An electric power system also known as an electrical grid, or just grid, is a network of interconnected components that typically involve a generation element (such as a nuclear power plant, a hydro-electric plant, or a smaller plant powered by gas fueled turbo generators), a transmission system (high voltage lines), a distribution system (lower voltage lines), and a set of customers or loads (lowest voltage levels). The connection between elements of the grid is accomplished through a set of step-up transformers (e.g., increasing voltage from a generating station to the transmission line) and step-down transformers (e.g., decreasing voltage from transmission lines into the distribution system via a substation equipped with such transformers). A healthy operation of the entire grid depends on healthy operation of each element of the grid. This is important from a cost perspective as well as safety perspective, which in turn makes optimal operation of the grid an important aspect even for policy makers, which is exemplified by Stan M. Kaplan's report to Congress, “Electric Power Transmission: Background and Policy Issues”, CRS Report for Congress, 2009.
The health of the grid and its components is typically ensured by automatic generation control (AGC), which is a system for adjusting power output across multiple generators at different power plants and substations, especially in response to changes in consumption, or load. Since inception of electricity and power generation, this control was accomplished with fixing a single generating unit as a reference for regulation and having the remaining generating units be controlled using the so-called “speed droop”. According to Woodward Corp, “Speed Droop and Power Generation”, Woodward Application Note 01302, 1991, speed droop is a governor (or prime mover driving a synchronous generator) function which reduces the governor reference speed as fuel position (load) increases and vice versa. With modernization of power generation control, multiple generation units are enabled in regulation, which reduces wear and tear of each individual unit's control mechanisms and improves overall system operation and performance.
The disclosed invention is in the general field of automatic generation control, which is accomplished through two primary methods. The first method is the Active Power (P) and Frequency (F) control, while the second method is Reactive Power (Q) and Voltage (V) control. When connected to the grid, the frequency of a power plant network is fixed by the grid. The P/F control in this case is P control only. The purpose of P control is threefold:
In cases where any sub-network operates in an island mode, the frequency of the sub-network is determined by the generators connected to the islanded part of the power plant network. In these cases the purpose of control is as follows.
Strictly speaking, Active Power and Frequency control is not part of the disclosed invention as a claim, however, it interacts with the claimed invention of Reactive Power and Voltage Control functionality and its overview is provided henceforth for completeness purposes only. Active (Real) Power and Frequency control is known in the art with a good background provided by Chien-Ning Yu, “Real Power and Frequency Control of Large Electric Power Systems under Open Access,” Master's Thesis, MIT, 1996.
It is imperative to have proper Active Power and Frequency controls in place in order to achieve optimal operation and avoid system collapse. It is known that frequency within a power grid is constant when the same amount of electrical power is produced as consumed by the loads, including system losses. This is the optimal system state, however, if this is not the case frequency changes will occur. For example, the frequency of the system is reduced when a load increase is not compensated for by a corresponding increase of the turbine power of the connected generators. The power deficit will then decelerate the generator rotors and consequently reduce the frequency. Frequency reductions may also arise when production is lost, e.g., as a consequence of failures in the system where various safety response mechanisms disconnect the failed equipment from the grid. Significant reductions in frequency could lead to system collapse, due to the fact that most power station equipment, e.g. power supply systems, does not tolerate abnormally low frequencies. On the other hand, a load reduction in the system which is not compensated for by a reduction of turbine power leads to frequency increases, which could also destabilize the entire system.
The reactive mechanism similar to P/F control is Q/V control. Precise voltage control is required to ensure correct operating conditions for generators and loads. Voltage control is directly related to production and distribution of reactive power. Reactive power is the power used to support the transfer of real or active power over transmission and distribution networks in alternating current (AC) power systems, which are the majority of systems in modern power generation. In other words, reactive power is a large part of the cost associated with power generation and is a metric of a grid's efficiency to provide power to customers. The reactive power output of generator is controlled by means of machine excitation. Also, since transformers do not produce or consume any reactive power (they actually absorb reactive power), the Q/V control algorithm has to operate on both generators and transformers. As described in Larsson U.S. Pat. No. 7,956,596 B2, transformer voltage control is accomplished by changing transformer tap positions, which changes the flow of reactive power through the transformer. The purpose of Q/V control is as follows.
It is important that the voltage deviations in the system are limited. This is of importance for the connected loads, but a “good” voltage profile is also essential for keeping the losses low and for utilizing the reactive reserves to establish a secure operation of the system. Voltage control is, as been pointed out earlier, a more local control than the frequency control. Uniqueness and novelty of the disclosed invention is in the methodology used to accomplish coordinated voltage control, while controlling the distribution of reactive power between substations and reducing of interaction between voltage control modules.
A method of coordinated voltage control for electric power systems is disclosed that focuses on control of distribution of reactive power between substations while minimizing the interaction between voltage control modules. The method is applicable to power systems with at least two substations and at least one load. The said control is accomplished by utilizing available control elements including transformers equipped with On Load Tap Changers and turbo generators equipped with Automatic Voltage Regulators. The said control is accomplished via the following steps. First, the algorithm assesses operating mode of each Voltage Control Module across both High Level and Low Level voltage substations. Second, the Master Voltage Controller uses a Proportional-Integral-Derivative control algorithm to regulate voltage across all turbo generators within the High Level voltages buses, where the primary process variable is the average of all high level bus voltages and secondary process variable is output by the reactive power exchange PID algorithms and the overall control action is the sum of primary and secondary control outputs. Third, the algorithm counteracts potentially destabilizing interactions between High and Low Level control modules by adjusting the Low Level set point using a correction coefficient (so called E ratio). Fourth, the system controls all the low level substations by incorporating the said correction coefficient using a set of PID control loops. Fifth, the system maintains predetermined relationships across all generators connected to each low level substation by matching functions of reactive power load rate using a flow rate balancing parameter, which is a scaling factor. Sixth, the system allows for the controller to make “course” adjustments using OLTC control mechanism to limit the exchange of reactive power with the power grid within operator specified dead band. And finally, seventh, the Voltage Control module calculates its response from the deviation of its voltage variable to manipulate the set points of the on load tap changers (OLTC) of the transformers which connect High Level Substation and Low Level Substation (or load) in a way that minimizes interaction between high voltage buses.
Details of the disclosed invention are illustrated on a specific example of a simplified power distribution system shown in
The main system transformers (T-1 through T-6) are used in voltage control operations and are equipped with On Load Tap Changers (OLTC). Each transformer's index indicates the to/from voltage transformation. For example, transformer T-3 index is 110/35, which means that T-3 transforms 110 kV of potential available in Substation 2 into 35 kV of potential in Substation 4. Also, transformer T-5 index is 10/110. Since Substation 5 is powered by turbo generators TG3 and TG4, which usually operate at 10 kV, T-5 steps-up 10 kV from Substation 5 into 110 kV in Substation 1. The diagonal arrow through the double circle transformer index indicates presence of an OLTC, while three circle symbol indicates a three winding potential transformer.
All gas turbine driven generators are equipped with voltage regulatory control systems. The network supplies five main loads (LOAD 1 through LOAD 5) of varying voltage. For example, LOAD 2 is connected to Substation 6 with a step-up transformer taking 10.5 kV into 35 kV.
The disclosed invention is embedded into the overall Power Control System (PCS) which controls generators and transformers in the various subsystems in order to achieve voltage control, reactive power control, active power control, and frequency control of the system. PCS produces set points for all generators and also controls the set points of the transformers' OLTC's.
One of the primary control functions of PCS is Active Power and Frequency Control. This is well known in the art and is provided in this document for reference and completeness purposes only due to the fact that P/F control interacts with the disclosed Voltage Control algorithms.
The primary control variable PV1 in MIC loop is the active power flow to/from grid. Its set point is denoted by SP1 and it is operator adjustable. MIC final control elements are the gas turbines' TG1-TG7 fuel controllers, which accept power (MW) set points from MIC. The secondary power load sharing control loop's purpose is to distribute the total load by equalizing appropriate variables. The primary control variables of Load Sharing Control Applications are MW load of each turbo generator. The set points for the load sharing control application is the average MW load of all generators operating in droop control mode.
The fundamental idea of droop control is that since all synchronous generators frequencies are set by the grid, each generator must run at the same speed. Let fTGi, pTGi, and NTGi be the frequency (in Hz), number of poles, and speed (in RPM) respectively of generator TGi, for i=1, . . . , 7. Then the following relationship holds:
fTGi=α·pTGi·NTGi (1)
where α is a constant. Therefore, frequency is directly proportional to speed. Next, depending on the rating (aka no load speed) of each generator's turbine RTGi and its full load speed FTGi, the droop percent is calculated according to equation (2).
Thus, droop can be thought of as a percentage change in rating (or design) speed required for 100% governor action. Since the frequency is fixed by the grid, so is each generator's speed, thus an increase in turbine speed reference increases RTGi-FTGi, which then drives the controller to increase fuel flow to increase power output. Thus, final control elements for load sharing control are the same as with active power flow control, which are gas turbines TG1-TG7 fuel controllers. The end result is that each turbo generator shares load which is proportional to its rating.
Let CVPTGi denote the fuel controller action issued by MIC PV1 loop (active power) and let CVLTGi denote the fuel controller action issued by MIC PV2 loop (load sharing). The final output from MIC is then given by equation (3).
MIC=Σi=17(CVPTGi+CVLTGi) (3)
In situations when the local power distribution network is isolated from the grid, frequency controls are enabled. The MIC control application uses an alternative control variable measuring network frequency. The frequency set points are operator adjustable and final control elements are still the gas turbines TG1-TG7 fuel controllers. Further detail on the relationship between active power control modules is provided in
Configuration decision within the MIC control application is active power vs frequency control, which depends on whether the network is connected to the grid (active power control) or is islanded (frequency control). If grid is connected, the active power flow between grid and power network is controlled by Active Power Control Module. The main objective of control then is to maintain active power flow by producing megawatt set points (MW SP) 31 and 32 to turbo generators TG1-TGN power controllers. The system uses PID computation algorithm to calculate each MW SP, where PID control itself is well known in the art, see for example, U.S. Pat. No. 8,907,643 B2 by Sreenivas et al. The Active Power Control Module interacts closely with the Load Sharing Control Module which keeps all operating generators within predefined range in accordance with the generator manufacturer and dispatcher recommendations.
If the network is islanded (i.e., if the grid is not connected), then the measured frequency is maintained by Frequency Control Module. Similar to active power control, a PID algorithm is used by the Frequency Control Module to produce MW SP's 31 and 32 for all turbo generators TG1-TGN, where N=7 in case of a power system shown in
Regardless of connection to the grid, both active power and frequency control modules interact with the Load Sharing Module. The module input is either frequency control output 35 or active power control output 36, and measured active power from turbo generators 33 and 34. The module processes measured active power received from TGs to calculate the average load sharing set point according to equation (4).
Next, the load sharing module analyzes the operating conditions of each unit and calculates the adjustments (if any) to be made to the main stream control output 37 and 38. It then sends the output adjustments to the MW set points for implementation.
The described design has the effect of maintaining headroom between actual and maximum turbine output for frequency response reserve as a result of its load sharing action. The load sharing function is designed to put all turbine-generators at the same per unit load with respect to their present-day maximum capacities. In addition, the MW control limits of each unit are settable by the control-room operator. This allows the operator to ensure the availability of frequency responsive reserve on each unit by setting the high control limit of the Load Sharing Module at a suitable value below what the operator knows to be the maximum capability in a given day.
The rest of the discussion centers on the key aspect of the disclosed invention, which is the Reactive Power and Voltage Control.
The second control loop is VIC1 which controls the reactive power and voltage for the 110 kV Substation 1. The primary control variable of the VIC1 controller is the 110 kV Substation 1 bus voltage, 41. Let δVIC1 be a predefined target variance for the VIC1 set point, which is operator adjustable or adjustable by Coordinated Master Controller, call the set point SP1. Then SP1 is allowed to vary in the following interval [SP1−δVIC1, SP1+δVIC1]. VIC1 final control elements are the Automatic Voltage Regulator (AVR) of TG5 as well as the OLTC's of T-5 and T-6 transformers.
The third control loop is VIC2 which controls the reactive power and voltage for the 110 kV Substation 2. The primary control variable of the VIC2 controller is the 110 kV Substation 2 bus voltage, 42. Let δVIC2 be a predefined target variance for the VIC2 set point, which is operator adjustable or adjustable by Coordinated Master Controller, call the set point SP2. Then SP2 is allowed to vary in the following interval [SP2−δVIC2, SP2+δVIC2]. VIC2 final control elements are the OLTC's of T-3 and T-4 transformers.
The fourth control loop is VIC3 which controls the reactive power and voltage for the 110 kV Substation 3. The primary control variable of the VIC3 controller is the 110 kV Substation 3 bus voltage, 43. Let δVIC3 be a predefined target variance for the VIC3 set point, which is operator adjustable or adjustable by Coordinated Master Controller, call the set point SP3. Then SP3 is allowed to vary in the following interval [SP3−δVIC3, SP3+δVIC3]. VIC3 final control element is the AVR of TG-6 and the AVR of TG-7.
The fifth control loop is VIC4 which controls the reactive power and voltage for the 35 kV Substation 4. The primary control variable of the VIC4 controller is the 35 kV Substation 4 bus voltage, 44. Let δVIC4 be a predefined target variance for the VIC4 set point, which is operator adjustable or adjustable by Coordinated Master Controller, call the set point SP4. Then SP4 is allowed to vary in the following interval [SP4−δVIC4, SP4+δVIC4]. VIC4 final control element is the AVR of TG-1 and the AVR of TG-2.
The sixth control loop is VIC5 which controls the reactive power and voltage for the 10 kV Substation 5. The primary control variable of the VIC5 controller is the 10 kV Substation 5 bus voltage, 45. Let δVIC5 be a predefined target variance for the VIC5 set point, which is operator adjustable or adjustable by Coordinated Master Controller, call the set point SP5. Then SP5 is allowed to vary in the following interval [SP5−SP5+δVIC5]. VIC5 final control element is the AVR of TG-3 and the AVR of TG-4.
The seventh and last control loop is the VIC0 Load Sharing Control loop which distributes the total reactive load by equalizing appropriate variables. The primary control variables of the Reactive Power Load Sharing Control Application are the reactive power measures (MVAR) of each generator. Let QrTgi denote the rated reactive power of each turbo generator operating in droop control mode in a given power system. Then the reactive power load sharing control application set point is given by equation (5).
VIC0 load sharing application final control elements are similar to those of VIC1-VIC5, which are turbo generator AVR's and transformer OLTC's across the entire power system. Let CVQj denote the fuel controller action issued by Reactive Power Load Sharing Control Application and let CVVj denote the Master Controller loop/Voltage Control loops controller actions, where j spans the variety of AVR and OLTC actions. The final output from the VIC controller is then given by equation (6).
VIC=CVQj+CVVj (6)
The overall voltage control architecture can be thought of consisting of three distinct layers of control:
The disclosed invention utilizes different strategies to regulate voltage for High Voltage and Low Voltage substations. The strategy of High Level Substation voltage control is introduced in
Referring now to the power system shown in
Third, the kV PID algorithm uses kV set point 63 in conjunction with the computed PVkV to generate the module output 65.
The next series of steps is the invocation of the MVAR Export/Import Control Module, which distributes the total load by equalizing appropriate variables. In particular, fourth step involves calculation of the total Export/Import process variable 62. Let MVAR12 be the Export/Import MVAR value between Substation 1 and Substation 2. Let MVAR13 be the Export/Import MVAR value between Substation 1 and Substation 3. Then let PVMVAR be the primary control variable of the Export/Import Control Module, which is calculated as the average MVAR of all export/import distribution lines. In case of the power system displayed in
Each export/import distribution line has an operator adjustable set point. Let MVAR_SP12 be the operator adjustable set point value of reactive power export/import between Substation 1 and Substation 2. Let MVAR_SP13 be the operator adjustable set point value of reactive power export/import between Substation 1 and Substation 3. Fifth step is then for the Export/Import Control Module to calculate the overall export/import set point 64 according to equation (9)
The sixth step of the algorithm summarizes the output generated by step three (voltage control output 65) and step five (export/import control module output 66). Total output is the Master Voltage Control Output 67.
The seventh and final step of the algorithm is to counteract potentially destabilizing interactions between High and Low Level Control Modules by calculating a set point correction coefficient for the Low Level PID Voltage Controller. The kV set point 68 is combined with the computed PV 61 according to equation (10).
The correction coefficient is called the E ratio and is calculated as a ratio of Primary Process Control Variable and Primary Voltage Set Point. Finally, the algorithm sends the said set point correction coefficient to each Low Level Voltage Control Modules described in the next section of the disclosed invention.
Low Level Substation voltage control uses the High Level Substation voltage control as input and its overall strategy is shown in
The main objective of Voltage Control Module is to maintain voltage by producing set point 70 to the turbo generators' AVR's. The voltage control module algorithm has three inputs: substation measured voltage 73, operator adjustable set point 72, and the E Ratio Re calculated by the High Level Control module. The control module uses a PID algorithm to calculate turbo generator's AVR set points 70. The set point 71 being fed into the PID algorithm is calculated by equation (11).
SP=kV SP·Re (11)
The PID algorithm is then executed using PV 73 and SP 71. Referring now to the power system shown in
In such multi-unit generator settings, the disclosed invention provides a load sharing function which allows balancing of the reactive power output among all the generators. Let PVlsi denote the load rate (or load sharing process variable 77) of each generator with i=1, . . . , N. Then the load rate is computed according to equation (12).
Each turbo generator's load sharing algorithm step then compares PVlsi with the average load rate (or Load Sharing Set Point 74), where SP 74 is given by equation (13).
If each unit Load Sharing Process Variable is different from Load Sharing Set Point, a correction is carried out on each generator according to equation (14).
Where OUTlsi is the load sharing loop current scan output 75, OUTlsi(n-1) is the load sharing loop previous scan output and Δi is a parametrically defined load sharing ramp. Finally, the main TG set point 76 for each turbo generator is provided by equation (15).
OUTi=OUTlsi+M_OUT (15)
Thus each turbo generator control is the additive action of the main voltage control and load sharing control.
Next section of the disclosed invention relates to transformer control actions for the Low Level substations.
SP=kV SP·Re (16)
Where kV SP is operator adjustable and Re is the E Ratio calculated by the High Level Substation Module. This set point is split into High Voltage set point SPh and Low Voltage set point SPl using a dispatcher adjustable parameter δ according to equations (17) and (18).
SPh=SP+δ (17)
SPh=SP−δ (18)
This is done to ensure that the on load tap changers only change position whenever the demand value exceeds a set of predefined limits. The voltage control module provides the “Raise” R or “Lower” L commands to the OLTC control module based on conditions provided by equation (19).
Transformers' OLTC's can operate independently from each other or their steps can be coordinated. For example, if OLTC T2 Cascade mode is OFF and OLTC T1 Cascade mode is ON, then only T1 will execute Voltage Control Module's “Raise” and “Lower” commands. In case of coordination, the disclosed invention provides a load sharing function which allows balancing of the reactive power output among such transformers.
Each transformer's reactive power range (Qmin and Qmax) is defined based on rated power and flowing active power according to equations (20) and (21).
Qi_min=−√{square root over (MVAi2−MWi2)} (20)
Qi_max=√{square root over (MVAi2−MWi2)} (21)
For i={1,2}. Similar to above, the load rate is computed according to equation (22).
Each OLTC's load sharing algorithm step then compares PVlsiBT with the average load rate (or Load Sharing Set Point) given by equation (23).
If each unit Load Sharing Process Variable is different from Load Sharing Set Point, a correction is carried out on each transformer according to equation (24).
Where OUTTlsi is the transformer's load sharing loop current scan output, OUTTlsi(n-1) is the load sharing loop previous scan output and ∈i is a parametrically defined load sharing ramp.
The final step of the disclosed invention is the High Level Voltage Control Module control action; its architecture is shown in
The High Level Voltage Control Module action consists of three major components. These are the Export/Import Control Module, which distributes the total load by equalizing appropriate variables, the Voltage Control Module which provides the High and Low level set points, and the OLTC Control Module which adjusts tap changer positions to generate appropriate MVAR values.
The primary control variable of Export/Import Control Module is the average MVAR of all export/import distribution lines. Referring now to the power system shown in
Additionally, let MVAR 12 and MVAR 13 be the measured process variables for the exchange of reactive power between Substation 1 and Substation 2 and Substation 1 and Substation 3, respectively. Then the total export/import PV is given by equation (26).
Next step of the algorithm is the Voltage Control Module. The Set Point for control algorithm of High Level Voltage Control Module is the sum of the operator defined set point 91 and the Export/Import Control Module outputs 92; let this set point value be σ_SP. This set point is split into High Voltage set point H_SPh and Low Voltage set point H_SPl using a dispatcher adjustable parameter γ according to equations (27) and (28).
H_SPh=σ_SP+γ (27)
H_SPl=σ_SP−γ (28)
As before, this is made available by the disclosed invention to ensure that the on load tap changers only change position whenever the demand value exceeds a set of predefined limits. Similar to low level substation control, the voltage control module provides the “Raise” R or “Lower” L commands to the OLTC control module based on conditions provided by equation (29).
Transformers' OLTC's can operate independently from each other or their steps can be coordinated. For example, if OLTC T2 Cascade mode is OFF and OLTC T1 Cascade mode is ON, then only T1 will execute Voltage Control Module's “Raise” and “Lower” commands. In case of coordination, as with the low voltage control, the disclosed invention provides a load sharing function which allows balancing of the reactive power output among such transformers.
Similar to low level voltage control, each high voltage transformer's reactive power range (HL_Qmin and HL_Qmax) is defined based on rated power and flowing active power according to equations (30) and (31).
HL_Qi_min=−√{square root over (MVAi2−MWi2)} (30)
HL_Qi_max=√{square root over (MVAi2−MWi2)} (31)
For i={1,2}. The load rate is similarly computed according to equation (32).
Each OLTC's load sharing algorithm step then compares HL_PVlsiBT with the average load rate (or Load Sharing Set Point) given by equation (33).
If each unit Load Sharing Process Variable is different from Load Sharing Set Point, a correction is carried out on each transformer according to equation (34).
Where HL_OUTTlsi is the transformer's load sharing loop current scan output, HL_OUT Tlsi(n-1) is the load sharing loop previous scan output and θi is a parametrically defined load sharing ramp.
This application claims priority under 35 U.S.C. § 119 to provisional application Ser. No. 62/220,642, filed Sep. 18, 2015, herein incorporated by reference in its entirety.
Number | Name | Date | Kind |
---|---|---|---|
6549880 | Willoughby | Apr 2003 | B1 |
6614631 | Drake | Sep 2003 | B1 |
8275485 | Schweitzer, III | Sep 2012 | B2 |
20040100341 | Luetzelschwab | May 2004 | A1 |
20040239298 | Norrga | Dec 2004 | A1 |
20040244470 | Vicci | Dec 2004 | A1 |
20060212737 | Chandra | Sep 2006 | A1 |
20060259255 | Anderson | Nov 2006 | A1 |
20070067625 | Jiang | Mar 2007 | A1 |
20110157942 | Babcock | Jun 2011 | A1 |
20120134061 | Kasztenny | May 2012 | A1 |
20130099574 | Bourgeois | Apr 2013 | A1 |
20130131878 | Wilkins | May 2013 | A1 |
20130187464 | Smith | Jul 2013 | A1 |
20130307494 | Meinecke | Nov 2013 | A1 |
20150155712 | Mondal | Jun 2015 | A1 |
20150180355 | Freeman | Jun 2015 | A1 |
20150364919 | Schumer | Dec 2015 | A1 |
20160118878 | Alteneiji | Apr 2016 | A1 |
20160224045 | Wong | Aug 2016 | A1 |
Number | Date | Country | |
---|---|---|---|
20170085086 A1 | Mar 2017 | US |
Number | Date | Country | |
---|---|---|---|
62220642 | Sep 2015 | US |