Information
-
Patent Grant
-
6745835
-
Patent Number
6,745,835
-
Date Filed
Thursday, August 1, 200223 years ago
-
Date Issued
Tuesday, June 8, 200421 years ago
-
Inventors
-
Original Assignees
-
Examiners
- Bagnell; David
- Collins; Giovan
Agents
- Salazar; J.L. Jennie
- Jeffery; Brigitte L.
- Ryberg; John
-
CPC
-
US Classifications
Field of Search
US
- 166 264
- 166 167
- 166 100
- 175 40
- 073 15255
- 073 15228
- 073 15223
- 073 15224
- 073 15226
-
International Classifications
-
Abstract
A method for sampling a subsurface formation includes positioning a formation testing tool in a borehole having borehole fluid with a pressure less than formation pressure such that a pressure differential exists between the borehole and the formation. The method also includes establishing fluid communication between the tool and the formation, and inducing flow from the formation into the tool by exposing the tool to the pressure differential. The method further includes capturing a formation fluid sample in a sample tank by directing formation fluid to the sample tank and exposing the sample tank to the pressure differential. A system for sampling a subsurface formation includes a formation testing tool having a probe assembly, a sample tank, and a conduit system. The system also includes wellhead for controlling borehole pressure. The wellhead includes a sealing apparatus, a pressure increasing device, and a flow adjustment device.
Description
BACKGROUND OF INVENTION
The invention relates generally to formation fluid sampling. More particularly, the invention relates to a method and an apparatus for obtaining a fluid sample from a subsurface formation traversed by a borehole while controlling the flow rate and/or pressure.
Fluid samples from subsurface formations are typically collected from a reservoir for analysis at the surface, downhole or in specialized laboratories. Information obtained from analyzing formation fluid samples often plays a vital role in the planning and development of hydrocarbon reservoirs and in the assessment of a reservoir's capacity and performance.
FIG. 1
shows one example of a conventional formation testing tool
100
which may be used to obtain a sample or conduct tests in a subsurface formation. Sampling operations are typically conducted in “overbalanced” boreholes, wherein the hydrostatic pressure of the borehole fluid is greater than the formation pressure. Overbalancing typically prevents the formation fluid from breaking through the walls of the wellbore and causing either “blowouts” or undesired pressure at surface.
In a typical sampling operation, the formation testing tool
100
is lowered into an overbalanced borehole
109
on a wireline
111
and positioned adjacent the subsurface formation
103
to be sampled. The formation testing tool
100
makes physical contact with the inside surface of the borehole
109
by engaging a probe
104
of a probe assembly
102
with a wall
112
of the borehole
109
. One or more stabilizer pads
115
also extend from the formation testing tool
100
to stabilize the formation testing tool
100
in the borehole
109
.
As shown in
FIG. 1
, the formation testing tool
100
includes a pump module
105
which is used to induce fluid flow from the formation
103
into the formation testing tool
100
. An analyzer module
106
may also be provided to analyze fluid obtained from the formation. A plurality of sample tanks (not shown) are also disposed in a sample tank module
118
of the formation testing tool
100
to enable the collection of formation fluid samples in the tool
100
.
Contact between the probe
104
of the formation testing tool
100
and the borehole wall
112
enables pressure communication with the formation
103
. A seal is disposed around the probe
104
to isolate the inner parts of the formation testing tool
100
from the borehole fluid. In openhole boreholes, mudcake is typically disposed on the borehole wall
112
to isolate the formation fluid from the borehole fluid. In cased boreholes, casing and cement are disposed in the borehole to isolate the formation fluid from the borehole fluid.
Once the formation testing tool
100
is positioned and set as described above, one or more formation fluid samples may be obtained from the formation
103
. Fluid communication is established between the formation testing tool
100
and the subsurface formation
103
by contacting the probe
104
to the subsurface formation
103
. Because the formation
103
is at a lower pressure than the borehole
109
, and the formation testing tool
100
is in communication with the higher borehole pressure, formation fluid may then be drawn into the formation testing tool
100
by using a downhole pump module
105
. A downhole pump is used to create a desired pressure differential between the formation testing tool
100
and the subsurface formation
103
to induce flow from the formation
103
into the formation testing tool
100
.
Other prior art formation testing tools and sampling methods have been developed as described in detail in U.S. Pat. Nos. 4,860,581; 4,936,139 (both assigned to Schlumberger); U.S. Pat. No. 5,303,775 (assigned to Western Atlas); and U.S. Pat. No. 5,934,374 (assigned to Halliburton). The formation sampling methods and tools in these cases disclose formation sampling operations carried out by flowing fluid into the formation testing tool with a downhole pump that creates a desired pressure differential. U.S. Pat. No. 5,377,755, assigned to Western Atlas International is another example of a formation testing tool used for sampling. This patent describes a formation testing tool including a bi-directional pump adapted to control the pressure differential in sample tanks. Valves are disposed in flow lines between the pump and the sample tanks to allow for the selective communication of fluid therebetween.
The prior art downhole testers and sampling techniques utilize pumps to collect samples and maintain the samples in “single phase.” In single phase sampling operations, the pressure drop experienced by the formation fluid must be minimized to avoid drawing the formation fluid sample at a pressure below its bubble point pressure or asphaltene precipitation point. This is achieved in prior art formation testing tools by providing flow control during sampling. The flow control is largely dependent on the operation of one or more downhole pumps. As formation fluid is drawn out of the formation, the pressure drop experienced by the formation fluid and the rate of flow are regulated by the speed of the pump.
In a sampling operation, the initial drawdown of formation fluid from the formation is often contaminated by mudcake, filtrate, or debris. Pumps are used to remove a sufficient amount of formation fluid before collecting a formation fluid sample to purge these contaminates from the fluid stream. This initial formation fluid removal operation is referred to as the clean-up phase. When a sampling operation includes a clean-up phase, flow control is provided downhole by initially running a downhole pump as fast as possible to reduce the clean-up period and then lowering the downhole pump speed to maintain the formation fluid sample in a single phase during collection or downhole analysis of the sample. If the speed required by the downhole pump is below a certain operating threshold, the pump motor may stall causing the pump to fail. Therefore, the operating range of the downhole pump must be optimally designed or selected prior to a sampling operation. If failure of the downhole pump occurs during an operation, either another pump is required or the tool must be pulled to the surface and the existing pump fixed or replaced before a single phase sample may be acquired.
To minimize or avoid problems associated with the use of downhole pumps during sampling operations, a method is desired which allows for a formation fluid sample to be obtained and that allows for control of the flow rate and/or pressure disturbance experienced by the formation fluid during sampling. A method is also desired which permits sampling in a wellbore which does not require the use of a downhole pump. It is further desired that such a method may provide a technique for obtaining single phase samples.
SUMMARY OF INVENTION
In one aspect, the present invention relates to a method for sampling a subsurface formation traversed by a borehole. In one embodiment, the method comprises positioning a formation testing tool in a borehole having borehole fluid therein with a pressure less than formation pressure such that a pressure differential exists between the formation and the borehole. The formation testing tool includes a sample chamber having a first side, a second side and a movable fluid separator disposed there between. The method further includes establishing fluid communication between the formation testing tool and the formation and inducing fluid flow from the formation to the formation testing tool by exposing an interior of the formation testing tool to the pressure differential. The method also includes capturing a sample of the formation fluid in a sample tank associated with the formation testing tool by exposing the sample tank to the pressure differential.
In another aspect, the present invention relates to a method for performing a controlled pretest on a subsurface formation traversed by a borehole. In one embodiment, the method comprises positioning a formation testing tool in a borehole having borehole fluid therein with a pressure less than formation pressure such that a pressure differential exists between the borehole and the formation. The formation testing tool includes a variable volume sample tank having a sample chamber, a buffer chamber, and a moveable fluid separator between the sample chamber and the buffer chamber. The method further comprises establishing fluid communication between the formation testing tool and the formation, and inducing fluid flow from the formation into the formation testing tool by exposing an interior of the formation testing tool to the pressure differential. The method also includes drawing a volume of formation fluid in the sample tank by directing the formation fluid to the sample chamber of the sample tank and exposing the buffer chamber of the sample tank to the borehole pressure. The method further includes holding the volume on the sample chamber of the sample tank constant to allow pressure in the sample tank to build-up to a pressure proximal the formation pressure.
In another aspect, the present invention relates to a system for pressure controlled downhole sampling a subsurface formation traversed by a borehole. In one embodiment, the system comprises a formation testing tool adapted for placement in the borehole and a wellhead. The wellhead is disposed about the borehole proximal the surface and is adapted to seal borehole fluid therein such that the borehole fluid is maintained at a desired pressure. The formation testing tool includes a probe assembly, a conduit system, and at least one sample tank. The probe assembly is adapted to establish fluid communication between the formation testing tool and the subsurface formation. At least one sample tank includes a sample chamber adapted to accept formation fluid therein, a buffer chamber in fluid communication with the borehole, and a moveable fluid separator disposed between the sample chamber and the buffer chamber to maintain a separation of fluid there between. The conduit system includes a first end in fluid communication with the probe assembly, a second end in fluid communication with the borehole, and a third end in fluid communication with the sample chamber of the sample tank. The wellhead includes a sealing apparatus disposed about the borehole and adapted to seal borehole fluid therein, at least one pressure increasing device disposed in fluid communication with the borehole and adapted to enable selective increase of pressure in the borehole, and at least one flow adjustment device adapted to enable adjustment of the flow of borehole fluid out of the borehole.
Advantages of one or more embodiments of the invention may include the ability to accurately control the pressure drop experienced by the formation fluid during sampling by manipulating surface pressure applied to the borehole at the surface. Advantageously, by controlling the pressure and/or flow rate of borehole fluid at the surface a single phase formation fluid sample may be obtained.
Other aspects and advantages of the invention will be apparent from the following description and the appended claims.
BRIEF DESCRIPTION OF DRAWINGS
FIG. 1
shows a schematic view of a conventional formation testing tool positioned in a borehole adjacent a subsurface formation to be sampled.
FIG. 2
shows a partial cross sectional view of a formation testing tool and system in accordance with the present invention.
FIGS. 3A-3F
, show examples of valve configurations for various phases of sampling for a formation testing tool similar to that shown in FIG.
2
.
FIG. 4
shows a method for obtaining a formation fluid sample from a subsurface formation in accordance with the present invention.
FIG. 5
shows an example of steps for positioning a formation testing tool.
FIG. 6
shows an example of steps for inducing fluid flow from a subsurface formation into a formation testing tool.
FIG. 7
shows an example of steps for monitoring and controlling the pressure differential experienced by the formation fluid during a clean up and/or sample capturing operation.
FIG. 8
shows an example of steps for capturing a formation fluid sample.
DETAILED DESCRIPTION
The present invention provides a method and apparatus for sampling subsurface formations traversed by a borehole by controlling sampling pressures. In preferred embodiments, the method, advantageously, allows for manipulation of the borehole pressure after the formation pressure has been determined, which allows for control of the drawdown pressure and flow rate of formation fluid from the formation to the formation testing tool. In other embodiments, the method and apparatus may, advantageously, be used to obtain a single phase formation fluid sample from cased or openhole boreholes and/or provide for sampling without requiring a pump.
Exemplary embodiments of the present invention will now be described with reference to the accompanying figures.
FIG. 2
depicts a formation testing tool
300
and wellhead equipment
301
disposed about a borehole
340
having a casing
338
therein. The formation testing tool
300
is lowered into the cased borehole
340
on a work string
330
. The borehole
340
is in an “underbalanced” condition, meaning that the borehole wherein the borehole fluid disposed therein has a pressure that is less than the pressure of the formation(s)
312
to be sampled. The work string
330
is used to convey the formation testing tool
300
into the borehole
340
, and the wellhead equipment
301
is used to control and adjust the pressure of the borehole fluid in the borehole
340
. Examples of work strings may include cable, drill pipe, coiled tubing, etc.
The wellhead equipment
301
includes a work string sealing apparatus
328
, a pressure increasing device
332
(such as a pump) and a flow adjustment device
334
(such as a valve). The sealing apparatus
328
is positioned about the casing
338
to affect a pressure seal about the wellbore
340
. The sealing apparatus
328
may comprise any type of equipment or device known in the art for shutting in a borehole at the surface and/or affecting a pressure seal on a borehole around a work string. An example of a wellhead device used to seal wellbores is disclosed in U.S. Pat. No. 4,718,487 assigned to Hydrolex Inc.
The wellhead equipment
301
also includes a pressure increasing device
332
. The pressure increasing device
332
enables an increase of pressure on the borehole fluid in the borehole
340
. In
FIG. 2
, the pressure increasing device
332
includes a pump (not shown) disposed proximal the surface
303
and arranged in fluid communication with the borehole
340
. The wellhead equipment
301
may also include a controller (
333
) operationally coupled to the pressure increasing device
332
.
In addition to sealing apparatus
328
and the pressure increasing device
332
, the wellhead equipment
301
also includes a flow adjustment device
334
. The flow adjustment device
334
enables adjustment of the flow of borehole fluid from the borehole
340
and/or the pressure on tho borehole fluid in the borehole
340
. In
FIG. 2
, the flow adjustment device
334
is a flow valve, such as a metering valve or the like, which enables the adjustment of the flow of borehole fluid out of the borehole
340
. The controller (
333
) may also be operationally coupled to the flow adjustment device
334
. It will be realized by one of skill in the art that other combinations of valves and pumps are possible to achieve the same objective of controlling the pressure and/or flow of fluid to/from the borehole
340
. For example, a pump that allows flow in the reverse direction could be used to reduce wellhead pressure.
In the formation testing tool
300
, the probe assembly
306
comprises a probe capable of effecting sealing engagement on the inside surface of the borehole
340
. As shown in
FIG. 2
, the tool
300
engages the casing
338
lining the borehole
340
. The probe assembly
306
may be adapted to extend from the formation testing tool
300
and establish fluid communication between the formation testing tool
300
and the formation
312
.
As shown in
FIG. 2
, the conduit system
308
comprises internal fluid flow lines in the formation testing tool
300
. The conduit system
308
facilitates fluid communication within the formation testing tool
300
. The conduit system
308
includes a plurality of valves
314
,
316
,
318
,
320
and
322
to enable the selective directing of the formation fluid as it flows into and through the formation testing tool
300
.
In
FIG. 2
, the conduit system
308
includes at least two paths or passages. A first passage leads from the probe assembly
306
through the formation testing tool
300
to an exit port
342
. The first passage enables transferring of formation fluid directly to the borehole
340
, such as during a clean-up operation. The second passage leads from the probe assembly
306
through the formation testing tool
300
to the at least one sample tank
310
of the formation testing tool
300
.
In
FIG. 2
, the conduit system
308
also includes at least one pressure sensing device
324
(or
323
), such as a pressure gauge or the like, disposed proximal the probe assembly
306
. The pressure sensing device
324
enables monitoring of the formation pressure based on the pressure of the formation fluid entering the conduit system
308
from the formation
312
. Valves
314
,
318
are disposed in the conduit system
308
downstream of the pressure sensing device
324
. When the valves
314
,
318
are positioned in the closed position, pressure in the conduit system
308
between the probe
306
and valves
318
,
314
is allowed to build up to the formation pressure. This positioning provides accurate measurements of the pressure of formation fluid entering the conduit system
308
from the formation
312
. “Downstream” of the pressure sensing device is used herein to mean positioned in the conduit system
308
further away from the probe assembly
306
than the pressure sensing device
324
.
In
FIG. 2
, the conduit system
308
also preferably includes a second pressure sensing device
323
disposed proximal the exit port
342
leading to the borehole
340
. The second pressure sensing device
323
is positioned to enable monitoring of the pressure of borehole fluid in the borehole
340
. While it is desirable to have more than one pressure gauge, any number of pressure gauges may be used to determine downhole sampling conditions. By having two or more pressure gauges, it is possible to simultaneously determine wellbore pressure (P
H
) and formation pressure (P
F
), and the pressure differential P
H
versus P
F
.
At least one valve
314
is preferably disposed upstream of the pressure sensing device
323
. When the valve
314
is positioned in the closed position, the pressure sensing device
323
can be used to obtain an accurate measurement of the pressure of the borehole fluid in the borehole
340
. “Upstream” of the pressure sensing device
323
as used herein means positioned in the conduit system
308
further away from the exit port
342
than the pressure sensing device
323
.
The sample tank
310
is arranged in fluid communication with the internal conduit system
308
. The sample tank
310
is adapted to accept and retain an amount of formation fluid transferred thereto. As shown in
FIG. 2
, the sample tank
310
includes a first variable volume (hereafter referred to as the sample chamber
310
A) and a second variable volume (hereafter referred to as the buffer chamber
310
B). The sample chamber
310
A and the buffer chamber
310
B of the sample tank
310
are separated by a movable fluid separator
310
C, such as a piston, disposed there between. The movement of the fluid separator
310
C results in a change in the volume on the sample chamber
310
A and the buffer chamber
310
B of the sample tank
310
.
The moveable fluid separator
310
C may be a piston, diaphragm, or the like. in
FIG. 2
, the moveable fluid separator
310
C is adapted to move along the interior of the sample tank
310
between a first position proximal an entrance port
313
A on the sample chamber
310
A of the sample tank
310
and a second position proximal an exit port
313
B on the buffer chamber
310
B of the sample tank
310
. The sample tank
310
is arranged such that the sample chamber
310
A is in fluid communication with the conduit system
308
and the buffer chamber
310
B is in fluid communication with the borehole
340
. Additionally, a valve could be positioned between the buffer chamber
310
B and the exit port
313
B. This would allow a sample to be overpressured before retrieval at surface.
In the example shown in
FIG. 2
, the formation testing tool
300
is lowered into the borehole
340
using a work string
330
. Casing
338
is disposed in the borehole
340
and fixed in place using cement
336
. The borehole
340
is filled with borehole fluid selected to have a hydrostatic pressure that is less than the formation pressure at the desired depth. The probe assembly
306
that extends from the formation testing tool
300
engages with the casing
338
. Fluid communication is initiated between the formation testing tool
300
and the subsurface formation
312
by perforating or drilling a fluid channel
307
through the casing
338
and cement
336
to the formation
312
. The tool
300
may optionally be provided with additional devices, such as perforation module
339
, for creating fluid channels in the wellbore. Techniques and devices for creating fluid channels are described in U.S. Pat. No. 5,692,565 to MacDougall. As shown in
FIG. 3A
, valves
314
,
316
can be opened to allow debris and contaminates to be washed from the formation
312
to the borehole
340
as fluid communication is initiated.
Referring to
FIG. 2
, the wellhead equipment
301
is applied to the borehole
340
and sealed using the sealing apparatus
328
. The pressure increasing device
332
of the wellhead equipment
301
may be manipulated to increase the pressure of the borehole fluid in the borehole
340
to a selected pressure proximal to the formation pressure. For example, if the pressure increasing device
332
is a pump, additional borehole fluid is pumped into the borehole to increase the pressure of the borehole fluid. Alternatively, the borehole pressure may be increased by introducing a fluid or material into the borehole
340
which has a greater density than the borehole fluid. Because the formation pressure is greater than the borehole pressure, the difference between the formation pressure and the borehole pressure causes formation fluid to flow from the formation
312
into the formation testing tool
300
.
As shown in
FIG. 3B
, the pressure differential between the formation
312
and the borehole
340
may be monitored and adjusted to result in a desired drawdown of fluid from the formation
312
by closing the valve
314
between the probe
306
and borehole exit port
342
, closing valve
318
and opening the valve
316
proximal to the exit port
342
to expose the first and the second pressure sensing devices
324
,
323
to isolated formation pressure and borehole pressure, respectively.
A clean-up operation may be carried out prior to capturing a sample in at least one sample tank
310
. For example, as shown in
FIG. 3C
, valves
314
,
316
in the conduit system
308
between the probe assembly
306
and the borehole exit port
342
can be opened and the valve
318
closed to direct formation fluid from the formation to the borehole
340
.
Alternatively, as shown in
FIG. 3D
, valves
314
,
318
, and
322
in the conduit system
308
between the probe assembly
306
and a borehole exit port
343
can be opened and the valves
316
and
320
closed to direct formation fluid to exit the formation testing tool
300
at a location above the point of sampling (alternatively, can also be below). A fluid analyzer (not shown) may be disposed in the path between the probe assembly
306
and a borehole exit port
343
to enable monitoring of the formation fluid as it flows from the formation
312
. A sample tank
310
may also be disposed in the path between the probe assembly
306
and a borehole exit port
343
to enable a sample of formation fluid to be collected as it flows from the formation
312
. Formation fluid may be directed to the borehole exit port
343
until the fluid analyzer (not shown) determines that the formation fluid flowing from the formation is substantially free of contaminants and debris.
As shown in
FIG. 3E
, for capturing a sample, a valve
320
is disposed proximal the entrance port
313
A on the sample chamber
310
A of the sample tank
310
. The valve
320
enables selective transfer and/or capture of fluid from the conduit system
308
to the sample tank
310
. For example, the sample tank
310
is configured such that when valves
318
and
320
are opened and
322
is closed, and the valves
314
and/or
316
are closed, the higher pressure formation fluid from the formation
312
is directed into the sample chamber
310
A of the sample tank
310
.
While FIGS.
2
and
3
A-
3
E depict a preferred arrangement of valves, gauges and conduits, it will be appreciated by one of skill in the art that the arrangement may be varied. For example, valves
318
,
314
and/or pressure gauges
323
,
324
may be repositioned along conduit
308
closer to probe assembly
306
. Other variations may also be envisioned.
The difference between the formation pressure and the borehole pressure results in the flow of formation fluid into the sample tank
310
. This results in the displacement of the movable fluid separator
310
C in a direction toward the exit port
313
B and expansion of the volume of the sample chamber
310
A of the sample tank
310
. As the moveable fluid separator
310
C is displaced, the volume of the buffer chamber
310
B of the sample tank
310
decreases and the moveable fluid separator
310
C forces the lower pressure fluid of the buffer chamber
310
B of the sample tank
310
out of the exit port
313
B and into the borehole
340
.
Formation fluid may continue to flow through the conduit system
308
and into the sample tank
310
until the moveable fluid separator
310
C comes to rest against a surface on the buffer chamber
310
B of the sample tank
310
. After the moveable fluid separator
310
C comes to rest against the surface on the buffer chamber
310
B of the sample tank
310
, the pressure of the formation fluid on the sample chamber
310
A of the sample tank
310
may be allowed to increase until it equalizes the pressure of the formation fluid entering the conduit system
308
. Once formation fluid has been captured in the sample tank
310
, the valve
320
may be closed to retain the captured formation fluid sample in the sample tank
310
. The sample pressure can then be increased by increasing the borehole pressure to a desired level. The port
313
B may be provided with an exit port valve that may be closed to trap and/or isolate the sample tank
310
.
Referring to
FIG. 2
, once a formation sample has been captured in the formation testing tool as described above, the communication path from the formation testing tool
300
to the formation
312
may be plugged using the perforation module
339
as described in U.S. Pat. No. 5,692,565 to MacDougall. The formation testing tool
300
is then disengaged from the borehole
340
and moved to another location to perform additional sampling operations or retrieved at the surface.
Those skilled in the art will appreciate that embodiments of the present invention may be carried out under manual control or automatic control from the surface. For example, a pressure increasing device
332
included in the wellhead equipment
301
may be controlled manually by an operator monitoring the downhole pressure differential between the borehole and the formation, which may be transmitted to the surface by any method known in the art. The pressure increasing device
332
may be manipulated automatically using a controller (
333
) which based on downhole pressure readings and selected conditions automatically adjusts the pressure of the fluid in tile borehole to maintain it within a selected range.
The wellhead equipment, advantageously, allows for manipulation, regulation, and/or control of pressure in the borehole at the depth of the sampling operation. In other embodiments, wellhead equipment may include additional equipment known in the art for controlling and adjusting borehole pressure during testing or sampling operations. The additional equipment required for specific embodiments of the invention may be determined by one of ordinary skill in the art without undue research or experimentation.
Those skilled in the art will appreciate that existing formation testing tools may be modified and used in accordance with an embodiment of the invention based on the above description. The aforementioned modifications can be determined by one of ordinary skill in the art without undue research or experimentation.
While embodiments of the invention may be carried out using any formation testing tool known in the art, preferred formation testing tools and techniques may include such sampling tools as those disclosed in U.S. Pat. No. 5,692,565 to MacDougall, U.S. Pat. No. 4,860,581 to Zimmerman and/or U.S. Pat. No. 4,929,139 to Zimmerman, all of which are assigned to Schlumberger Technology Corporation, the assignee of the present invention.
In another aspect, the present invention provides a method for sampling a subsurface formation without requiring a downhole pump. An exemplary embodiment in accordance with this aspect of the invention is illustrated in FIG.
4
.
In the method of
FIG. 4
, a formation testing tool is positioned in a borehole having borehole fluid therein such that the borehole pressure (P
H
) is less than the formation pressure (P
F
) at the desired depth for sampling. Fluid communication is established between the formation testing tool and the subsurface formation
420
and flow is induced into the formation testing tool by exposing an interior of the formation testing tool to the pressure differential between the formation and the borehole
430
. A sample of the formation fluid is captured in at least one sample tank by directing the formation fluid to the sample tank and exposing the sample tank to the pressure differential
440
.
As shown in
FIG. 5
, in one example, positioning of the formation testing tool includes filling the borehole with a borehole fluid selected to have a hydrostatic pressure that is less than the formation pressure at the desired depth
512
. The formation testing tool is then conveyed in the borehole
514
and set at the formation depth in sealing engagement with a wall of the borehole and adjacent to the subsurface formation
516
. The formation testing tool may be conveyed in the borehole by any method known in the art. For example, the formation testing tool may be conveyed by attaching the formation testing tool to a wireline cable, drill string, coiled tubing, jointed tubing, or other known work string. Setting the formation testing tool may include engaging a probe assembly of the formation testing tool with the borehole wall. Setting the formation testing tool may also include engaging stabilizing pads with an opposite side of the wellbore to stabilize the formation testing tool in the wellbore.
Once the formation testing tool is positioned in the borehole (
410
in FIG.
4
), fluid communication between the formation testing tool and the subsurface formation is established (
420
in FIG.
4
). Establishing fluid communication between the formation testing tool and the subsurface formation may include establishing a fluid channel through the wall of the borehole between a probe assembly in sealing engagement with the borehole wall and the subsurface formation to be sampled. In a cased borehole, establishing fluid communication may comprise drilling or perforating through casing and cement disposed in the borehole.
Referring to
FIG. 4
, once fluid communication between the formation testing tool and the formation is established
420
, flow from the formation is induced
430
. As shown in
FIG. 6
, in one example, inducing flow comprises exposing a first end of a conduit system in the formation testing tool to the fluid communication established between the formation testing tool and the subsurface formation
631
and exposing a second end of the conduit system to the fluid communication with the borehole
632
.
As shown in
FIG. 6
, inducing flow also comprises confirming that the borehole pressure is less than the formation pressure at (or proximal) the desired depth
634
and allowing fluid to flow between the first end and the second end of the conduit system
636
. The pressure drop experienced by the formation fluid may be controlled by manipulating a pressure changing device or a flow adjustment device at the surface to adjust the pressure of the borehole fluid
638
.
As shown in
FIG. 7
, in one example, confirming the borehole pressure is less than the formation pressure (
634
in
FIG. 6
) comprises measuring the borehole pressure
733
, measuring the formation pressure
735
, and comparing the borehole pressure measurement (P
H
) and the formation pressure measurement (P
F
)
737
to determine if the underbalanced pressure situation is within a desired range for cleanup and/or sampling. The borehole pressure is preferably measured proximal to the desired depth to obtain an accurate assessment of whether the desired underbalanced situation exists at the depth of investigation. If a desired underbalanced pressure situation does not exist, the surface pressure of the borehole fluid may be adjusted
739
and the effect on the borehole pressure at the desired depth monitored downhole until the desired underbalanced pressure situation is established. In a preferred embodiment, the borehole pressure is adjusted to maintain the pressure differential between the borehole and the formation to within a selected range to maintain the desired fluid sample in the single phase.
After fluid flow is induced, the formation fluid is captured in at least one sample tank. As shown in
FIG. 8
, capturing a formation fluid sample (
440
in
FIG. 4
) may comprise opening a flow path to a sample chamber of the sample tank
840
, closing a flow path directing formation fluid to the borehole
841
, and accepting formation fluid into a sample chamber of the sample tank
842
. The borehole fluid pressure is controlled using wellhead equipment to maintain a pressure differential between the borehole and the formation. The pressure differential is preferably kept to within a selected range to prevent phase separation of the formation fluid as it is transferred to and captured in the sample tank
843
.
Flow is accepted into the sample chamber of the sample tank until a moveable fluid separator comes to rest
844
. The moveable fluid separator comes to rest. The moveable fluid separator may seat or seal against the exit port leading out of the sample tank and into the borehole. Alternatively, the moveable fluid separator may be adapted to come to rest after collection of a selected volume of formation fluid.
Formation fluid is allowed to enter into the sample chamber of the sample tank until the pressure in the sample tank increases to a pressure proximal to formation pressure
845
. Formation fluid may enter the sample tank until the pressure in the sample tank substantially equals the formation pressure. The sample tank is then closed to retain the formation fluid therein
846
.
In some cases, overpressurizing a formation fluid sample may be desired to ensure that the captured sample is maintained in the single phase upon cooling when it is retrieved at the surface. In these cases, after closing the formation fluid in the sample chamber of the sample tank
846
, the borehole pressure is adjusted to a pressure higher than the formation pressure
847
. By exposing the sample tank to the adjusted higher borehole pressure, the formation fluid in the sample tank may be increased to a desired pressure above the formation pressure
848
. The pressure in the sample tank may be monitored by a pressure sensing device disposed in or proximal the sample tank, or by a pressure sensing device in communication with the borehole at the desired depth. Once the desired sample pressure is achieved, the buffer chamber of the sample tank can be closed to capture the formation fluid sample at the higher pressure
849
.
In another aspect, the present invention may also provide a method for performing a controlled formation test, such as a pretest, without requiring a downhole pump to control the drawdown rate of the formation fluid during the formation test. Embodiments in accordance with this aspect of the invention will be apparent to those of ordinary skill in the art in view of the above description.
The method may also comprise positioning a formation testing tool in a borehole having borehole fluid therein with a pressure less than the formation pressure such that a pressure differential exists there between. The formation testing tool includes at least one sample tank having two variable volumes therein on a sample chamber and a buffer chamber of the sample tank. The sample tank includes a moveable fluid separator disposed between the volumes. The movement of the moveable fluid separator results in a change in the volume on the sample chamber and the buffer chamber of the sample tank.
The method may further comprise establishing fluid communication between the formation testing tool and the formation and inducing movement of formation fluid from the formation into the formation testing tool by exposing an interior of the formation testing tool to the pressure differential. The method may also comprise drawing down a volume of formation fluid into the sample chamber of the sample tank by directing the formation fluid to the sample chamber and exposing the buffer chamber of the sample tank to the lower borehole pressure. The pressure differential across the moveable fluid separator in the sample tank, advantageously, results in the drawdown of formation fluid into the sample tank. The method may further comprise holding the volume on the sample chamber of the sample tank constant and allowing the pressure in the sample tank to build up to a pressure proximal the formation pressure.
In accordance with one or more embodiments of the invention, the borehole may be an open borehole that includes a mudcake build-up along the borehole wall to reduce the likelihood of the formation fluid flowing directly from the formation into the borehole during the sampling operation. In a preferred embodiment, the borehole may comprise casing and cement along the borehole wall to reduce or eliminate the likelihood of the formation producing fluid into the underbalanced borehole during the sampling operation. In one or more embodiments, the well may be shut-in at the surface after the formation testing tool is run into the borehole, and the surface pressure applied to the borehole fluid may be reduced to zero using wellhead equipment to ensure that the initial borehole pressure at the desired depth is lower than the pressure of the formation being sampled.
The borehole pressure may also be monitored and adjusted at any desired time during a sampling or testing operation. The borehole pressure may be monitored and adjusted during the initial inducement of flow into the formation testing tool, during a clean-up operation, and/or during the sample capturing operation. The flow (or pressure) may be monitored and adjusted to remain within a selected range so that a desired drawdown of formation fluid can be achieved. For example, based on monitored formation pressure measurements, a desired borehole pressure may be determined. Additionally, the surface pressure applied to the borehole fluid may be adjusted to produce the desired borehole pressure at the desired depth. Preferably, the borehole pressure is monitored and selectively adjusted to maintain a selected pressure differential that results in a formation fluid pressure drop that is as large as possible without crossing the bubble point pressure or the asphaltene onset pressure. By monitoring and controlling the pressure differential between the formation pressure and the borehole pressure to within a predetermined range, a formation fluid sample obtained in a single phase as it is collected by the formation testing tool.
The borehole fluid may also be selected to have a density that results in a desired hydrostatic pressure in the borehole that is less than the expected or known formation pressure at the desired depth. Examples of fluids that may be used to create an underbalanced pressure situation in a borehole include lighter density fluids, such as diesel based, water based, or oil based fluids. However, those skilled in the art will appreciate that any other type of fluid that results in an underbalanced pressure situation in the borehole may be used as the borehole fluid without departing from the spirit of the invention.
The fluid channel may also be established by penetrating, drilling, or perforating a tunnel between the formation testing tool and the subsurface formation. One example of a method known in the art that may be used to establish fluid communication between a formation testing tool and a subsurface formation in a cased borehole is described in detail in U.S. Pat. No. 5,692,565 to MacDougall et al., assigned to the assignee of the present invention. Those skilled in the art will appreciate that any method known in the art for establishing fluid communication between a formation testing tool and a subsurface formation may be adapted and used for other embodiments without departing from the spirit of the invention.
The moveable fluid separator in the sample tank may also be an expandable separator which separates a volume of fluid on the sample chamber of the sample tank from a volume of fluid on the buffer chamber of the sample tank. The moveable fluid separator between the sample chamber and the buffer chamber of the sample tank preferably maintains the separation of formation fluid entering the sample tank from the borehole fluid on the backside of the moveable fluid separator while allowing the pressure differential between the formation and the borehole to result in a drawdown of formation fluid into the sample tank.
A clean-up operation may also be performed prior to the capturing of a sample in the formation testing tool. The clean-up operation may comprise passing formation fluid from the formation testing tool to the borehole while analyzing the formation fluid for contaminates until the formation fluid is determined to be substantially free of contaminants (i.e., is detected to contain less than or equal to a selected amount of contaminates). The formation fluid may be analyzed using any method known in the art, including resistivity and optical analyzing methods.
The devices and methods described above may provide several advantages. For example, one or more embodiments may provide a method that advantageously provides the ability to manipulate borehole pressure after the actual formation pressure has been measured. This may allow for accurate control of the pressure drop experienced by the formation fluid during a sampling operation while eliminating concerns about downhole pump failure problems. In one ore more embodiments, by manipulating the borehole pressure from the surface, the drawdown pressure, and/or the flow rate of the formation fluid can be easily controlled and adjusted and conversion between an underbalanced and an overbalanced pressure situation can be easily achieved. In one or more embodiments, because the sampling operation is a stationary operation, it may be easy to establish a static seal on the work string using wellhead pressure gear.
Other advantages may include that establishing fluid communication between the formation testing tool and the subsurface formation can be done in an entirely underbalanced pressure situation, thereby, minimizing damage to the formation during this operation. In one or more embodiments, the borehole pressure may advantageously be adjusted to substantially equal the formation pressure, and then the drawdown rate of the formation fluid may be accurately adjusted from the surface to obtain a formation fluid sample in a single phase with a minimal pressure drop across the formation fluid as it is captured. Advantageously, techniques in accordance with the invention may be used to perform controlled pretests using large volume chambers.
Those skilled in the art will appreciate that although various techniques have been shown herein as used in a cased borehole environment the invention is not limited to cased boreholes. Rather, embodiments of the invention may be used for any type of borehole including openhole, cased, or lined boreholes, without departing from the spirit of the invention. For example, in an alternative embodiment, a method or apparatus in accordance with the invention may be used in an openhole well having a specialized mudcake disposed on the wellbore walls to reduce the possibility of the formation fluid producing into the wellbore during the underbalanced sampling operation.
While the invention has been described with respect to a limited number of embodiments, those skilled in the art, having benefit of this disclosure, will appreciate that other embodiments can be devised which do not depart from the scope of the invention as disclosed herein. For example, embodiments of the invention may be easily adapted and used to perform specific formation sampling or testing operations without departing from the spirit of the invention. Accordingly, the scope of the invention should be limited only by the attached claims.
Claims
- 1. A method for obtaining a formation fluid sample from a subsurface formation traversed by a borehole, the method comprising:positioning a formation testing tool in the borehole containing borehole fluid with a pressure less than formation pressure such that a pressure differential exists there between, the formation testing tool including a sample tank having a sample chamber, a buffer chamber, and a movable fluid separator disposed there between; establishing fluid communication between the formation testing tool and the formation; inducing movement of the formation fluid into the formation testing tool by exposing an interior of the formation testing tool to the pressure differential; and capturing a sample of the formation fluid in the sample tank by exposing the sample tank to the pressure differential.
- 2. The method of claim 1, wherein the capturing comprises directing the formation fluid to the sample chamber of the sample tank and exposing the buffer chamber of the sample tank to the borehole pressure.
- 3. The method of claim 1, wherein the positioning comprises:conveying the formation testing tool in the borehole; and setting the formation testing tool in sealing engagement with a wall of the borehole adjacent the subsurface formation.
- 4. The method of claim 3, wherein the setting the formation testing tool comprises engaging a probe assembly with the borehole wall.
- 5. The method of claim 4, wherein the establishing fluid communication comprises establishing a fluid channel through the wall of the borehole between the probe assembly and the subsurface formation.
- 6. The method of claim 3, wherein the borehole wall comprises casing and cement.
- 7. The method of claim 6, wherein the establishing fluid communication comprises drilling a fluid channel between the formation testing tool and the subsurface formation through the casing and cement.
- 8. The method of claim 6, wherein the establishing the fluid channel comprises perforating a fluid channel between the formation testing tool and the subsurface formation through the casing and cement.
- 9. The method of claim 1, wherein the formation testing tool further comprises a conduit system disposed therein adapted to direct fluid flow through the formation testing tool, and the inducing movement of formation fluid comprises:exposing a first end of the conduit system to the fluid communication with the formation; and exposing a second end of the conduit system to fluid communication with the borehole.
- 10. The method of claim 9, wherein the inducing movement of formation fluid further comprises:confirming the borehole pressure is less than the formation pressure at depth; and allowing fluid flow between the first end and the second end of the conduit system.
- 11. The method of claim 10, wherein the confirming comprises:measuring the borehole pressure proximal to formation depth; measuring the formation pressure; and comparing the borehole pressure and the formation pressure measurements.
- 12. The method of claim 11, wherein confirming further comprises adjusting the borehole pressure such that the pressure differential is within a selected range.
- 13. The method of claim 11, wherein the measuring the borehole pressure comprises exposing a pressure sensing device proximal the second end of the conduit system to the fluid communication with the borehole.
- 14. The method of claim 11, wherein the measuring the formation pressure comprises exposing a pressure sensing device proximal the first end of the conduit system to the fluid communication with the formation.
- 15. The method of claim 1, wherein inducing movement comprises manipulating the borehole pressure to control the pressure differential to within a predetermined range to prevent phase separation of the formation fluid during sampling.
- 16. The method of claim 1, wherein inducing movement further comprises:controlling a pressure drop experienced by the formation fluid by manipulating at least one of a flow adjustment mechanisms and a pressure increasing device disposed proximal an earth surface to adjust the pressure of the borehole fluid.
- 17. The method of claim 16, wherein borehole pressure is adjusted to substantially equal formation pressure and the flow rate of formation fluid into the formation tool is adjusted from the surface by selectively adjusting the borehole pressure.
- 18. The method of claim 16, wherein borehole pressure is adjusted to substantially equal formation pressure and the flow rate of formation fluid into the formation tool is adjusted from the surface by selectively adjusting the flowrate from the borehole at surface via a metering valve.
- 19. The method of claim 16, wherein the flow adjustment mechanism comprises a valve.
- 20. The method of claim 16, wherein the pressure increasing device comprises a pump.
- 21. The method of claim 16, wherein the borehole pressure is adjusted to a selected pressure so that the pressure drop experienced by the formation fluid is as large as possible without crossing at least one selected from the bubble point pressure and the asphaltene onset pressure to maintain the formation fluid in single phase as it moves into the formation testing tool.
- 22. The method of claim 1, wherein prior to the capturing, formation fluid is analyzed for contaminates as it flows into the formation testing tool and is directed to the borehole until the formation fluid is determined to contain an acceptable amount of contaminates therein.
- 23. The method of claim 1, wherein the directing the formation fluid to the sample tank comprises:opening the sample chamber of the sample tank; and closing an exit path in the formation testing tool to the borehole.
- 24. The method of claim 1, wherein the capturing further comprises accepting fluid flow into the sample chamber of the sample tank until said sample tank is substantially filled with formation fluid.
- 25. The method of claim 24, wherein the capturing further comprises accepting fluid flow into the sample chamber of the sample tank until the pressure in the sample tank increases to a pressure above the borehole pressure.
- 26. The method of claim 1, wherein the capturing further comprises monitoring and controlling the pressure differential between the formation pressure and the borehole pressure to within a predetermined range to prevent phase separation of the formation fluid during sampling.
- 27. The method of claim 1, wherein the capturing further comprises:sealing the formation fluid in the sample chamber of the sample tank; increasing the borehole pressure by manipulating the at least one pressure increasing device; allowing the pressure of the formation fluid in the sample tank to increase to a pressure above the formation pressure; and sealing in the buffer chamber of the sample tank to retain the formation fluid sample at the increased pressure.
- 28. The method of claim 1, wherein the moveable fluid separator comprises a free floating piston.
- 29. A method for performing a pretest, comprising:positioning a formation testing tool in a borehole having borehole fluid therein with hydrostatic pressure less than formation pressure such that a pressure differential exists there between, the formation testing tool including a variable volume sample tank having a sample chamber, a buffer chamber, and a movable fluid separator disposed there between; establishing fluid communication between the formation testing tool and the formation; inducing movement of formation fluid from the formation into the formation testing tool by exposing an interior of the formation tool to the pressure differential; drawing a volume of the formation fluid in the sample tank by directing the formation fluid to the sample chamber of the sample tank and exposing the buffer chamber of the sample tank to the borehole pressure, the pressure differential between the borehole and the formation pressure resulting in a drawdown of formation fluid from the formation into the sample tank; and holding the volume of the sampling chamber constant to allow pressure in the sampling chamber to build up to a pressure proximal to the formation pressure.
- 30. The method of claim 29, wherein the casing and cement are disposed in the wellbore, and the establishing fluid communication comprises establishing a fluid channel between the formation testing tool and the subsurface formation through the casing and cement.
- 31. The method of claim 29, wherein the formation testing tool further comprises a conduit system disposed therein to direct fluid flow therethrough, and the inducing movement of formation fluid comprises:exposing a first end of the conduit system to the fluid communication with the formation; exposing a second end of the conduit system to fluid communication with the borehole; confirming the borehole pressure is less than the formation pressure at depth; and allowing fluid flow between the first end and the second end of the conduit system.
- 32. The method of claim 29, wherein the inducing movement further comprises controlling a pressure drop experienced by the formation fluid by manipulating at least one of a flow adjustment mechanism and a pressure increasing device disposed proximal an earth surface to adjust the pressure of the borehole fluid.
- 33. The method of claim 32, wherein the borehole pressure is adjusted to a selected pressure so that the pressure drop experienced by the formation fluid is as large as possible without crossing at least one selected from the bubble point pressure and the asphaltene onset pressure to maintain the formation fluid in single phase as it moves into the formation testing tool.
- 34. The method of claim 29, wherein prior to the capturing, formation fluid is analyzed for contaminates as it flows into the formation testing tool and is directed to the borehole until the formation fluid is determined to contain less than an acceptable amount of contaminates therein.
- 35. The method of claim 29, wherein the capturing further comprises monitoring and controlling the pressure differential between the formation pressure and the borehole pressure to within a predetermined range to prevent phase separation of the formation fluid during sampling.
- 36. The method of claim 29, wherein inducing movement comprises manipulating the borehole pressure to control the pressure differential between the formation pressure and the borehole pressure to within a predetermined range to prevent phase separation of the formation fluid during sampling.
- 37. The method of claim 29, wherein inducing formation fluid flow comprises: regulating the pressure drop experienced by the formation fluid by manipulating the pressure of the borehole fluid using wellhead equipment at earth surface;transferring formation fluid from the formation into a sample tank by controlling the pressure differential between the formation pressure and the borehole pressure to within a predetermined range to prevent phase separation of the formation fluid during sampling.
- 38. The method of claim 29, wherein the inducing movement further comprises controlling a pressure drop experienced by the formation fluid by manipulating at least one of a flow adjustment mechanism and a pressure increasing device disposed proximal an earth surface to adjust the flow rate of the borehole fluid.
- 39. A sampling system for obtaining a formation fluid sample froma subsurface formation traversed by a borehole, the system comprising: formation testing tool adapted for placement in the borehole and including: a probe assembly adapted to establish fluid communication between the formation testing tool and the subsurface formation; at least one sample tank having a sample chamber adapted to accept formation fluid therein, a buffer chamber in fluid communication with the borehole, and a fluid separator disposed there between to maintain separation of fluid in the sample chamber and the buffer chamber of the sample tank; a conduit system adapted to direct fluid flow through the formation testing tool, the conduit system having a first end in fluid communication with the probe assembly, a second end in fluid communication with the borehole, and a third end in fluid communication with the sample chamber of the sample tank; and a wellhead disposed about the borehole proximal the surface and adapted to seal borehole fluid therein such that the borehole fluid is maintained at a desired pressure.
- 40. The sampling system of claim 39, wherein the wellhead comprises at least one pressure increasing device disposed in fluid communication with the borehole and adapted to enable selective increase of borehole fluid pressure in the borehole.
- 41. The sampling system of claim 40, wherein the wellhead farther comprises at least one flow adjustment device adapted to enable adjustment of borehole fluid flow out of the borehole.
- 42. The sampling system of claim 41, wherein the at least one flow adjustment device comprises a metering valve adapted to enable selective removal of borehole fluid from the borehole to decrease a hydrostatic pressure therein.
- 43. The sampling system of claim 42, wherein the wellhead equipment enables selective control to within a predetermined range to prevent phase separation of formation fluid during the sampling.
- 44. The sampling system of claim 41, further comprising a controller operationally coupled to the at least one pressure increasing device and the at least one flow adjustment device and adapted to automatically control fluid flow in and out of the borehole based on differential pressure measured downhole between the formation pressure and the borehole pressure during sampling.
- 45. The sampling system of claim 40, wherein the at least one pressure increasing device comprises a pump adapted to pump borehole fluid into the borehole to increase a hydrostatic pressure therein.
- 46. The sampling system of claim 39, wherein the internal conduit system comprises:a first path between the probe assembly and the borehole to enable fluid communication between the probe and the borehole; and a second path between the probe and the sample tank to enable fluid communication between the probe and the sample tank.
- 47. The sampling system of claim 39, wherein the internal conduit system further comprises at least one flow restriction device disposed in the first path to enable selective fluid communication therethrough.
- 48. The sampling system of claim 39, wherein the internal conduit system further comprises at least one flow restriction device disposed in the second path to enable selective fluid communication therethrough.
- 49. The sampling system of claim 39, wherein a pressure sensing device is disposed in the conduit system proximal the first end to enable a monitoring of formation pressure.
- 50. The sampling system of claim 39, wherein a pressure sensing device is disposed proximal the first end of the conduit system between the probe and at least one flow restriction device to enable selective isolation and measurement of formation pressure.
- 51. The sampling system of claim 39, wherein the second end of the conduit system is coupled to an exit port in the formation testing tool leading to the borehole and a flow restriction device is disposed in the conduit system proximal the exit port to enable selective fluid communication between the conduit system and the borehole.
- 52. The sampling system of claim 39, wherein a pressure sensing device is disposed proximal the second end of the conduit system to enable a monitoring of borehole pressure.
- 53. The sampling system of claim 39, wherein a pressure sensing device is disposed proximal the second end of the conduit system between at least one flow restriction device and a port to the borehole to enable selective isolation and measurement of borehole pressure.
- 54. The sampling system of claim 39, wherein the third end of the conduit system is coupled to an opening in the at least one sample tank and a valve is disposed in the conduit proximal the opening to enable selective fluid communication between the conduit system and the at least one sample tank.
- 55. The sampling system of claim 39, wherein a pressure sensing device is disposed proximal the sample tank and adapted to enable a monitoring of pressure in the sample tank.
- 56. The sampling system of claim 39, wherein the movable fluid separator comprises a free floating piston.
- 57. The sampling system of claim 39, wherein the wellhead equipment is arranged to enable surface manipulation of borehole pressure for selectively control of a pressure differential between formation pressure and the borehole pressure during sampling.
US Referenced Citations (27)
Foreign Referenced Citations (1)
| Number |
Date |
Country |
| 0 791 723 |
Aug 1997 |
EP |