Claims
- 1. An apparatus system for preparing a fuel tank for repairs and verifying repair work upon completion, said apparatus comprising:
a supply system constructed and arranged to be coupled to said fuel tank for providing a supply of inert gas into said fuel tank to purge said fuel tank of oxygen to a certain level and to inert said fuel tank with said gas;
said supply system including:
a gas release system constructed and arranged to provide said supply of inert gas and including an arrangement for connecting and facilitating transport of said inert gas; a supply mechanism configured and positioned to facilitate and regulate a transfer of gas from said gas release system to said fuel tank; a connector mechanism for coupling said supply mechanism to said gas release system; a relief system constructed and arranged to be coupled to said fuel tank to regulate and relieve pressure in said fuel tank, and a plurality of connectors for connecting said apparatus system to said fuel tank;
said plurality of connectors including:
a first of said plurality of connectors constructed and arranged to couple said supply system to said fuel tank, and a second of said plurality of connectors constructed and arranged to couple said relief system to said fuel tank.
- 2. The apparatus according to claim 1, wherein said certain level of oxygen is below about 6 percent.
- 3. The apparatus according to claim 1, wherein said arrangement is a manifold system.
- 4. The apparatus according to claim 1, wherein said supply of inert gas is nitrogen gas.
- 5. The apparatus according to claim 1, wherein said certain level of oxygen is below about 6 percent, said arrangement is a manifold system, and said supply of inert gas is nitrogen gas.
- 6. The apparatus system according to claim 1, wherein said supply system further comprises a high pressure regulating mechanism.
- 7. The apparatus system according to claim 1, wherein said supply system further comprises a high pressure relief mechanism.
- 8. The apparatus according to claim 1, wherein said connectors are a length of hose with fuel filler cap tank adapters attached to one end of each length of hose.
- 9. The apparatus according to claim 1, wherein said supply system is coupled to said fuel tank opposite where said relief system is coupled to said fuel tank.
- 10. The apparatus according to claim 1, wherein said fuel tank is a locomotive fuel tank.
- 11. The apparatus system according to claim 1, wherein said supply system comprises an arrangement of at least one of each of a pressure regulating mechanism, a flow control mechanism, a flow measuring mechanism, and a pressure measuring mechanism along at least one passage for carrying said gas.
- 12. The apparatus according to claim 11, wherein said flow control mechanism is a valve.
- 13. The apparatus according to claim 11, wherein said flow measuring mechanism is a flow meter valve.
- 14. The apparatus according to claim 11, wherein said pressure measuring mechanism is a pressure gauge.
- 15. The apparatus according to claim 11, wherein said pressure regulating mechanism is a pressure regulator.
- 16. The apparatus according to claim 11, wherein said flow control mechanism is a valve, said flow measuring mechanism is a flow meter valve, said pressure measuring mechanism is a pressure gauge, and said pressure regulating mechanism is a pressure regulator.
- 17. The apparatus according to claim 1, wherein said relief system comprises an arrangement of at least one of each of a flow control mechanism and a pressure measuring mechanism along at least one passage for carrying said gas.
- 18. The apparatus according to claim 17, wherein said relief system further comprises a pressure relieving mechanism along said at least one passage.
- 19. The apparatus according to claim 18, wherein said pressure relieving mechanism is a pressure relief valve.
- 20. The apparatus according to claim 17, wherein said flow control mechanism is a valve.
- 21. The apparatus according to claim 17, wherein said pressure measuring mechanism is a pressure gauge.
- 22. The apparatus according to claim 17, wherein said relief system further comprises a pressure relieving mechanism along said at least one passage, said flow control mechanism is a valve, and said pressure measuring mechanism is a pressure gauge.
- 23. A method for verifying repair work on a fuel tank using an apparatus which verifies repair work by pressurizing said fuel tank with gas, said apparatus comprising a supply system, a relief system, and a plurality of connectors, said method comprising:
connecting the apparatus to the fuel tank with completed repair work; pressurizing said fuel tank with inert gas to a certain pressure level; maintaining the certain pressure level for a specified period of time; and performing an inspection of the repaired area of the fuel tank.
- 24. The method according to claim 23, wherein said certain pressure level is between 1.8 and 2.0 psi.
- 25. The method according to claim 23, wherein said specified period of time is at least 80 minutes.
- 26. The method according to claim 23, wherein said inspection includes at least one of an audible inspection and a visual inspection of the repair work.
- 27. The method according to claim 23, wherein said certain pressure level is between 1.8 and 2.0 psi, said specified period of time is at least 80 minutes, and said inspection includes at least one of an audible inspection and a visual inspection of the repair work.
- 28. A method for preparing a fuel tank for repairs and verifying the repair work using an apparatus, which renders an environment of the fuel tank non-reactive by supplying the fuel tank with a certain gas and verifies repair work by pressurizing said fuel with said certain gas, said apparatus comprising a supply system, a relief system, and plurality of connectors, wherein each of said supply system and relief system is coupled to said fuel tank, said method comprising:
connecting the apparatus to the fuel tank, wherein the supply system is connected to a first side of the tank, and the relief system is connected to a second side of the tank; purging the fuel tank of oxygen to a certain level using the gas by providing the certain gas through the supply system and releasing the oxygen through the relief system until a level of the oxygen in the fuel tank reaches the certain level; closing, to the environment, openings on the fuel tank; repairing the fuel tank while maintaining the certain level of oxygen in the fuel tank; providing the certain gas through the supply system to the fuel tank to pressurize the fuel tank with the certain gas to a certain pressure level; maintaining the certain pressure level for a specified period of time; and performing an inspection of the repaired area of the fuel tank.
- 29. The method according to claim 28 further comprises
repairing any remaining repairs found following the inspection of a repaired area; re-pressurizing the fuel tank by supplying the certain gas through the supply system to the fuel tank; re-testing the repaired area; and repeating the repairing of any of the remaining repairs, re-pressurizing the fuel tank, and retesting the repaired area until the retesting indicates that the remaining repairs are complete.
- 30. The method according to claim 28, wherein said certain level of oxygen is below about 6 percent.
- 31. The method according to claim 28 wherein said certain level of oxygen is measured by at least one gas inspector.
- 32. The method according to claim 28, wherein said certain pressure level is between 1.8 and 2.0 psi.
- 33. The method according to claim 28, wherein said specified period of time is at least 80 minutes.
- 34. The method according to claim 28, wherein said inspection includes at least one of an audible inspection and a visual inspection of the repair work.
- 35. The method according to claim 28, wherein said certain level of oxygen is below about 6 percent, said certain level of oxygen is measured by at least one gas inspector, said certain pressure level is between 1.8 and 2.0 psi, said specified period of time is at least 80 minutes, and said inspection includes at least one of an audible inspection and a visual inspection of the repair work.
- 36. The method according to claim 29, wherein said certain level of oxygen is below about 6 percent.
- 37. The method according to claim 29 wherein said certain level of oxygen is measured by at least one gas inspector.
- 38. The method according to claim 29, wherein said certain pressure level is between 1.8 and 2.0 psi.
- 39. The method according to claim 29, wherein said specified period of time is at least 80 minutes.
- 40. The method according to claim 29, wherein said inspection includes at least one of an audible inspection or visual inspection of the repair work.
- 41. The method according to claim 29, wherein said certain level of oxygen is below about 6 percent, said certain level of oxygen is measured by at least one gas inspector, said certain pressure level is between 1.8 and 2.0 psi, said specified period of time is at least 80 minutes, and said inspection includes at least one of an audible inspection and a visual inspection of the repair work.
Parent Case Info
[0001] This application claims the benefit of priority from provisional U.S. patent application 60/161,372, filed in the U.S. Patent and Trademark Office on Oct. 26, 1999, herein incorporated by reference in its entirety.
Provisional Applications (1)
|
Number |
Date |
Country |
|
60161372 |
Oct 1999 |
US |
Divisions (1)
|
Number |
Date |
Country |
Parent |
09640915 |
Aug 2000 |
US |
Child |
10125603 |
Apr 2002 |
US |