the top lip portion (curve-dover portion) of the curb. The concrete slurry is then poured between the form and allowed to harden. The wood forms are then removed, the trench partially filled with compacted earth and crushed stone, and the road and sidewalk are laid down.




In an alternative method, especially useful for setting curved curbs, two benches are tied to the curb, one at the leading end and one at the center. The bench and curb are then lifted by the work crew and placed in the trench in the curb's line and grade. The trailing end of the curb is placed in the bracket of a previously positioned bench.




A corner steel curb, used at street corners and generally 85° to 95°, is positioned in a different way. In the first step, the corner curb is lowered by the work crew into the trench and positioned on wooden blocks which lay on the floor of the trench. In the second step the tangents of the corner steel curb are aligned with intersecting streets. In the third step, metal stakes are placed in support plates welded to the curb and are driven into the ground, at the bottom of a rounded trench. The stakes are vertical. The support plates are welded to the curb. The support plate has a bushing having a bolt and the bolt is tightened on the stake to hold the curb to the desired elevation (vertical position). A series of short metal squares have been welded to the back of the curb surface towards the sidewalk in the curb fabrication shop. The squares are used in conjunction with curb ties and a series of short metal tracks. Curb ties are connected, at their front end, to the squares. At their back end, the curb ties are connected to a metal track which had been fastened, generally in the curb fabricator's shop, fastened to a 2½″×8″ or 18″ continuous expansion joint which separates the back of the curb from the sidewalk. The curb ties make the expansion joint, which is flexible, follow the curvature of the steel curb, and hold it in position to resist the pressure of the concrete slurry. The curb and sidewalk are poured together.











BRIEF DESCRIPTION OF THE DRAWINGS




In the drawings:





FIG. 1A

is an end view of a conventional straight metal curb;





FIG. 1B

is a front elevational view of the front face of the curb of

FIG. 1A

;





FIG. 2

is a front elevational view of the front face of two full curbs, of the type of

FIG. 1

, one in a trench and one about to be placed in a trench;





FIG. 3

is an end view of the bench of the present invention;





FIG. 4

is a plan view (top view) of the bench of

FIG. 3

;





FIG. 5

is a back elevational view of the bench of

FIG. 3

;





FIG. 6

is a perspective view of a tubular steel clamp;





FIG. 7

is an end view of the bench of

FIG. 1

in a trench;





FIG. 8

is a sectional view of a straight curb within a curb form and having a curb form bottom tie;





FIG. 9

is a top plan view of a curb form bottom tie;





FIG. 10

is an end view of a curved steel curb lying on its face;





FIG. 11

is an end view of the curb of

FIG. 10

lying on its face and tied to a bench;





FIG. 12

is an end view of the curb of

FIG. 10

tied to a bench and positioned at its final attitude, its face nearly vertical;





FIG. 13

is an end view of the curb of

FIG. 10

tied to a bench and positioned at its final attitude, its face nearly vertical in a trench;





FIG. 14

is an end view of a corner curb, with curb support/standoff bracket and expansion joint filler in a trench;





FIG. 15A

is a top view of a corner curb of

FIG. 14

before the turnbuckles used for modifying the shape of the corner have been removed and before the stakes that hold the shape have been installed;





FIG. 15B

is a top view, enlarged, of a curb support/standoff bracket used with the corner curb of

FIG. 15A

;





FIG. 16

is a side view of an expansion joint filler tie used with the corner curb of

FIG. 14

;





FIG. 17

is a top view (enlarged) of the curb support/standoff bracket used on the steel corner curb;





FIG. 18

is a side view of one system for installing a steel curb in a narrow trench which is often used when only the curb and sidewalk are being replaced but not the road;





FIG. 19

is a front view of an alternative system for installing a steel curb in a narrow trench;





FIG. 20

is a side view of the system of

FIG. 19

;





FIG. 21

is an enlarged top view of a bracket which is welded to a steel curb;





FIGS. 22 and 23

are side plan views of form holders for a concrete curb positioned within a trench.











DETAILED DESCRIPTION OF THE INVENTION




The present invention, in its first embodiment, uses a conventional straight steel curb to form a steel faced concrete curb. As shown in

FIGS. 1A and 1B

, the steel curb


1


consists of a nearly vertical plate portion


2


whose outer face


3


is exposed and extends from approximately 4″ below the road to the level of the sidewalk. An integral lip portion


4


has a curved edge


5


and is positioned so that its top surface


6


is at the level of the sidewalk.




A series of concrete stud anchors


7


(studs) are welded to the back face


8


of the curb


1


, for example, spaced 1-foot apart, and act to anchor the curb in the concrete. In addition, two bench studs


7


A, near the opposite ends of the curb


1


, are used in conjunction with loose wedge to balance and set the verticality of the curb, see FIG.


7


.




The metal or plastic curb bench


9


of the present invention is shown in

FIGS. 3-5

. It comprises a bottom sheet metal or plastic plate


10


having a length “L


1


”, two front sheet metal plates


11


,


12


having a height “H


1


”, two back sheet metal plates


13


,


14


having a height “H


2


”. The plates are welded or injected (if plastic) together to form a unitary structure. The front plates


11


,


12


are preferably not plumb in respect to the bottom plate


10


but are inclined at an 84° angle or 6° out of plumb. Front plates


11


,


12


and support brackets


25


and


25


A and the back plates


13


,


14


are each separated by gaps


19


,


20


; preferably the gaps are each about ⅜″ for the front plates and ½″ for the back plates and support brackets.




The typical dimensions for 18″ curbs are: L


1


, 11{fraction (27/32)} inches; L


2


, 8{fraction (23/32)} inches; and the sheet metal is 10 GA.




It will be understood that these dimensions, as well as the other preferred dimensions set forth, are only by way of example and may vary depending on the thickness of the roadway and the curb reveal and depending on local conditions and construction practices.




The front plates


12


and


13


carry a sheet metal bracket member


25


on its interior face. The support bracket member


25


forms a shelf


26


which supports the bottom edge of one end of the steel curb


1


.




A front flange


30


(vertical protrusion) is integral with the bottom plate and a back flange


31


(vertical protrusion) is also integral with the bottom plate


10


. The flanges


30


,


31


are used to hold the bottom edges of the front and back wood forms, respectively, in position. These flanges are used instead of the conventional method of holding the bottoms of the forms in position against the hydrostatic force of the concrete slurry by shoveling a pile of earth against the outside faces of the forms. Generally the earth will be removed, after the concrete has hardened, which is labor-intensive. The flanges


30


-


31


are preferably 1¾ inches in height.




The front plate


12


and back plate


13


are welded to the bottom plate


10


by two pairs each of relatively weak welds


32


,


33


, respectively. These welds are adapted to break due to force of the expansion and contraction of concrete and steel faced curb resulting from changes in length due to temperature changes. Alternately, the bottom plate may be formed with pleats to act in an accordion-like manner to provide the expansion.




As shown in

FIG. 2

, at the start of the line of curbs, the first bench (not shown) of

FIG. 3

is positioned without the curb being attached to it. The bottom plate


10


of the bench is positioned on the ground


28


of the trench a distance below the taut guidance string


50


(string line) equal to the depth of the curb, for example 18″ to 27″. If the bench is too high relative to the string line, a little earth is removed from beneath the bottom plate


10


or, after it has been set, the steel curb can be hammered down, causing the bench to sink slightly into the previously compacted earth. If the bench is too low, some earth, or a shim, is put under the bottom plate


10


. As described in detail below, the trailing end of the steel curb is placed by the work crew on the shelf


25


of the bracket member


26


. Since the bench was already correctly positioned in relation to the guidance string line


50


, when the leading end of the preceding curb was placed, the trailing end of the next steel curb is correctly positioned as soon as it is lowered into the shelf


26


A bracket member


25


. The crew does not need to re-position or measure that the trailing end of the curb, as that end is correctly positioned as to line and elevation. Using a loose wedge between the trailing end bench stud


7


A and bench batter plate


16


B, the face of the curb is battered to match the proximate curb 1:10 or 6° out of plumb.




A ½-inch gap is left between the ends of the two proximate steel curbs and that gap is filled with a piece of expansion joint.




After a number of steel curbs are in place, supported and aligned by the benches, the forms will be laid on the bench bottom plate


10


between the bottom plate flanges and the front and back plate. The forms are preferably lumber boards, although alternatively they may be sheet metal or plywood.




A form clamp of tubular steel


81


(tubular curb clamps) is used in place of the conventionally used inverted U bent generally from ¾″ round or square steel bar. The clamp


81


comprises a first member


82


, which is positioned behind the back form, a front member


83


positioned in front of the front face of the front form, and a connecting top member


81


, see FIG.


6


B.




As shown in

FIG. 7

, the back form


29


is made of two pieces of lumber spliced longitudinally, as in the conventional method. The back form


29


is removably attached to two benches


9


and


39


supporting the two ends of the steel curb


27


, see FIG.


2


. The back form


29


is at least the full height to the top of the curb


27


, preferably 21 inches high, when the full height H


3


is 21 inches.




A front form


34


, preferably is a single piece of lumber removably attached by curb form clamps to the front faces of the two benches


9


,


39


lapping over the steel curb a minimum of 2″.




Preferably, in addition to the two benches at the opposite ends of a steel curb, the front form and back form are prevented from bowing at the bottom due to the hydrostatic pressure of the concrete slurry by “Curb Form Bottom Ties” (CFBT) and at the top by tubular curb clamps. Typically the CFBTs are placed on the trench floor, at 5 feet spacing, between the two benches and the top tubular clamps are lined up over the CFBT.




As shown in

FIGS. 8 and 9

, the CFBT


40


consists of a bottom


41


, a front flange


42


(vertical protrusion) and a back flange


43


. The flanges


42


,


43


are preferably 1¾ inches high (H


4


). The three CFBTs are placed on the trench floor preferably so that their back flange is 3″ to 4″ behind the guidance string i.e. further from the road than the guidance string. Then the back form is placed on the bench bottom plate between the back plate


14


and the flange


31


. Next, all 3 CFBTs are moved until their flanges touch the back form. Then the back finger


45


of each is raised (field bend up), for example, by the claw of a claw hammer. That back finger


45


holds the CFBT from being dislocated by the placement of the front form. The bottom edge of the front form


34


is then placed between the flange


42


and the front finger


47


, which has previously been bent upwards in the shop. The bottom edge of the back form


31


is then placed on the bench bottom plate against flange


43


.




In operation, in laying curved steel faced concrete curbs, as shown in

FIGS. 10-13

, the curb


27


A is first laid on the ground on its front face, see FIG.


10


. If this is the first curb to be installed in a curved trench, one bench is wired to one end (trailing end)of curb, one to the center, and another bench to the opposite (leading) end. Generally, however, one bench will already be in the trench, supporting the leading end of the straight steel curb that the curved steel curb will follow in which case a curb, only the center and leading end benches will be wired to the first curved curb. Illustrated in

FIG. 11

is a bench wired to the leading end of a curved steel curb. As shown in

FIG. 11

, the curb bench


9


A is on its side with the curb in its bracket


25


. The steel curb and bench


9


A are then tied together, for example, using metal baling wire


46


. A cast iron wedge


44


is hammered in to tighten the wire


46


to keep the bench from falling off. As shown in

FIG. 12

, the curb and the bench


9


, which are attached by the wire


46


, are positioned vertically and lifted. As shown in

FIGS. 12 and 13

, the curb and its attached benches


9


are uprighted and then lowered into the curved trench in their vertical position, usually with a crew of 4 men. The trailing end of the curb (unless it is the first curb of a run) is placed in bracket


25


of the bench supporting the leading end of the previous curb. That end is at the correct line, grade (height) and batter (inclination), as that bench had previously been correctly adjusted relative to the string line


50


and its proximate curb. The bench


9


A is then placed on the line and adjusted as to its correct height, by placing or removing dirt under its bottom plate. After an entire run of curved curb and one or two lengths of straight curb following it are in the trench, and generally in position, the benches are moved in or out as necessary so the curb has a smooth and pleasant looking curvature. Next the expansion joint filler located at the end of each curb is placed. Then the bailing wire securing wedge is cut. A set of overlapping splice plates one over the face and the other over the back of both proximate steel curbs are drawn together by a ½×12″ bolt passing through the ½″ expansion gap between the proximate curbs. The bolt and the exterior splice plate are removed after the concrete slurry hardens. The interior splice plate remains. The expansion joint filler is cut away to clear the interior plate. Wedge


44


is placed at the trailing end of each curb and used to make its batter match the batter of the proximate curb.




The curved curb is now in the trench and is correctly aligned. Concrete forms for curved steel faced concrete curb can be of 1½″×12″×18″ or 8″ hinged boards ¼″ thick plywood, masonite or sheet metal. The forms are placed 6½″ from the back of the steel curb, staked and clamped. After an entire run of curbs are correctly positioned on their benches in the curb, with their concrete forms in place, they are secured and sprayed with form oil, which is also done with straight curb. Then the concrete slurry is poured into the molds and allowed to dry, i.e., for one day or less. The forms, on their inner faces, have a removal coating of form oil which prevents the concrete from sticking to the boards, plywood, masonite or sheet metal of the forms.




After removal of the forms, the curved trench is partly filled with a mixture of crushed stone (base), and compacted earth and the sidewalk and road pavement are then laid in place. For example, on the roadway side, 10 inches of concrete may be poured on top of the base, allowed to harden, and then 3 inches of asphalt are laid on top of the concrete to form the road.




A different method and system may be used at corners using a steel corner curb


70


, as shown in

FIGS. 14-16

. The first step in the placement of a steel corner curb


52


is to remove the existing sidewalk and dig trench


51


A.




The second step is for the work crew to place three large wood blocks on the floor of the rounded trench. Then they place the steel corner curb on the wood blocks.




If the tangent ends of the steel corner curb do not follow the line of the intersecting streets, the central angle of the steel corner curb is sprung, in or out, so that they do, as shown in connection with FIG.


15


.




The corner curb


70


is made to fit the usual corner road site where the two roads intersect at a 90° angle, i.e., an N-S road intersects an E-W road. However, sometimes the roads are not at 90°, but at a different angle, i.e., 89° or 91°, or even less or more, such as 84° to 96°. It is then necessary to change the central angle of the steel corner curb to follow the line of the existing road intersection, e.g., to spring the curb


50


within a range of 84° to 96°.




As shown in the top plan view of

FIG. 15

, a set of two or four turnbuckles are used to spring the corner curb


70


to the desired angle. The curb


70


, whose side cross-sectional shape is the same as curb


70


shown in

FIGS. 10-13

has a series of curb support/standoff brackets


71


A-


71


E, with the brackets


71


A-


71


E being at its opposite ends. The description will be of bracket


71


A, it being understood that the brackets


71


A-


71


E are the same. As shown in

FIG. 17

, the bracket


71


A has one end


72


welded to the curb


70


. The bracket


71


A has elongated holes


73


,


74


to receive the ends of the turnbuckle rods and hole


75


. The description will now be of one turnbuckle and its rods, the others being the same. A rod


76


has a bent end engaged in hole


73


of bracket


71


A and a screw-threaded portion at its opposite end which is screw-engaged into turnbuckle


77


. The rod


78


has a bent end engaged in hole


74


of bracket


71


B and its other end is screw-engaged into turnbuckle


77


. Rotation of the turnbuckle


77


, and the other turnbuckles, will spring in the curved curb


70


into a smaller angle than 90° or, if turned in the opposite direction, will spring out the curb


70


to an angle greater than 90°. Preferably, after the curb is sprung (pulled or pushed) into the desired angle, stakes are inserted into a hole


80


in one bracket and driven into the earth and this is repeated from bracket to bracket. Then all the turnbuckles, and their respective rods, are removed. The stakes hold the curb to the desired angle it was sprung to by the turnbuckles.




Next, using a pry bar placed between one of the wood blocks that was initially placed on the bottom of the rounded trench, and the bottom of the steel curb, the curb is raised to the correct elevation and secured as follows. using the following procedure and system, shown in FIG.


14


.




The description which follows will be only of stake


52


A and its associated sleeve and brackets, it being understood that the other stakes use the same sleeve and bracket system as is used with stake


52


A. The stakes


52


A-


52


D are driven in the ground, at the bottom of


51


A. The stake is first passed through tubular sleeve


53


. The sleeve


53


is welded to a steel bracket


54


to resist the stack's tendency to lean. This insures that the curb maintains the angle it had been sprung to by the turnbuckle means. The sleeve


53


has a threaded hole to receive a ⅜″ tee bolt


55


to lock the sleeve to its stake


52


A (pin). The curb may be moved vertically on its stake


52


A and then locked, using the sleeve bolt


55


to position the curb


70


at its correct height.




As shown in

FIG. 16

, curb


70


is formed with a plurality, preferably four, squares


56


, welded onto its back face


64


, two near the ends and two on each side of the centerline and 48″ apart(viewed from above). The present invention provides a special sheet metal bracket member


57


which is associated with each square bar


56


. The top bracket member


57


has a square-shaped hole


59


at its front end which fits over the square


56


. The back end


61


of the bracket member


57


(see

FIG. 16

) has a bracket arm


62


perpendicular to the body


63


of the bracket. An inverse C-shaped clamp


60


is placed over the bracket arm


62


. The clamp


60


is attached, by two rivets


66


, to a continuous flexible ½″×18″ or 8″ premolded expansion joint filler


65


(FIG.


14


). The expansion joint


65


is used as to separate the curb from the side walk and thus provide for expansion and contraction. It is left in place in the trench


51


A. The curb tie bracket


57


is used to space the expansion joint


65


from the curb


70


.




The bracket


71


A has three functions. It is the same part as


71


B,


71


D and


71


E in FIG.


15


A. It is used to hold the curved steel curb


70


to the angle it was sprung to by turnbuckles. Also, the bracket


71


A which is welded to the top of the sleeve


53


and to the curb


50


. Thusly, the position of the sleeve determines the vertical height of the bracket


71


A and hence the vertical height of the curb


50


and spaces the expansion joint filler. The bracket


71


A includes a bent flange portion


67


for strength.




In order to save shipping costs, the curb


70


, its brackets are shop-welded to curb but are shipped unassembled. The expansion joint filler is fragile and would need a crate. They are assembled at the job site. At the site the front end of the bracket


57


is placed over the square


56


, the expansion joint


65


is curved and the bracket arm


62


is placed into the clamp


60


.




The above description is of one curb tie bracket and its associated square bar bracket arm. It will be understood, however, that a curved steel corner curb will typically use 4 stakes, each with its own set of brackets, and that the form


65


will run the entire length of the curb, albeit in two pieces each 114″ long.




The description of the systems and methods for installing steel curbs provided in relation to

FIGS. 1A-17

are used when the road (roadway) is removed and a wide trench is dug. However, the following two alternative embodiments may be employed when only one, or a few, sections of steel curb are to be replaced, and none of the road is removed. This situation often occurs when a section of sidewalk is badly broken and must be replaced and because of job conditions the curb must also be replaced. For example, only 100 feet of sidewalk and its proximate steel faced concrete curb may be replaced.




In the first embodiment, shown in

FIG. 18

, a flat steel plate


100


, which is reusable, is placed on top of the existing road


101


. The road


101


is not removed. The plate


100


is correctly positioned on top of the road


101


and a nail


102


is driven through a hole near its proximate end. The nail is driven into the asphalt of the road to hold plate


100


in position. The plate


100


, at its opposite distal end, carries an adjustable nut


103


which connects the plate


100


to a vertical threaded steel rod


104


. The rod


104


, at its bottom, has screw threads


106


which are screwed into screw fitting


107


of a U-shaped steel bracket


105


. The bracket


105


is positioned along the edge of the road along an imaginary line connecting the end of the remaining curb at one limit and the end of the remaining curb at the other limit of the new sidewalk and curb. The bracket


105


is correctly positioned and then it supports the bottom edges of either or both the leading and trailing ends of the adjacent steel curb


108


which is laid in the bracket


105


. The nut on the threaded rod


104


(hanger bar) is used to adjust the steel curb to the elevation of the existing curb, which remains in place. The concrete is then poured, the rod


104


is unscrewed from the bracket


105


, and the rod


104


plate


100


are removed. The bracket


105


stays in the concrete.




An alternative embodiment of a system and method for placing replacement steel curbs without removal of any of the road, is shown in

FIGS. 19-21

. It uses an extendable leg comprising a rod or tube within a pipe which is similar to that shown in FIG.


14


.




The sidewalk and curb are removed and a narrow trench


110


is dug. The tube


112


fits within a pipe (tube)


113


of ¾-inch inner diameter. As shown in

FIG. 21

, a bracket


114


is welded to the steel curb


118


and has a flange portion


115


which carries a nut


116


. A tee bolt


117


is screwed into nut


116


and passes through a hole in pipe


113


. When tightened, the tee bolt


117


positions the tube


112


within the pipe


113


.




The pipes


120


and


121


are welded at both ends of the ends of the first of a series of curbs


125


at weld point


122


, see

FIG. 20. A

shelf bracket


119


is also welded to curb


125


at its leading end, at its bottom edge, to support and align the next steel curb


118


in the line. That next steel curb


118


, which is an otherwise conventional curb, has a pipe


112


of the same type as pipe


120


.




In addition, there is also described below a concrete form used to form a concrete curb without a steel curb, especially a corner concrete curb (curved as seen from above). This system is especially useful when a broken curb and sidewalk are being replaced and when a corner must be replaced to provide a handicap ramp to comply with the “Americans With Disabilities Act.” The existing road is not removed, but may be patched.




The first step is to remove the damaged curb and sidewalk to form a trench. There is provided a form holder to position and hold the front concrete multi-sectional form. The front form covers only the curb reveal with the remainder of the curb poured against the asphalt and concrete base of the existing road. The form holder also holds an expansion joint filler. This form holder (24″ OC.) applies a force to curve a 2×⅛×48″/72″ steel plate to the curvature of the curb that was removed.




As shown in

FIG. 22

, the expansion joint filler holder


140


uses a back vertical steel arm


130


, for example, ¼×1½×19¾ inches. The back arm


130


is spaced ½ inch from the front vertical steel arm


131


, which is preferably is ¼×1½×29¼ inches. The front arm


131


is bent to form a horizontal arm portion


132


, preferably


12


inches long. The premolded bituminous expansion joint filler


133


(expansion joint filler) sheet, which isolates the curb from the sidewalk, is held between the arms


131


and


130


. It is preferably ½×18 inch continuous. The curb and sidewalk are poured simultaneously.




The horizontal portion


132


, near its free end, has a hole through which a vertical rod


135


protrudes. The rod may be braced by plate


136


, if necessary. The rod


135


rests on a plate


137


and is used to position the horizontal arm portion. The plate


137


at its back rests on a ¼″×2″×4″ plate and at its front end rests on a bent plate with slotted holes. The front and back plates rest on the road and two nails are driven through two holes in the back plate into the asphalt. The curb form


140


is a steel sheet 2″×⅛″ and 48″ or 72″ long. It has threaded studs


141


welded to it.




For straight concrete curb (without steel facing) for limited repair 20′ to 100′ a system similar to that of

FIG. 18

may be used. The front for plate must be 7″ high instead of 2″ high and {fraction (3/16)}″ thick instead of ⅛″ thick.




In the embodiment of

FIG. 23

, the horizontal arm portion


132


is integral with the back arm


130


. The arm portion


132


has a descending vertical portion


145


and a horizontal portion


141


having a nail hole


142


. A nail is driven through the nail hole


142


into the asphalt of the road to position the form holder


143


. The vertical portion


140


holds the front form


144


.



Claims
  • 1. An elongated steel curb and bench laid within a trench having a trench floor, the steel curb having a nearly vertical wall portion adapted to be proximate a roadway and having interior and exterior faces, the steel curb having an integral top horizontal flange portion adapted to be level with a sidewalk and a bottom edge;the bench being a metal or plastic member having a bottom plate adapted to lie on the trench floor, a front plate, a back plate and a bracket attached to the front plate, the bracket supporting the bottom edge of the curb to position the curb in the trench, and two vertical protrusions on the bottom plate adapted to position a concrete form of lumber.
  • 2. The steel curb and bench as in claim 1 wherein the vertical protrusions are flanges which are integral with the bottom plate.
  • 3. The steel curb and bench as in claim 1 and an inverted U-shaped tubular steel frame adapted to hold front and back concrete forms.
  • 4. The steel curb and bench as in claim 1 and two of said brackets on said bench are adapted to hold the curb at the correct elevation and position one steel curb relative to an adjacent steel curb.
  • 5. An elongated steel curb and a metal bench laid within a trench having a trench floor, the steel curb having a vertical wall portion adapted to be proximate to a roadway and having interior and exterior faces, the steel curb having an integral top horizontal flange portion adapted to be level with a sidewalk and a bottom edge;the bench being a metal or plastic member having a bottom plate adapted to lie on the trench floor, a front plate, a back plate and a bracket attached to the front plate, the bracket supporting the bottom edge of the curb to position the curb in the trench, the front plate and back plate being welded to the bottom plate by weld lines adapted to shear under pressure from expanding or contracting concrete or having pleats to expand and contract.
  • 6. The steel curb and bench as in claim 1 and an inverted U-shaped tubular steel frame adapted to hold front and back concrete forms.
  • 7. The steel curb and bench as in claim 1 and two of said brackets on each bench adapted to position one steel curb relative to an adjacent steel curb.
  • 8. A method for installing a series of steel curbs, comprising:(a) digging an elongated trench along a side of a road; (b) placing a plurality of benches in the trench and aligning each bench with a string line; each bench being a metal or plastic member having a bottom plate adapted to lie on the trench floor, a front plate, a back plate, a bracket attached to the front plate, the bottom plate extending beyond the front and back plates and having vertical protrusions forming a front and back channel adapted to hold concrete forms, the bracket being adapted to support the bottom edge of the curb to position the curb in the trench; and (c) placing a steel curb with its bottom edge at its two ends in the brackets of the two benches; and (d) placing a front concrete form in the front channel and a back concrete form in the back channel and pouring a concrete slurry within the said forms.
US Referenced Citations (22)
Number Name Date Kind
398630 Landis Feb 1889 A
408057 White Jul 1889 A
442060 Landis Dec 1890 A
534441 Landis Feb 1895 A
670001 Morss Mar 1901 A
691794 Morss Jan 1902 A
1020887 Cornwall Mar 1912 A
1034504 Pindell Aug 1912 A
1185291 Davis May 1916 A
1789829 Moore Jan 1931 A
1927388 Campbell Sep 1933 A
1978491 Gladman Oct 1934 A
3157098 Mason Nov 1964 A
3203327 Daley Aug 1965 A
3208362 Sigmund Sep 1965 A
3844073 Peletz Oct 1974 A
3957383 Fredericks May 1976 A
4804292 DeLuca Feb 1989 A
5302047 Ivey Apr 1994 A
6106706 Roy et al. Aug 2000 A
6227758 Missick et al. May 2001 B1
6231758 Morris et al. May 2001 B1
Foreign Referenced Citations (2)
Number Date Country
3240331 May 1984 DE
08003932 Jan 1996 JP