This is a National Phase application claiming priority to PCT/GB2014/050183 filed Jan. 24, 2014 which claims priority to GB 1301318.0 filed Jan. 25, 2013, all of which are herein incorporated by reference in their entireties.
The invention to which this application relates is a method and apparatus for forming structures such as tunnels and, in particular, although not necessarily exclusively, for forming tunnels of a type which are known in the art as “green tunnels” and which term is hereinafter referred to for ease of illustration and in a non-limiting manner.
Green tunnels are a form of structure in which the aim is to form the tunnel for a particular service such as a road, railway, waterway, or the like and, once formed, to return the surface above and/or adjacent the tunnel structure to, or close to, it's original condition or another predefined condition. Typically the aim is to return the scenery and/or usage of the said surface to as close as possible to what it was prior to the performance of the tunnelling, or to another predefined condition. Increasingly, the formation of routes for new transport and/or communication services, such as high speed rail services in the United Kingdom, and/or highways or motorways cause considerable controversy and resistance due to the real and/or perceived, impact that the same will have on the landscape and environment through which the new route is to pass. In an effort to mitigate this problem it is increasingly the case that the specification for any tunnelling or excavation, and at least for tunnelling or excavation at relatively shallow depths from the surface, requires the tunnel structure which is to be formed as being specified as having to be a green tunnel.
Conventionally, the approach to forming green tunnels is to excavate the soil and rock to form a trench along the path of the new route to the required depth and then to form the tunnel progressively along the route by casting the base, walls and roof of the tunnel using formwork, reinforcement and concrete. This is a slow process and requires many frequent deliveries of materials, and personnel to the locations where the tunnel is being formed and the removal of material and personnel in the opposite direction along the route as the tunnel is formed which requires significant transport access to be formed and causes large scale disruption to the surrounding environment. This also significantly increases the overall size of the area of the landscape which is required to be disturbed, and subsequently reinstated, in order to allow the tunnel structure to be formed.
Furthermore, access for transport is required to be provided at all points along the route in order to service the works and to allow the delivery of the box units and/or materials for casting m-situ and movement to the location for use on the route, and also the movement of the material following excavation and, thereafter, to allow reinstatement. The use of existing access roads and/or formation of new access roads can cause significant disruption to residents and the local environment in the area and, in itself, requires excavation works which need to be reinstated subsequently. As a result of this, while it is the case that the works can eventually be reinstated to form a green tunnel, the extent of the reinstatement which is required using the conventional method and apparatus is significant, disruptive and can be costly.
The aim of the present invention is therefore to provide a method and apparatus which allows the formation of tunnels in a form which allows the preparatory work and the subsequent works performed in order to meet the requirement for reinstatement of the material above and adjacent to the green tunnel which has been formed to be minimised. A further aim is to allow the support infrastructure required for the formation of the tunnel to be reduced.
In a first aspect of the invention there is provided a method of forming a tunnel, said method comprising the steps of forming at least one access point along the route of the said tunnel, forming at least one support base in at least one direction away from the access point along said route, providing the support base with guide means thereon, and wherein at least one deck structure is advanced along the guide means to form at least the roof of at least a portion of the tunnel so that at least a portion of the said tunnel is formed outwardly from the said access point along said route.
Typically a plurality of deck structures are advanced in succession along the guide means to form at least the roof of at least a portion of the tunnel.
In one embodiment at least the lower part of the tunnel walls are formed from upstanding parts of the support base, which is formed by a plurality of units advanced into position as excavation works are performed. In one embodiment the deck structures include downwardly depending portions which form part of the side walls of the tunnel.
In one embodiment the said tunnel portion extends from the access point to an end of the tunnel or, alternatively, to a further access point spaced from the first.
In one embodiment a plurality of tunnel portions are extended outwardly from an access point in the direction of said tunnel route, said portions typically angularly offset around the access point. Typically the said tunnel portions extend outwardly from the access point in opposing directions and extend the tunnel along the route in opposite directions from the access point.
Typically, the support base is formed by two spaced apart base portions, each of which includes guide means thereon such that the deck structures are supported by, and span between, the respective guide means.
Typically the support base portions are installed along access tunnels which are formed along the route and which extend from the access point. The access tunnels which are formed allow access for piling and the support base units to be installed therealong and the guide means to be exposed when required to allow the deck structures to be moved, typically by jacking, along the same.
In one embodiment each support base portion includes a series of piles depending downwardly therefrom, a base unit and on the upper and/or side walls thereof guide means are formed.
In one embodiment excavation works are performed in front of the leading deck structure to define the cavity which is to form the tunnel.
In one embodiment the deck structures are cast at the access point from which the same are to be advanced along the guide means or are transported to the access point and from which the same are then advanced along the guide means.
Typically the deck structures are moved along the guide means by jacking means provided at the access point. In one embodiment, further jacking apparatus may be provided at a location spaced along the tunnel route from the access point to provide further jacking forces if required.
Typically, the excavation of material in advance of the leading deck structure is required in the area between the support base portions in order to form the main cavity of the tunnel. The excavation can be performed using one, or a combination, of tunnelling excavation in which a shield is provided at the leading deck structure and tunnelling excavation is performed, and/or open excavation in which the excavation work is performed along and downwardly from the surface.
In one embodiment a portion of the tunnel is formed at or adjacent to the access point and which may form an end of the tunnel or a portion of the tunnel intermediate the tunnel ends.
Typically tunnelling excavation methods will be performed when the tunnel to be formed is located relatively deep below the surface and open excavation methods will be performed when the tunnel is to be formed at a relatively shallow depth from the surface.
In one embodiment, excavation apparatus can be located on the one or more leading deck structures which have been advanced in to position and which are adjacent the location at which excavation is to be performed, thereby avoiding the need for significant disruption to the land to the side of the tunnelling route or the need for significant additional land on one, or both sides, of the route to be provided.
Typically, in which ever form of excavation, the material which is removed may be placed to one side of the route for subsequent use for reclamation or removal or, alternatively, may be placed onto vehicles which use the top of the installed deck structure as a transport path back to the access point and, thereafter, access to the local transport infrastructure.
Typically the length of the tunnel formed from any given access point can be dependent upon a number of parameters such as the depth of excavation, the size of the tunnel to be formed, and the like, and is therefore unlimited in many instances. For example, lengths of tunnel of 1 km can be achieved in each direction therefore meaning that a tunnel of 2 km in length can be formed from a single access point. This therefore represents significant savings in terms of additional excavation works, the amount of land which is disrupted and the support transport infrastructure which is required to be formed.
Typically, once the tunnel is formed, material can be moved over the top of the deck structure, either from the side where the excavated material was deposited or from transported material which again may be transported along the top of the deck structure. Thus the surface above the structure can be reinstated as required with minimum disruption.
In a further aspect of the invention there is provided a method of forming a tunnel, said method comprising the steps of forming at least one access point along the route of the said tunnel, said tunnel structure is partially formed by forming at least one support base in at least one direction away from the access point along said route, and wherein the remainder of the tunnel structure is formed by a plurality of deck structures which are progressively advanced along the route from the access point and in contact with the support base.
In one embodiment a plurality of access points are provided along the tunnel route and are interlinked by the tunnel structure which is advanced from and between the access points. Typically the access points form part of the tunnel structure.
A tunnel formed using the method as described above is also claimed.
In a further aspect of the invention there is provided a tunnel, said tunnel formed from a support base including guide means formed thereon, side walls and a roof structure formed from one or more deck structures movable along and supported by the guide means of the support base and wherein said tunnel includes at least one access point from which the deck structures are advanced along the guide means and from which at least part of the said tunnel apparatus extends.
Typically the support base includes first and second, spaced apart portions in which the guide means are formed and the deck structures are located on and span the guide means of the respective support base portions.
In one embodiment the tunnel comprises a first series of deck structures which define a first portion of the tunnel and a second series of deck structures, spaced from the first, which define a second portion of the tunnel.
In one embodiment the said passageways are spaced apart along a substantially horizontal plane. Alternatively, or in addition, the passageways are spaced apart along a substantially vertical plane.
Specific embodiments of the invention are now described with reference to the accompanying drawings wherein;
Referring firstly to
A service road 4 may already be present or is formed so as to allow the transport of personnel, apparatus and removal and provision of materials to be performed via the access point and the road 4. In this case the tunnel 6 is shown as being formed in two directions 8,10 from the access point along the required route 1. In order to achieved this the following method steps can be performed with reference to
At the access point 2 a pit or shaft is excavated and this will ultimately form part of the tunnel structure 6 as well as acting as access means during the formation of the tunnel structure 6. From the pit or shaft, access tunnels 12, 12′ and 14,14′ are formed along the tunnel route, in the directions 8 and 10 respectively. From within the access tunnels piles 16 are formed downwardly and support base units 18 are placed along the access tunnels from the access point and are supported by the piles. Alternative methods can be used such as piling alone from the surface and/or placing a beam on top of the same.
In the embodiment shown, guide means 20 are formed in the support base portions 22,22′ which are formed along the access tunnels 12,12′,14,14′ and, when required the guide means can be exposed for use. The guide means are provided to have low friction whilst providing guidance for the movement of deck structures therealong and the guide means and or deck structures may include a low friction coating and/or guide tracks may be provided.
Typically the guide means are only exposed soon before the advancement of the deck structures 24 in the directions 8 and 10 respectively from the access point 2. The deck structures are successively added and jacked along the guide means in the respective directions from the access point 2.
Ahead of the leading deck structure 24′ there is a need to excavate the material, typically soil and rock 26, which lies ahead of the deck structures. In
Furthermore, as shown in
Also shown in
If necessary, partition walls 36,38 may be installed in the interior of the tunnel cavity 40 to form, in the case shown in
Once the tunnel structure 6 is formed, the top surface 30 of the deck structures 24 can be overlaid with material 26 and then landscaped as required to provide the full reinstatement of the environment above the tunnel.
It is envisaged that the invention will be of particular use when forming tunnels for use in carrying transport routes such as rail and road transport. For example, when forming roads an open trench can be formed and the tunnel structure is installed below and/or along the existing road. Conventionally the techniques used would take up a lot of space on the existing road and limit use of the same during construction works but this can be avoided in the apparatus and method of the current invention as it allows the tunnel structure to be installed without disruption of existing roads, and other installations such as crossroads, pipelines, cables etc. to be achieved.
Number | Date | Country | Kind |
---|---|---|---|
1301318.0 | Jan 2013 | GB | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/GB2014/050183 | 1/24/2014 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2014/114941 | 7/31/2014 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
3442088 | Borisof | May 1969 | A |
6406220 | Thomson | Jun 2002 | B1 |
20010006304 | Seear | Jul 2001 | A1 |
Number | Date | Country |
---|---|---|
06185294 | Jul 1994 | JP |
H06 185294 | Jul 1994 | JP |
06346699 | Dec 1994 | JP |
2001336164 | Dec 2001 | JP |
2012017314 | Feb 2012 | WO |
Entry |
---|
International Searching Authority Search Report, Issued in connection to International Application No. PCT/GB2014/050183, 10 pages Feb. 9, 2015. |
Number | Date | Country | |
---|---|---|---|
20150322630 A1 | Nov 2015 | US |