The present invention relates to a method and to an arrangement for installing an elevator.
In prior art solutions where elevators are needed before the building has been completed so-called jump elevators are used during the construction time. Usually jump elevators are used only in high-rise buildings and all the work related to jump elevators is rather complicated because the whole temporary machine room with its machinery and electric connections is moved in a stepwise manner to a higher floor and the at the same time the length of the hoisting rope in use is increased accordingly. That means in general that all the components depending on the hoisting height, such as car cables, compensating ropes, overspeed governors and shaft electrification and shaft cables should be extended over the entire length of the finished elevator shaft. All this causes a lot of work, which also make the process slow.
U.S. Pat. No. 5,033,586 shows a prior art solution where a temporary elevator machine room module comprising two levels in a frame can be lifted to a desired height and secured at its new position. The elevator machinery with the ordinary machine room components and hoisting rope supplies with rope reels are placed on the upper space of the module. When the machine room module is to be moved, the elevator car is locked at its place, and the required additional rope length is supplied from the reels of the hoisting rope supply. A disadvantage with this solution is that the whole hoisting rope supply with the reels and all the components of the machine room have to be lifted together with the machine room, and in addition all the electrification has to be deactivated and then built again when the elevator machine room module is in its new location. Heavy hoists are needed and the installation work is difficult and also slow and dangerous. The dismantling of the temporary machine room module causes also a lot of waste material and takes time.
The object of the present invention is to eliminate drawbacks of prior art technology and to achieve an advantageous, fast and easy method and arrangement for installing an elevator in lower-rise buildings so that the elevator can be used during the construction time and the use can be extended to a higher operation level as the construction work is progressing, and which elevator is also applicable for use as a normal elevator in the finished building. The method according to the invention is characterized by, during a jump to make the elevator serve a higher floor, taking extensions needed for a suspension ropes from one or more first supply reels and taking extensions needed for a traction member from one or more second supply reels, and the arrangement according to the invention is characterized by the arrangement comprising one or more first supply reels for the extensions needed for the suspension ropes during the jump and one or more second supply reels for the extensions needed for the traction member during the jump. Other embodiments of the invention are characterized by what is presented in the other claims.
The inventive content of the application can also be defined differently than in the claims presented below. The inventive content may also consist of several separate inventions, especially if the invention is considered in the light of expressions or implicit sub-tasks or from the point of view of advantages or categories of advantages achieved. In this case, some of the attributes contained in the claims below may be superfluous from the point of view of separate inventive concepts. Likewise the different details presented in connection with each embodiment can also be applied in other embodiments. In addition it can be stated that at least some of the subordinate claims can, in at least some situations, be deemed to be inventive in their own right.
The method and arrangement according to the invention have several useful advantages. Among other things it makes it possible to use the elevator during the construction time in an economical and fast way. The method and arrangement according to the invention makes it possible to use a jump-elevator installation technology economically also in lower-rise buildings. In that case elevators can be used in lower-rise buildings earlier which increases a total usage of the elevators. Because there is no need to lift the hoisting machinery and all the rope supplies in connection with the jump the jump is easier and faster to make and does not need as heavy hoisting devices as prior art systems. One big advantage is that there is no need to move the electricity supply because the hoisting machinery stays at its place all the time. Yet one advantage is that the own hoisting machinery can be used at least partially for the installation. Also one advantage is that the method and arrangement according to the invention cause only a minimal amount of waste material, because, for example the method and arrangement according to the invention does not need a temporary machine room that should be dismantled after the installation.
An advantageous way to carry out the invention is to install an elevator, comprising at least a car, a balancing weight, their guide rails, hoisting machinery, suspension ropes connecting the car and the balancing weight from up, a traction member connecting the car and the balancing weight from down and driving wheel driven by the hoisting machine and tractively connected to the traction member in such manner that the elevator is installed at least in two phases, using so called jump method. Between the jumps the elevator is serving number of the floors, usually the lowermost floors of the building or the lowermost floors of a particular elevator shaft. During a jump phase the working elevator is build taller and the extensions needed for each suspension rope is taken from a respective suspension supply reel and extension needed for each traction member is are taken from a respective traction member supply reel.
During the jumps, both suspension ropes and traction ropes can be released from their reels at the same time. Suspension rope release and traction member release from their reels can be done in a sequence or by alternating them.
Preferably the hoisting machine is installed to its final place in early phase of the installation and its place is not changed during or between the jumps. In the an auxiliary hoist is preferably used, when the pulley(s) which suspend(s) the suspension ropes above the elevator car are moved to an upper position.
In the following, the invention will be described in detail by the aid of example embodiments by referring to the attached simplified and diagrammatic drawings, wherein
It is essential to the solution according to the invention that any temporary machine room is not needed and that the hoisting machinery is not lifted during jumps to a higher level.
The basic embodiments of
The supporting and moving of the elevator car 1 are separated from each other. The elevator car 1 is driven by a hoisting machinery 4 equipped with a drive wheel 5. The hoisting machinery 4 is placed in the lower part of the elevator shaft below the elevator car 1 into its final location in the initial installation phase before the later jumps to be done. A traction member 1b is connected between the balancing weight 3 and the elevator car 1. The traction member 1b can be a single member or a bunch of similar parallel members, for instance the traction member 1b can be a toothed belt, chain or other type of member that does not slip on the drive wheel 5.
A first end of the traction member 1b is secured in its fastening point 1c at the bottom of the elevator car 1 and from the fastening point 1c the traction member 1b is passed around and under the drive sheave 5 of the hoisting machinery 4, and from the drive sheave 5 the traction member 1b is further passed under and around a diverting pulley 6 to a supply reel 10 that is secured on the lower part of the balancing weight 3. The supply reel 10 acts as the second supply reel. Depending on need the supply reels 10 can also be more than one. The supply reel 10 acts as a traction member supply for the jumps to higher levels. During the normal service of the elevator in the construction phase the supply reel 10 is locked from rotating and the traction member 1b is secured by clamps or other suitable way so that the length of the traction member 1b between the car 1 and the balancing weight 3 does not change unintentionally.
In the embodiment of
The first method according to the invention comprises among other things for instance the following steps in the initial phase:
After the last step 12) the elevator car 1 can run in the elevator shaft and the elevator is able to serve the lowermost floors of the building though the building is still under construction.
The first method according to the invention comprises among other things for instance the following steps in the jump situation:
The order of some steps may occasionally change. After the step 24) above the elevator is ready for service according to
The first method according to the invention comprises among other things for instance the following steps in the situation of the final conversion:
In this embodiment the steps as follows are made and/or can be made on the roof of the elevator car 1: 5)-10), 14)-22) and 26)-28).
The second method according to the invention comprises among other things for instance the following steps in the initial phase:
After that the elevator car 1 can run in the shaft and the elevator is able to serve the lowermost floors of the building though the building is still under construction. At the same time when the elevator is in a normal service next upper guide rails 2 and landing doors can be installed working on the installation stage 12.
The second method according to the invention comprises among other things for instance the following steps in the jump situation:
The order of some steps may occasionally change. After the step 126) above the elevator is ready for service. During the normal service next upper guide rails and landing doors, etc. can be installed using the installation stage 12 until the final height is reached.
The second method according to the invention comprises among other things for instance the following steps in the situation of the final conversion:
In this embodiment the steps as follows are made and/or can be made on the installation stage 12: 105), 108), 109), 114), 117), 119), 123), 124) and 127). Whereas the steps as follows are made and/or can be made on the roof of the elevator car 1: 105), 107), 109)-111), 114), 117)-124) and 128)-136).
The fourth method according to the invention comprises among other things for instance the following steps in the jump situation:
The order of some steps may occasionally change. After the step 250) above the elevator is ready for service, still having supply reels 9 and 10 until the whole elevator shaft is at its maximum height. During the normal service next upper guide rails and landing doors, etc. can be installed using the installation stage 12 until the final height is reached. The jump can be done in the same way also in the elevator arrangement where the installation stage 12 is not used. In that case the auxiliary hoist 11 suspending the support beam 2a is suspended from the fixed point in the building.
The steps of all the methods described here are very much the same in all installation phases. Only minor differences occur where some steps can vary, some step can be missing and some steps can be done in a different order. It is, however common to all the methods and the arrangements according to the invention that in the elevator installed the suspension and moving have been separated from each other and the only and final hoisting machinery 4 is in the lower part of the elevator shaft below the elevator car 1, for instance at the bottom of the elevator shaft. Then the hoisting machinery 4 is not lifted upwards in the jump phase, only the support beam 2a with the diverting pulleys 7 is lifted upwards during the jump with either the elevator car 1 or the balancing weight 3. And at the same time either the elevator car 1 or the balancing weight 3 is arranged to draw the extensions for the suspension ropes 1a and for the traction member 1b either non-simultaneously or preferably simultaneously from their own supply reels 9 and 10, and so that the lengths of the extensions of the traction member 1b and suspension ropes 1a are for a car run of an equal length.
The supply reels 9 and 10 can be placed mutually in a different moving object, for instance so that the reel or reels 9 for suspension ropes 1a are placed in the elevator car 1 and the reel or reels 10 for the traction member 1b are placed in the balancing weight 3, or vice versa. In that case the balancing during the jump may not change or the change is small and easy to compensate.
The supply reels 9 and 10 can also be placed mutually in the same moving object, for instance so that the reel or reels 9 for suspension ropes 1a are placed in the top part of the elevator car 1 and the reel or reels 10 for the traction member 1b are placed in lower part of the elevator car 1, or the reel or reels 9 for suspension ropes 1a are placed in the top part of the balancing weight 3 and the reel or reels 10 for the traction member 1b are placed in lower part of the balancing weight 3. In that case the balancing during the jump may change considerably and then the compensating of the change is important.
Thus, the jump phase in all the methods according to the invention may comprise a further step where the balancing is checked after the jump and, if needed, adjusted to be correct for instance by adding more weight either to the elevator car 1 or to the balancing weight 3.
After the whole elevator shaft is at its maximum height the final conversion is done according to one of the methods described above, and after the final conversion the elevator is ready for normal service according to the situation that is shown in
Thanks to the inventive solution according to the invention the jump to the next higher level is easy and fast to make, and thus also shorter jumps can be economically done and consequently the elevator can serve the building also during the construction time more flexibly than in prior art solutions.
Instead of using the auxiliary hoist 11 mentioned above for suspending and lifting the elevator car 1, support beam 2a or balancing weight 3, or other components of the elevator the own hoisting machinery 4 of the elevator can be used mainly or at least partially for the installation described above.
It is obvious to the person skilled in the art that the invention is not restricted to the examples described above but that it may be varied within the scope of the claims presented below.
This application is a continuation of PCT International Application No. PCT/FI2014/050666 which has an International filing date of Sep. 1, 2014, the entire contents of which are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
5033586 | Richards et al. | Jul 1991 | A |
10227212 | Alasentie | Mar 2019 | B2 |
20120291395 | Plathin | Nov 2012 | A1 |
20140000987 | Peacock et al. | Jan 2014 | A1 |
20140231179 | Alasentie | Aug 2014 | A1 |
20150034425 | Ratia | Feb 2015 | A1 |
Number | Date | Country |
---|---|---|
103303771 | Sep 2013 | CN |
WO-2013079790 | Jun 2013 | WO |
Entry |
---|
European Search Report for corresponding European Application No. 14901081.1 dated Mar. 8, 2018. |
International Search Report PCT/ISA/210 for International Application No. PCT/FI2014/050666 dated May 19, 2015. |
Written Opinion of the International Searching Authority PCT/ISA/237 for International Application No. PCT/FI2014/050666 dated May 19, 2015. |
Chinese Office Action dated Jun. 28, 2018 issued in corresponding Chinese Application No. 201480081669.6 (with translation). |
Number | Date | Country | |
---|---|---|---|
20170166419 A1 | Jun 2017 | US |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/FI2014/050666 | Sep 2014 | US |
Child | 15433062 | US |