This invention relates to a) the warming of cold fluids, such as liquefied natural gas (LNG), using a heat exchanger and b) the storage of the resulting fluid in an uncompensated salt cavern. In an alternative embodiment, a conventional vaporizer system can also be used to warm a cold fluid prior to storage in an uncompensated salt cavern.
Much of the natural gas used in the United States is produced along the Gulf Coast. There is an extensive pipeline network both offshore and onshore that transports this natural gas from the wellhead to market. In other parts of the world, there is also natural gas production, but sometimes there is no pipeline network to transport the gas to market. In the industry, this sort of natural gas is often referred to as “stranded” because there is no ready market or pipeline connection. As a result, this stranded gas that is produced concurrently with crude oil is often burned at a flare. This is sometimes referred to as being “flared off”.
Different business concepts have been developed to more effectively utilize stranded gas. One such concept is construction of a petrochemical plant near the source of natural gas to use the gas as a feedstock for the plant. Several ammonia and urea plants have been constructed around the world for this purpose.
Another approach is to liquefy the natural gas at or near the source and to transport the LNG via ship to a receiving terminal. At the LNG receiving facility, the LNG is offloaded from the transport ship and stored in cryogenic tanks located onshore. At some point, the LNG is transferred from the cryogenic storage tanks to a conventional vaporizer system and gasified. The gas is then sent to market via a pipeline. At the start of this process, liquefaction may consume 9-10% of the LNG by volume. At the end of the process, the gasification may consume an additional 2-3% of the LNG by volume. To the best of Applicants knowledge, none of the existing conventional LNG facilities that use vaporizer systems thereafter store the resulting gas in salt caverns. Rather, the conventional LNG facilities with vaporizers transfer all of the resulting gas to a pipeline for transmission to market.
Currently there are more than 100 LNG transport ships in service worldwide and more are on order. LNG transport ships are specifically designed to transport the LNG as a cryogenic liquid at or below −250° F. and near or slightly above atmospheric pressure. Further, the ships run on the LNG and are counter-flooded to maintain a constant draft of about 40 feet. The LNG ships currently in service vary in size and capacity, but some hold about 3 billion cubic feet of gas (Bcf) (approx. 840,000 barrels) or more. Some of the ships of the future may have even greater capacity and as much as 5 Bcf. One of the reasons LNG is transported as a liquid is because it takes less space.
There are a number of LNG facilities around the world. In the U.S., two LNG receiving facilities are currently operational (one located in Everett, Mass. and one located south of Lake Charles, La.) and two are being refurbished (one located in Cove Point, Md. and one located at Elba Island, Ga.). Construction of additional LNG facilities in the U.S. has been announced by several different concerns.
The LNG receiving facilities in the U.S. typically include offloading pumps and equipment, cryogenic storage tanks and a conventional vaporizer system to convert the LNG into a gas. The gas may be odorized using conventional equipment before it is transmitted to market via a pipeline. LNG terminals are typically designed for peak shaving or as a base load facility. Base load LNG vaporization is the term applied to a system that requires almost constant vaporization of LNG for the basic load rather than periodic vaporization for seasonal or peak incremental requirements for a natural gas distribution system. At a typical base load LNG facility, a LNG ship will arrive every 3-5 days to offload the LNG. The LNG is pumped from the ship to the LNG storage tank(s) as a liquid (approx. −250° F.) and stored as a liquid at low-pressure (about one atmosphere). It typically may take 12 hours or more to pump the LNG from the ship to the cryogenic storage tanks onshore.
LNG transport ships may cost more than $100,000,000 to build. It is therefore expedient to offload the LNG as quickly as possible so the ship can return to sea and pick up another load. A typical U.S. LNG base load facility will have three or four cryogenic storage tanks with capacities that vary, but are in the range of 250,000-400,000 barrels each. Many of the current LNG ships have a capacity of approximately 840,000 barrels. It therefore will take several cryogenic tanks to hold the entire cargo from one LNG ship. These tanks are not available to receive LNG from another ship until they are again mostly emptied.
Conventional base load LNG terminals are continuously vaporizing the LNG from the cryogenic tanks and pumping it into a pipeline for transport to market. So, during the interval between ships (3-5 days), the facility converts the LNG to gas (referred to as regasification, gasification or vaporization) which empties the cryogenic tanks to make room for the next shipment. The LNG receiving and gasification terminal may produce in excess of a billion cubic feet of gas per day (BCFD). In summary, transport ships may arrive every few days, but vaporization of the LNG at a base load facility is generally continuous. Conventional vaporizer systems, well known to those skilled in the art, are used to warm and convert the LNG to usable gas. The LNG is warmed from approximately −250° F. in the vaporizer system and converted from liquid phase to usable gas before it can be transferred to a pipeline. Unfortunately, some of the gas is used as a heat source in the vaporization process, or if ambient temperature fluids are used, very large heat exchangers are required. There is a need for a more economical way to convert the LNG from a cold liquid to usable gas.
LNG cryogenic storage tanks are expensive to build and maintain. Further, the cryogenic tanks are on the surface and present a tempting terrorist target. There is therefore a need for a new way to receive and store LNG for both base load and peak shaving facilities. Specifically, there is a need to develop a new methodology that eliminates the need for the expensive cryogenic storage tanks. More importantly, there is a need for a more secure way to store huge amounts of flammable materials.
There are many different types of salt formations around the world. Some, but not all of these salt formations are suitable for cavern storage of hydrocarbons. For example, “domal” type salt is usually suitable for cavern storage. In the U.S., there are more than 300 known salt domes, many of which are located in offshore territorial waters. Salt domes are also known to exist in other areas of the world including Mexico, Northeast Brazil and Europe. Salt domes are solid formations of salt that may have a core temperature of 90° F. or more. A well can be drilled into the salt dome and fresh water can be injected through the well into the salt to create a cavern. Salt cavern storage of hydrocarbons is a proven technique that is well established in the oil and gas industry. Salt caverns are capable of storing large quantities of fluid. Salt caverns have high sendout capacity and most important, they are very, very secure. For example, the U.S. Strategic Petroleum Reserve now stores approximately 600,000,000 barrels of crude oil in salt caverns in Louisiana and Texas, i.e., at Bryan Mound, Tex.
When fresh water is injected into domal salt, it dissolves thus creating brine, which is returned to the surface. The more fresh water that is injected into the salt dome, the larger the cavern becomes. The tops of many salt domes are often found at depths of less than 1500 feet. A salt cavern is an elongate chamber that may be up to 1,500 feet in length and have a capacity that varies between 3-15,000,000 barrels. The largest is about 40 million barrels. Each cavern itself needs to be fully surrounded by the salt formation so nothing escapes to the surrounding strata or another cavern. Multiple caverns will typically be formed in a single salt dome. Presently, there are more than a 1,000 salt caverns being used in the U.S. and Canada to store hydrocarbons.
Two different conventional techniques are used in salt cavern storage-compensated and uncompensated. In a compensated cavern, brine or water is pumped into the bottom of the salt cavern to displace the hydrocarbon or other product out of the cavern. The product floats on top of the brine. When product is injected into the cavern, the brine is forced out. Hydrocarbons do not mix with the brine making it an ideal fluid to use in a compensated salt cavern. In an uncompensated storage cavern, no displacing liquid is used. Uncompensated salt caverns are commonly used to store natural gas that has been produced from wells. High-pressure compressors are used to inject the natural gas in an uncompensated salt cavern. Some natural gas must always be left in the cavern to prevent cavern closure due to salt creep. The volume of gas that must always be left in an uncompensated cavern is sometimes referred to in the industry as a “cushion”. This gas provides a minimum storage pressure that must be maintained in the cavern. Again, to the best of Applicants knowledge, none of the present LNG receiving facilities take the LNG from the tankers, vaporize it and then store the resulting gas in salt caverns.
Uncompensated salt caverns for natural gas storage preferably operate in a temperature range of approximately +40° F. to +140° F. and pressures of 1500 to 4000 psig. If a cryogenic fluid at sub-zero temperature is pumped into a cavern, thermal fracturing of the salt may occur and degrade the integrity of the salt cavern. For this reason, LNG at very low temperatures cannot be stored in conventional salt caverns. If a fluid is pumped into a salt cavern and the fluid is above 140° F. it will encourage creep and decrease the volume of the salt cavern.
The present invention is referred to as the Bishop One-Step Process. It eliminates the need for expensive cryogenic storage tanks. The present invention uses a high pressure pumping system to raise the pressure of the LNG from about one atmosphere to about 1200 psig or more. This increase in pressure changes the state of the LNG from a cryogenic liquid to dense phase natural gas (DPNG). The present invention also uses a unique heat exchanger called the Bishop Process heat exchanger mounted onshore or offshore to raise the temperature of the DPNG from about −250° F. to about +40° F. so the warmed DPNG can be stored in an uncompensated salt cavern. In addition, the DPNG can also be stored in other types of salt strata, provided the formation does not leak. All of these techniques eliminate the need for conventional surface mounted cryogenic storage tanks. Subsurface storage is more secure than conventional systems as demonstrated by the use of a salt cavern storage system by the Strategic Petroleum Preserve. Once the LNG has been warmed and converted from a liquid to DPNG using the present invention, it can also be transferred through a throttling valve or regulator into a pipeline for transport to market. In an alternative embodiment, a conventional vaporizer system can also be used to gasify the LNG prior to storage in an uncompensated salt cavern.
U.S. Pat. No. 5,511,905 is owned by the assignee of the present application. William M. Bishop is listed as a joint inventor on the present application and the '905 patent. This prior art patent discloses warming of LNG with brine (at approximately 90° F.) using a heat exchanger in a compensated salt cavern. This prior patent teaches storage in the dense phase in the compensated salt cavern. The '905 patent does not disclose use of an uncompensated salt cavern. The '905 patent also discloses that cold fluids may be warmed using a heat exchanger at the surface. The surface heat exchanger might be used where the cold fluids being offloaded from a tanker are to be heated for transportation through a pipeline. The brine passing through the surface heat exchanger could be pumped from a brine pond rather than the subterranean cavern.
U.S. Pat. No. 6,298,671 is owned by BP Amoco Corporation and is for a Method for Producing, Transporting, Offloading, Storing and Distributing Natural Gas to a Marketplace. The patent teaches production of natural gas from a first remotely located subterranean formation, which is a natural gas producing field. The natural gas is liquefied and shipped to another location. The LNG is re-gasified and injected into a second subterranean formation capable of storing natural gas which is a depleted or at least a partially depleted subterranean formation which has previously produced gas in sufficient quantities to justify the construction of a system of producing wells, gathering facilities and distribution pipelines for the distribution to a market of natural gas from the subterranean formation. The patent teaches injection of the re-gasified natural gas into the depleted or partially depleted natural gas field at temperatures above the hydrate formation level from 32° F. to about 80° F. and at pressures of from about 200 to about 2500 psig. This patent makes no mention of a salt cavern. This patent makes no mention of dense phase or the importance thereof. Furthermore, there are limitations on the injection and send our capacity of depleted and partially depleted gas reservoirs that are not present in salt cavern storage. In addition, temperature variances between the depleted reservoir and the injected gas create problems in the depleted reservoir itself that are not present in salt cavern storage. For all of these many reasons, salt caverns are preferred over cryogenic storage tanks or depleted gas reservoirs for use in a modern LNG facility.
The Bishop One-Step Process warms a cold fluid using a heat exchanger mounted onshore or a heat exchanger mounted offshore on a platform or subsea and stores the resulting DPNG in an uncompensated salt cavern. In an alternative embodiment, a conventional LNG vaporizer system can also be used to gasify a cold fluid prior to storage in an uncompensated salt cavern or transmission through a pipeline.
The term “cold fluid” as used herein means liquid natural gas (LNG), liquid petroleum gas (LPG), liquid hydrogen, liquid helium, liquid olefins, liquid propane, liquid butane, chilled compressed natural gas and other fluids that are maintained at sub-zero temperatures so they can be transported as a liquid rather than as gases. The heat exchangers of the present invention use a warm fluid to raise the temperature of the cold fluid. This warm fluid used in the heat exchangers will hereinafter be referred to as warmant. Warmant can be fresh water or seawater. Other warmants from industrial processes may be used where it is desired to cool a liquid used in such a process.
To accomplish heat exchange in a horizontal flow configuration, such as the Bishop One-Step Process, it is important that the cold fluid be at a temperature and pressure such that it is maintained in the dense or critical phase so that no phase change takes place in the cold fluid during its warming to the desired temperature. This eliminates problems associated with two-phase flow such as stratification, cavitation and vapor lock.
The dense or critical phase is defined as the state of a fluid when it is outside the two-phase envelope of the pressure-temperature phase diagram for the fluid (see FIG. 9). In this condition, there is no distinction between liquid and gas, and density changes on warming are gradual with no change in phase. This allows the heat exchanger of the Bishop One-Step Process to reduce or avoid stratification, cavitation and vapor lock, which are problems with two-phase gas-liquid flows.
A well 32 extends from the surface 22 through the earth 24 and into the salt dome 26. An uncompensated salt cavern 34 has been washed in the salt dome 26 using techniques that are well known to those skilled in the art. Another well 36 extends from the surface 22, through the earth 24, the salt dome 26 and into a second uncompensated salt cavern 38. The upper surface 40 of the salt dome 26 is preferably located about 1500 feet below the surface 22 of the earth, although salt domes occurring at other depths both onshore 27 or offshore 28 may also be suitable. A typical cavern 34 may be disposed 2,500 feet below the surface 22 of the earth 24, have an approximate height of 2,000 feet and a diameter of approximately 200 feet. The size and capacity of the cavern 34 will vary. Salt domes and salt caverns can occur completely onshore 27, completely offshore 28 or somewhere in between. A pipeline 42 has been laid under the surface 22 of the earth 24.
A dock 44 has been constructed on the bottom 46 of a harbor, not shown. A cold fluid transport ship 48 is tied up at the dock 44. The cold fluid transport ship 48 typically has a plurality of cryogenic tanks 50 that are used to store cold fluid 51. The cold fluid is transported in the cryogenic tanks 50 as a liquid having a sub-zero temperature. Low-pressure pump systems 52 are positioned in the cryogenic tanks 50 or on the transport ship 48 to facilitate off loading of the cold fluid 51.
After the cold fluid transport ship 48 has tied up to the dock 44, an articulated piping system 54 on the dock 44, which may include hoses and flexible loading arms, is connected to the low-pressure pump system 52 on the transport ship 48. The other end of the articulated piping system 54 is connected to high-pressure pump system 56 mounted on or near the dock 44. Various types of pumps are used in the LNG industry including vertical, multistaged deepwell turbines, multistage submersibles and multistaged horizontal.
When it is time to begin the off loading process, the low-pressure pump system 52 and the high-pressure pump system 56 transfer the cold fluid 51 from the cryogenic tanks 50 on the transport ship 48 through hoses, flexible loading arms and articulated piping 54 and additional piping 58 to the inlet 60 of a heat exchanger 62 used in the present invention. When the cold fluid 51 leaves the high-pressure pump system 56 it has been converted to a dense phase fluid 64 because of the pressure imparted by the pump. The term dense phase is discussed in greater detail below concerning FIG. 9. The Bishop Process heat exchanger 62 will warm the cold fluid to approximately +40° F. or higher, depending on downstream requirements. This heat exchanger makes use of the dense phase state of the fluid and a high Froude number for the flow to ensure that stratification, phase change, cavitation and vapor lock do not occur in the heat exchange process, regardless of the orientation of the flow with respect to gravity. These conditions are essential to the warming operation and are discussed in detail below in connection with FIG. 9. When the cold fluid 51 leaves the outlet 63 of the heat exchanger 62, it is a dense phase fluid 64. A flexible joint 65 or an expansion joint is connected to the outlet 63 of the heat exchanger 62 to accommodate expansion and contraction of the cryogenically compatible piping 61, better seen in
Piping 70 connects the heat exchanger 62 with a wellhead 72, mounted on a well 36. Additional piping 74 connects the heat exchanger 62 with another wellhead 76, mounted on the well 32. The high-pressure pump system 56 generates sufficient pressure to transport the dense phase fluid 64 through the flexible joint 65, the piping 70, through the wellhead 72, the well 36 into the uncompensated salt cavern 38. Likewise the pressure from the high-pressure pump system 56 will be sufficient to transport the dense phase fluid 64 through the flexible joint 65, the piping 70 and 74, through the wellhead 76 and the well 32 into the uncompensated salt cavern 34. Dense phase fluid 64 therefore can be injected via the wells 32 and 36 for storage into uncompensated salt caverns 34 and 38.
In addition, dense phase fluid 64 can be transferred from the heat exchanger 62 through piping 78 to a throttling valve 80 or regulator which connects via additional subsurface or surface piping 84 to the inlet 86 of the pipeline 42. The dense phase fluid 64 is then transported via the pipeline 42 to market. (The pipeline 42 may also be on the surface.)
If additional pumps are needed, they may be added to the piping system at appropriate points, not shown in this schematic. The cold fluid 51 may also be delivered to the facility 19 via inland waterway, rail or truck, not shown.
The first section 100 of the heat exchanger 62 includes a central cryogenically compatible pipe 61 and an outer conduit 104. (High nickel steel pipe may be suitable in this low temperature application). The interior cryogenically compatible conduit 61 is positioned at or near the center of the outer conduit 104 by a plurality of centralizers 106, 108 and 110.
A warmant 99 flows through the annular area 101 of the first section 100 of heat exchanger 62. The annular area 101 is defined by the outside diameter of the cryogenically compatible pipe 61 and the inside diameter of the outer conduit 104.
The second section 102 of the heat exchanger 62 is likewise formed by the cryogenically compatible pipe 61 and the outer conduit 112. The cryogenically compatible pipe 61 is positioned, more or less, in the center of the outer conduit 112 by a plurality of centralizers 114, 116 and 118. All of the centralizers, 106, 108, 110, 114, 116 and 118, are formed generally the same as shown in FIG. 6.
A first surface reservoir 120, sometimes referred to as a pond, and a second surface reservoir 122 are formed onshore 27 near the heat exchanger 62 and are used to store warmant 99. Piping 124 connects the first reservoir 120 with a low-pressure pump 126. Piping 128 connects the low-pressure pump 126 with ports 130 to allow fluid communication between the reservoir 122 and the first section 100 of heat exchanger 62. The warmant flows through the annular area 101 as indicated by the flow arrows and exits the first section 100 of the heat exchanger 62 at ports 132 as indicated by the flow arrows. Additional piping 134 connects the ports 132 with the second reservoir 122.
Piping 136 connects the first reservoir 120 with low-pressure pump 138. Piping 140 connects low-pressure 138 with ports 142 formed in the second section 102 of the heat exchanger 62. The warmant is pumped from the first reservoir 120 through the pump 138 into the annular area 103 between the outside diameter of the cryogenically compatible pipe 61 and the inside diameter of the outer conduit pipe 112. The warmant 99 flows through the annular area 103 of the second section 102 of the heat exchanger 62 as indicated by the flow arrows and exits at the ports 144 which are connected by pipe 146 to the second reservoir 122. The cold fluid 51 enters the inlet 60 of the heat exchanger 62 as a cold liquid and leaves the outlet 63 as a warm dense phase fluid 64. The cryogenically compatible pipe 61 is connected to a flexible joint 65 to account for expansion and contraction of the cryogenically compatible pipe 61. All piping downstream of flexible joint 65 is not cryogenically compatible.
In the parallel flow configuration of
It is important to avoid freez-up of the heat exchanger 62. Freez-up blocks the flow of warmant 94 and renders the heat exchanger 62 inoperable. It is also important to reduce or eliminate icing. Icing renders the heat exchanger 62 less efficient. It is therefore necessary to carefully design the area, generally identified by the numeral 63 where the cold fluid 51 in the pipe 61 first encounters the warmant 99 in the annular area 101 of the first section 100 of the heat exchanger 62. Here it is necessary to prevent or reduce freezing of the warmant 99 on the pipe 61, which could block the ports, 130 and the annular area 101. In most cases, it is possible to choose flow rates and pipe diameter ratio such that freezing is not a problem. For example, if a dense phase natural gas expands by a factor of four in the warming process, the heat balance then indicates that the warmant flow rate is required to be four times that of the inlet dense phase. This results in a diameter ratio of two (outer pipe/inner pipe) in order to balance friction losses in the two paths. However, the heat transfer rate is improved if the diameters are closer together. An optimum ratio is approximately 1.5. Where conditions are extreme, it is possible to prevent local freezing by increasing the thermal insulation at the wall of the cryogenically compatible pipe 61 in this region 63. One method for doing this is to simply increase the wall thickness of the pipe 61. This has the effect of pushing some of the warming function downstream to where the cold fluid 51 has already been warmed to some extent, and the possibility of freezing has been reduced. This may also increase the length of the heat exchanger.
In an alternative flow arrangement, the warmant 99 leaves the annular area 103 through the ports 142 and is transferred through the piping 212, shown in phantom, back to the second reservoir 122 making a continuous loop from and to the second reservoir 122. Likewise warmant 99 can be transferred from the first reservoir 120 through piping 214, as shown in phantom, to the pump 138, piping 206 through the ports 132 into the annular area 101 of the first section 100 of the heat exchanger 62. The warmant is then returned through the ports 130 and the piping 210 to the first reservoir 120.
The design of the heat exchanger 62 and the number of surface reservoirs is determined by a number of factors including the amount of space that is available and ambient temperatures of warmant 99. For example, if the warmant 99 has an average temperature of more than 80° F., the heat exchanger 62 may only need one section. However, if the warmant 99 is on average less than 80° F., two or more segments may be necessary, such as the two-segment design shown in
This hypothetical example is merely designed to give broad operational parameters for the Bishop One-Step Process conducted at or near dockside as shown in
Assume that 800,000 barrels of LNG (125,000 cubic meters) are stored in the cryogenic tanks 50 on the transport ship 48 at approximately one atmosphere and a temperature of −250° F. or colder. The low-pressure pump system 52 has the following general operational parameters: approx. 22,000 gpm (5000 m3/hr) with approx. 600 horsepower to produce a pressure of approximately 60 psig (4 bars). Due to frictional losses approximately 40 psig is delivered to the intake of the high-pressure pump system 56. The high-pressure pump system 56 will raise the pressure of the LNG typically to 1860 psig (120 bars) or more so that the cold fluid 51 will be in the dense phase after it leaves the high-pressure pump system 56. There are approximately ten pumps in the high-pressure pump system 56, each with a nominal pumping rate of 2,200 gpm (500 m3/hr) at a pressure increase of1860 psig (120 bars), resulting in approximately 1900 psig (123 bars) available for injection into the uncompensated salt caverns 34 and 38. The total required horsepower for the ten high-pressure pump system is approximately 24,000 hp. This represents the maximum power required when the uncompensated salt caverns are fully pressured, i.e. when they are full. The average fill rate may be higher than 22,000 gpm (5000 m3/hr). Assuming 13⅜″ nominal diameter pipe in the injection wells 32 and 36, approximately four uncompensated salt caverns having a minimum total capacity of approximately 3 billion cubic feet. The volume of the LNG will generally expand by a factor 2-4 during the heat exchange process, depending on the final pressure in the uncompensated salt cavern. Larger injection wells are feasible, along with more caverns if higher flows are needed.
Pumps 124 and 138 for the warmant 99 will be high-volume, low-pressure pump system with a combined flow rate of about 44,000 gpm (10,000 m3/hr) at about 60 psig (4 bars). The flow rate of the warmant through the heat exchanger 62 will be approximately two to four times the flow rate of the LNG through the cryogenically compatible tubing 61. The flow rate of the warmant will depend on the temperature of the warmant and the number of sections in the heat exchanger. (Each section has a separate warmant injection point.) The warmant could be treated for corrosion and fouling prevention to improve the efficiency of the heat exchanger 62. As the dense phase fluid 64 passes through the heat exchanger 62 it warms and expands. As it expands, the velocity increases through the heat exchanger.
Assuming an LNG flow rate of 22,000 gpm the heat exchanger 62 could have a cryogenically compatible center pipe 61 with a nominal outside diameter of approximately 13⅜ inches and the outer conduits 104 and 112 could have a nominal outside diameter of approximately 20 inches. The overall length of the heat exchanger 62 would be long enough, given the temperature of the warmant and other factors to allow the dense phase fluid 64 to reach a temperature of about 40° F. This could result in an overall length of several thousand feet and perhaps in the neighborhood of 5,000 feet. Multiple warmant injection points and parallel flow lines can greatly reduce this length. Depending on the distance from the receiving point to the storage space, the length may not be a problem. Parallel systems may also be used depending on the size of the facility and the need for redundancy. Pipe size and length can be greatly reduced by dividing the LNG flow into separate parallel paths. Two parallel heat exchangers 62 could have a cryogenically compatible center pipe 61 with a nominal outside diameter of approximately 8 inches and the outer conduits 104 and 112 could have a nominal outside diameter of approximately 12 inches. Use of parallel heat exchangers 62 is a design choice dependent upon material availability, ease of construction, and distance to storage.
In addition, the heat exchanger 62 need not be straight. To conserve space, or for other reasons the heat exchanger 62 may adopt any path such as an S-shaped design or a corkscrew-shaped design. The heat exchanger 62 can have 90° elbows and 180° turns to accommodate various design requirements.
If the dense phase fluid 64 is to be stored in an uncompensated salt cavern 34, one first needs to determine the minimum operational pressure of the salt cavern 34. For example, hypothetically, if the uncompensated cavern 34 had a maximum operating pressure of about 2,500 psig, the high-pressure pump system 56 would have the ability to pump at 2,800 psig or more. Of course operating at less than maximum is also possible, provided that pressure exceeds about 1,200 psig to maintain dense phase.
If the cold fluid 51 is to be heated and transferred directly into the pipeline 42, one first needs to determine the operational pressure of the pipeline. For example, hypothetically, if the pipeline operates at 1,000 psig, the high-pressure pump system 56 might still need to operate at pressures above 1,200 psig to maintain the dense phase of the fluid 64 depending on the temperature-pressure phase diagram. In order to reduce the pressure of the dense phase fluid 64 to pipeline operating pressures, it passes through the throttling valve 80 or regulator prior to entering the pipeline 42. Heating might also be necessary at this point to prevent the formation of two-phase flow, i.e. to keep liquids from forming. Conversely, the heat exchanger could be lengthened to increase the temperature such that subsequent expansion and cooling does not take the fluid out of the dense phase.
After dense phase fluid 64 has been injected into the uncompensated caverns 34 and 38, it can be stored until needed. The dense phase fluid 64 may be stored in the uncompensated salt cavern at pressures well exceeding the operational pressures of the pipeline. Therefore, all that is needed to transfer the dense phase fluid from the salt cavern 34 and 38 is to open valves, not shown, on the wellheads 72 and 76 and allow the dense phase fluid to pass through the throttling valve 80 or regulator which reduces its operational pressure to pressures compatible with the pipeline. In conclusion, the well 32 acts both to fill and empty the uncompensated salt cavern 34 as indicated by the flow arrows. Likewise, well 36 acts to both fill and empty the salt cavern 38 as indicated by the flow arrows.
A subsea Bishop Process heat exchanger 220 may be located on the sea floor 222 in proximity to the platform 226. In an alternative embodiment, not shown, the heat exchanger 220 could be mounted on the platform 226 above the surface 21 of the water 20. In a second alternative embodiment, not shown, the heat exchanger 220 could be mounted on and between the legs 227 (Best seen in
After the cold fluid transport ship 48 has been successfully secured to the mooring/docking device 228, articulated piping, hoses and flexible loading arms 228 are connected to the low-pressure pump system 52 located in the cryogenic tanks 50 or on board the transport ship 48. The other end of the articulated piping 228 is connected to a high-pressure pump system 230 located on the platform 226. Additional cryogenically compatible piping 232 connects the high-pressure pump system 230 to the inlet 234 of the subsea heat exchanger 220.
After the cold fluid 51 passes through the high-pressure pump system 230 it is converted into a dense phase fluid 64 and then passes through the heat exchanger 220. The fluid 64 stays in the dense phase as it passes through the heat exchanger 220. The outlet 236 of the heat exchanger 220 is connected to a flexible joint 238 or an expansion joint. The cryogenically compatible piping 235 in the heat exchanger 220 connects to one end of the flexible joint 238 and non-cryogenically piping 240 connects to the other end of the flexible joint 238. This allows for expansion and contraction of the cryogenically compatible piping 235. The subsea pipeline 242 is formed from non-cryogenically compatible piping.
The subsea pipeline 242 connects to a wellhead 76, which connects to the well 32 and the uncompensated salt cavern 34. Again, by opening valves, not shown, on the wellhead 76, dense phase fluid 64 can be transported from the subsea pipeline 242 through the well 32 and injected in the uncompensated salt cavern 34 for storage.
In addition, the dense phase fluid 64 can be transported through the subsea pipeline 242 to a throttling valve 80 or regulator which reduces the pressure and allows the dense phase fluid 64 to pass through the piping 84 into the inlet 86 of the pipeline 42 for transport to market.
After a sufficient amount of dense phase fluid 64 has been stored in the salt cavern 34, the valves, not shown, on the wellhead 76 can be shut off. This isolates the dense phase fluid 64 under pressure in the uncompensated salt cavern 34. In order to transfer the dense phase fluid 64 from the uncompensated salt cavern 34 to the pipeline 42, other valves, not shown, are opened on the wellhead 76 allowing the dense phase fluid which is under pressure in the uncompensated salt cavern 34 to move through the throttling valve 80 or regulator and the pipe 84 to the pipeline 42.
Because the pressure in the uncompensated salt cavern 34 is higher than the pressure in the pipeline 42, all that is necessary to get the dense phase fluid to market is to open one or more valves, not shown, on the wellhead 76 which allows the dense phase fluid 64 to pass through the throttling valve 80. The well 32 is used to inject and remove dense phase fluid 64 from the uncompensated salt cavern 34 as shown by the flow arrows.
Cold fluids 51 leave the cryogenic storage tanks 50 on the cold fluid transport ship 48 and are pumped by the low-pressure pump 52 through the articulated piping 228 to the high-pressure pump system 230 located on the platform 226. The cold fluid 51 then passes through piping 232 to the inlet 234 of the subsea heat exchanger 220. The piping 228, 232 and 235 must be cryogenically compatible with the cold fluid 51.
The offshore heat exchanger 220 uses seawater 20 as a warmant 99. The warmant enters piping 246 on the platform 226 and passes through the low-pressure warmant pump 244. The warmant pump 244 may also be submersible. Piping 248 connects the low-pressure warmant pump 244 to the inlet ports 266 on the first section 250 of the heat exchanger 220. The warmant 99 passes through the annular area 268 between the outside diameter of the cryogenically compatible pipe 235 and the inside diameter of the pipe 254. The warmant 99 then exits the outlet ports 270 as indicated by the flow arrows. A submersible low-pressure pump 272 pumps additional warmant 99 into the second section 252 of the heat exchanger 220. In the alternative, the pump 272 could also be located on the platform 226. The warmant passes through the inlet ports 274 into the annular area 276 as indicated by the flow arrows. The annular area 276 is between the outside diameter of the cryogenically compatible pipe 235 and the interior diameter of the outer conduit 256. The warmant 99 exits the second section 252 through the outlet ports 278 as indicated by the flow arrows.
The cold fluid 51 enters the heat exchanger at the inlet 234 as a dense phase fluid 64 as it leaves the outlet 236 of the heat exchanger 220 as a dense phase fluid. The cryogenically compatible pipe 235 is connected to non-cryogenically compatible pipe 240 by a flexible joint 238 or an expansion joint. This allows the remainder of the subsea pipeline 242 to be constructed from typical carbon steels that are less expensive than cryogenically compatible steels. The heat exchanger 220 must be designed to avoid freez-up and to reduce or avoid icing within the heat exchanger 62. Similar design considerations, previously discussed that apply to the heat exchanger 62 also apply to the heat exchanger 220.
This hypothetical example is merely designed to give broad operational parameters for the Bishop One-Step Process conducted offshore as shown in
Assume that 800,000 barrels of LNG (125,000 cubic meters) are stored in the cryogenic tanks 50 on the transport ship 48 at approximately one atmosphere and a temperature of 250° F. or colder. The cold fluid transport ship 48 is moored to a dolphin 224 or some other suitable mooring/docking apparatus such as a single point mooring/docking or multiple anchored mooring/docking lines. LNG flows from the ship 48 through the low-pressure pump system 52, through hoses, flexible loading arms and/or articulated piping 228 to the high-pressure pump system 230 on the platform 226. The dense phase fluid 64 leaves the outlet of the high-pressure pump system 230 and enters the heat exchanger 220. The heat exchanger 220 is shown on the sea floor 222, but it could be located elsewhere as previously discussed. Also the heat exchanger 222 can assume various shapes as previously discussed in Example 1.
Ambient heated vaporizers are known in conventional LNG facilities (See pg. 69 of the Operating Section Report of the AGA LNG Information Book, 1981). According to the aforementioned Operating Section Report, “Most base load (ambient heated) vaporizers use sea or river water as the heat source”. These are sometimes called open rack vaporizers. On information and belief, conventional open rack vaporizers generally operate at pressures in the neighborhood of 1,000-1,200 psig. These open rack vaporizers are different than the heat exchangers 62 and 220 used in the Bishop One-Step Process.
Comparison of heat exchangers used in the invention with conventional open rack vaporizers.
First, the heat exchangers in the Bishop One-Step Process easily accommodate higher pressures suitable for injection into uncompensated salt caverns. Typically, conventional vaporizer systems are not designed for operational pressures in excess of 1,200 psig.
Second, the sendout capacity of each conventional open rack vaporizer is substantially less than the sendout capacity of the heat exchangers used in the Bishop One-Step Process. On information and belief, several open rack vaporizers must be used in a bank to achieve the desired sendout capacity that can be achieved by one Bishop One-Step Process heat exchanger.
Third, the conventional open rack vaporizer is also believed to be more prone to ice formation and freezing problems that the heat exchangers in the Bishop One-Step Process. Vaporizers that avoid this problem sometimes use water-glycol mixtures, which introduce an environmental hazard.
Fourth, the heat exchanger used in the Bishop One-Step Process provides a needed path to the uncompensated salt cavern or pipeline, in addition to heating the fluid. The length of the exchanger can be varied by using alternate designs as needed.
Fifth, the heat exchanger used in the Bishop One-Step Process is easily flushed for cleaning, as with a biocide. There is little chance of clogging when doing this.
Sixth, the construction of the heat exchanger used in the Bishop One-Step Process is extremely simple from widely available materials, and can be done on site.
Seventh, the heat exchanger used in the Bishop One-Step Process can accommodate a wide range of cold fluids with no change in design LNG, ethylene, propane, etc.
Eighth, the heat exchanger used offshore in the Bishop One-Step Process uses little space, (because it can be on the sea floor) which is highly advantageous on platforms. The weight contribution is also almost negligible.
Ninth and dependent on all of the above features, the heat exchanger used in the Bishop One-Step Process is extremely low cost both in capital and operations.
Tenth, conventional open rank vaporizers are fed LNG from cryogenic storage tanks that are part of the land based LNG facility. The heat exchangers used in the Bishop One-Step Process are fed LNG from the cryogenic tanks that are on board the cold fluid transport ship. The Bishop One-Step Process does not require cryogenic storage tanks as a part of the onshore facility.
Recognizing some of these performance problems with open rack vaporizers, Osake Gas has developed a new vaporizer called the SUPERORV, which uses seawater as the warmant. Drawings of the SUPERORV and conventional open rack vaporizers are shown on the Osaka Gas web site (www.osakagas.co.jp). The distinctions listed above between the heat exchanger used in the Bishop One-Step Process are likewise believed to be applicable to the SUPERORV.
The center pipe 61 will be equipped with conventional centralizers 108 to keep it centered in the outer conduit 104. This serves two functions. Centralizing allows the warming to be uniform and thus minimize the occurrence of cold spots and stresses. Perhaps more importantly, the supported, centralized position allows the inner pipe 61 to expand and contract with large changes in temperature. The centralizer 108 has a hub 107 that surrounds the pipe 61 and a plurality of legs 109 that contact the inside surface of the outer conduit 104. The legs 109 are not permanently attached to the outer conduit 104 and permit independent movement of the inner pipe 61 and the outer conduit 104. This freedom of movement is important in the operation of the invention. To further permit expansion and contraction in the surface mounted heat exchanger 62 of
In the present invention, these problems are avoided by insuring that the cold fluid 51 is converted by the high-pressure pump system 56 or 230 into a dense phase fluid 64 and that it is maintained in the dense phase while a) it passes through the heat exchanger 62 or 220 and b) when it is stored in an uncompensated salt cavern. The dense phase exists when the temperature and pressure are high enough such that separate phases cannot exist. In a pure substance, for which this invention also applies, this is known at the critical point. In a mixture, such as natural gas, the dense phase exists over a wide range of conditions. In
The effect of confining the fluid to the dense phase is illustrated by an analysis of the densimetric Froude Number F that defines flow regimes for layered or stratified flows:
Measurement of the Froude Number occurs downstream of the high-pressure pump systems 56 and 230 and in the heat exchangers 62 and 220. In other words, the Froude Number, using the Bishop One-Step Process should be high enough to prevent stratification in the piping downstream of the high-pressure pump systems 56 and 230 and in the heat exchangers 62 and 220. Typically Froude Numbers exceeding 10 will prevent stratification. Note that conventional heat exchangers do not usually operate at pressures and temperatures high enough to produce a dense phase, and phase change problems may be avoided by other means.
In summary, using the present invention, the cold fluid 51 is kept in the dense phase by pressure as it leaves the high-pressure pump system 56 or 230 and thereafter as it passes through the heat exchangers 62 or 220 and while it is stored in uncompensated salt cavern.
Conventional LNG facilities offload LNG and store it onshore in cryogenic storage tanks as a liquid. In a conventional facility, the LNG is then run through a conventional vaporizer system to warm the liquid and convert it into a gas. The gas is odorized and transferred to a pipeline that transmits the gas to market. A simplified flow diagram of a conventional LNG vaporizer system is shown in
In the alternative embodiment shown in
Typically, the fluid 59 will be stored at a pressure exceeding pipeline pressures. Therefore, all that is necessary to transfer the fluid 59 from the uncompensated salt caverns 34 and 38 is to open valves, not shown, on the wellhead 76 and 72 allowing the gas 320 to pass through the piping 78 and the throttling valve 80 or a regulator, the piping 84 to the inlet 86 of the pipeline 42. Some additional heating may be necessary to the gas prior to entering the pipeline. Therefore, the wells 32 and 36 are used for injecting fluid 59 into the uncompensated salt caverns 34 and 38 and the wells are also used as an outlet for the stored fluid 59 when it is transferred to the pipeline 42. The flow arrows in the drawing therefore go in both directions indicating the dual features of the wells 32 and 36.
This hypothetical example is merely designed to give broad operational parameters for an alternative embodiment including a vaporizer system for warming of cold fluids with subsequent storage in uncompensated salt caverns and/or transportation through a pipeline, as shown in FIG. 10. Unlike conventional LNG facilities, no cryogenic tanks are used in the on-shore facility 310 of FIG. 10. (The ship 48, as previously mentioned, does contain cryogenic tanks 50.) A conventionally designed vaporizer system 260 is used in this alternative embodiment instead of the coaxial heat exchangers 62 and 220, discussed in the previous examples. (Conventional vaporizer systems typically operate in the range of 1,000-1,200 psig.) The conventionally designed vaporizer system 260 will need to be modified to accept the higher pressures associated with uncompensated salt caverns (typically in the range of 1,500-2,500 psig). A number of factors must be considered when designing the facility 310 including the type of cold fluid and warmant that will be used. Conventional instrumentation for process measurement, control and safety are included in the facility as needed including but not limited to: temperature and pressure sensors, flow measurement sensors, overpressure reliefs, regulators and valves. Various input parameters must also be considered including, pipe geometry and length, flow rates, temperatures and specific heat for both the cold fluid and the warmant. Various output parameters must also be considered including the type, size, temperature and pressure of the uncompensated salt caverns. For delivery directly to a pipeline, other output parameters must also be considered such as pipe geometry, pressure, length, flow rate and temperature. Other important design considerations include the size of the cold fluid transport ship and the time interval during which the ship must be fully offloaded and sent back to sea.
A plurality of vaporizer systems 260 might be required to reach desired flow rates. The vaporizer systems used in this alternative embodiment must be designed to withstand operational pressures in the range of 1,500 to 2,500 psig to withstand the higher pressures necessary for subsurface injection.
Conventional vaporizer systems are designed to function with stratification. Unlike Examples 1 and 2, it is not necessary in this alternative embodiment to have the fluid in the dense phase while it goes through the vaporizer nor are high Froude numbers required. Though not required, use of the dense phase is also acceptable.
Referring to
This process has several advantages over conventional LNG facilities. In this alternative embodiment, there is no need for cryogenic storage tanks. The fluid 59 is stored in an uncompensated salt cavern, which is more secure than surface mounted conventional cryogenic storage tanks. To Applicants knowledge, there is presently no conventional LNG facility using conventional vaporizers that subsequently injects gas into uncompensated salt cavern.
This application claims priority of U.S. provisional patent application 60/342,157 filed Dec. 9, 2001. This application is a divisional of U.S. patent application Ser. No. 10/246,954 filed on Sep. 18, 2002.
Number | Name | Date | Kind |
---|---|---|---|
3777502 | Michie et al. | Dec 1973 | A |
4894928 | Bishop | Jan 1990 | A |
5129759 | Bishop | Jul 1992 | A |
5439317 | Bishop et al. | Aug 1995 | A |
5511905 | Bishop et al. | Apr 1996 | A |
6298671 | Kennelley et al. | Oct 2001 | B1 |
6584781 | Bishop et al. | Jul 2003 | B2 |
Number | Date | Country | |
---|---|---|---|
20040112067 A1 | Jun 2004 | US |
Number | Date | Country | |
---|---|---|---|
60342157 | Dec 2001 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 10246954 | Sep 2002 | US |
Child | 10604947 | US |