Claims
- 1. A method for integrated horizontal selective testing of highly deviated or horizontally completed wells having one or more perforated zones and/or cased or open hole lateral branches to provide substantially real-time measurement of the production flow rates of a plurality of the perforated zones and/or lateral branches, comprising:
with a coiled tubing deployment system, positioning a downhole flow rate measurement tool having a production flow rate measurement capability at a selected location within the wellbore relative to a selected perforated zone or lateral branch; with the downhole flow rate measurement tool measuring the production flow rate of the production fluid at the selected location; successively moving the downhole flow rate measurement tool to other selected locations within the wellbore and conducting other production flow rate measurements; and correlating the flow rate measurement data of each of the production flow rate measurements for confirming the production flow rates of each of the perforated zones and/or lateral branches.
- 2. The method of claim 1, further comprising:
utilizing flow rate measurement data of each of the production flow rate measurements and constructing a production flow rate profile.
- 3. The method of claim 1, further comprising:
in the event the production flow rates of the perforated zones and/or lateral branches indicates the need for remedial activity downhole, un-deploying said downhole flow rate measurement tool; and deploying remedial equipment with said coiled tubing deployment system and conducting remedial activity within the well.
- 4. The method of claim 1, further comprising:
connecting a multi-phase flowmeter into the flowline of the well; and with the multi-phase flowmeter measuring the total production flow rate of the production fluid flowing through the flowline both during downhole flow rate measurement and for identifying changes in the production flow rate of the well after downhole flowrate measurement has been completed.
- 5. A method for integrated horizontal selective testing of highly deviated or horizontally completed wells having one or more perforated zones and/or cased or open hole lateral branches to provide substantially real-time flow rate measurement of production fluid of a plurality of the perforated zones and/or lateral branches, comprising:
with a coiled tubing string, positioning a downhole flow rate measurement tool having at least one re-settable packer and having a production flow rate measurement capability at a selected location within the highly deviated or horizontal wellbore relative to a selected perforated zone or lateral branch; setting the re-settable packer within the wellbore at the selected location and confirming sealing of the packer within the wellbore; with the downhole flow rate measurement tool, measuring the production flow rate of the production fluid at the selected location; successively moving the downhole flow rate measurement tool to other selected locations within the wellbore, setting and confirming sealing of the packer, and conducting other production flow rate measurements; and utilizing flow rate measurement data of each of the production flow rate measurements for confirming the production flow rates of each of the perforated zones and/or lateral branches.
- 6. The method of claim 5, further comprising:
connecting a multi-phase flowmeter into the flowline of the well to provide total production flow measurement identifying the total flow rates of oil, water, and gas of the production fluid flowing through the flowline.
- 7. The method of claim 5, further comprising:
with the coiled tubing string, retrieving said downhole tool flow rate measurement tool from the well; and with the coiled tubing string, conducting remedial downhole servicing activities to optimize well production.
- 8. The method of claim 7, comprising:
with the coiled tubing string, setting one or more packers and accomplishing optimal production zone shutoff.
- 9. The method of claim 5, wherein the downhole flow rate measurement tool has at least one logging tool and has a flow-by housing containing the logging tool and permitting production fluid flow past the logging tool, said method further comprising:
conducting well logging operations with said at least one logging tool during running of said downhole flow rate testing tool and during production flow for accurately positioning said downhole flow rate measurement tool and for selective measurement of individual production flow rates of selected perforated zones and/or lateral branches of the well.
- 10. The method of claim 9, wherein said at least one logging tool is a reservoir saturation logging tool, a gamma ray logging tool and a casing collar locator tool, said method comprising:
during running of the downhole flow rate measurement tool, recording gamma ray and casing collar locator log data along the wellbore.
- 11. The method of claim 10, further comprising:
during running of the downhole flow rate measurement tool, correlating depths of recorded data with log data previously acquired within the wellbore.
- 12. The method of claim 10, further comprising:
during running of the downhole flow rate measurement tool, confirming the depths of the perforations from the recorded data of said casing collar locator tool.
- 13. The method of claim 5, comprising:
with the downhole flow rate measurement tool located within the wellbore, measuring and recording the production flow rates of oil, water, and gas flowing from one or more perforated zones and/or lateral branches.
- 14. The method of claim 5, comprising:
with the downhole flowrated measurement tool located within the wellbore, with the coiled tubing string selectively positioning the downhole tool for location of the re-settable packer at a first pre-selected depth nearest the top of the bottommost perforation of the well; after measuring and recording the production flow rate at the selected depth, successively moving the downhole flow rate measurement tool upwardly to desired locations within the wellbore and measuring the production flow rates at the desired locations; and correlating production flow rate data of each production flow rate measurement for identification of the production flow rates of selected perforated zones and/or lateral branches.
- 15. A method for integrated horizontal selective testing of highly deviated or horizontal wells having one or more perforated zones and/or lateral branches to provide real-time oil, water, and gas production flow rate measurement from selected perforated zones and/or lateral branches, comprising:
connection of a surface located multi-phase flowmeter into the flowline of the well, the multi-phase flowmeter measuring the rates of oil, water, and gas flow through the flowline and providing real-time production flow data; using coiled tubing, conveying a downhole flow rate measurement tool into the well, the downhole flow rate measurement tool comprising a logging tool having a coiled tubing logging head provided with logging signal conductors, a wired upper deployment bar having logging signal conductors, a flow-by housing having located therein at least one logging instrument connected with said logging signal conductors, the flow-by housing defining at least one production flow passage permitting flow of production fluid therethrough, said downhole tool further comprising a re-settable packer; positioning the downhole flow rate measurement tool to locate said re-settable packer at a first pre-selected depth above the bottommost perforated zone or lateral branch; inflating said re-settable packer to sealing engagement with the wellbore; measuring the production flow rates of oil, water, and gas in the wellbore at the pre-selected depth; and correlating the production flow rate data of individual measurements for identification of the individual production flow rates of the individual perforated zones and/or lateral branches.
- 16. Apparatus for conducting integrated horizontal selective testing of highly deviated or horizontal multilateral wells, comprising:
a coiled tubing conveyance mechanism located at the surface and having a coiled tubing string for well tool conveyance; a downhole flow rate measurement tool having a re-settable packer and being conveyed to selected locations within a highly deviated or horizontal multilateral well by said coiled tubing mechanism for successive production flow rate tests, said re-settable packer selectively sealing within the wellbore to permit production flow rate measurement at each selected locations for indicating the production flow rates of individual perforated zones and/or lateral branches.
- 17. The apparatus of claim 16, further comprising:
a multi-phase flowmeter located at the surface and connected to the flowline of the well and measuring the flow rates of oil, water, and gas of the production fluid flowing through the flowline and acquiring and recording the total production flow rate data of the well.
- 18. The apparatus of claim 16, further comprising:
at least one logging tool located within said downhole flow rate measurement tool for selective location of said downhole flow rate measurement tool within a wellbore and for conducting well logging during running of said downhole flow rate measurement tool by said coiled tubing mechanism and during static location of said downhole flow rate measurement tool within the wellbore.
- 19. The apparatus of claim 18, wherein:
said at least one logging tool is a reservoir saturation logging tool, a gamma ray logging tool, and a casing collar locator logging tool, at least one being operable for precise location of said downhole flow rate measurement tool within the wellbore and at least one being operable for production flow rate measurement within the wellbore.
- 20. The apparatus of claim 18, wherein:
said downhole flow rate measurement tool has a flow-by housing defining a chamber within which said at least one logging tool is located, said flow-by housing having at least one flow-by passage permitting fluid flow through said at least one flow-by passage and past said at least one logging tool.
- 21. The apparatus of claim 20, further comprising:
an upper deployment bar connected with said coiled tubing string and connected with said flow-by housing and having at least one electrical conductor for conducting electrical signals to and from said at least one logging tool.
- 22. The apparatus of claim 20, further comprising:
a lower deployment bar having an upper end connected to said flow-by housing and having a lower end connected with said re-settable packer.
- 23. The apparatus of claim 22, further comprising:
an upper deployment bar connected with said coiled tubing string and connected with said flow-by housing and having at least one electrical conductor for conducting electrical signals to and from said at least one logging tool; and pressure barrier elements located both above and below said upper and lower deployment bars.
- 24. The apparatus of claim 23, wherein said pressure barrier elements are valve members.
- 25. The apparatus of claim 23, said pressure barrier elements are check valves arranged for closing responsive to predetermined conditions of production fluid flow.
CROSS-REFERENCE TO RELATED APPLICATIONS
[0001] This application claims priority from U.S. Provisional Application No. 60/369,165, filed Apr. 1, 2002, which is incorporated herein by reference.
Provisional Applications (1)
|
Number |
Date |
Country |
|
60369165 |
Apr 2002 |
US |