The present invention refers to a method and a device for mounting and dismounting blades onto wind turbines of the type that employ winches without a need for a conventional crane.
The development of new wind turbines has resulted in an increase in their size and power. Large wind turbines enable more capacity to be installed at the same site and reduce the visual impact of a farm consisting of several wind turbines.
A wind turbine consists of a stationary tower that elevates a nacelle bearing an electrical generator attached to a rotor mechanically. The rotor comprises a hub that attaches at least one blade, bolted to some studs from some bearings on the hub, which transforms the wind's kinetic energy in the rotating rotor.
The increase of generated power is linked directly to the dimensions of the wind turbine rotor and the consequential lengthening of the wind turbine blades. The blades represent the most critical element of a wind turbine and therefore undergo preventive inspections and corrective interventions for which the blades must be dismounted from the hub and brought down to the ground, and subsequently hoisted and remounted onto the hub after completing the maintenance tasks.
To do so, maintenance workers use large-scale cranes for handling rotors of a significant size and weight. Cranes of this sort have various drawbacks. Firstly, they are very costly, hence the cost of installing a wind turbine farm or undertaking maintenance is notably increased with their use. Secondly, given that wind turbines are usually installed on sites that are not easily accessed, transferring these cranes to the required spot is virtually impossible and normally requires conditioned accesses, which adds further complications and costs.
In this regard, the acknowledged state of the art provides various solutions that describe different pieces of equipment for mounting and dismounting wind turbine blades.
Patent WO2011/095167 describes hoisting equipment for mounting/dismounting that has a winch inside the wind turbine hub and attaches the blade through a hook to plates bolted to the blade bearing joint bolts. The equipment has an element equipped with a roller that is placed between the hook and the winch, enabling the blade to be lowered vertically and subsequently rotated to a horizontal position when near the ground. However, the drawback of this system is its need for a large amount of space to install a winch that supports the elevated weights of current blades in addition to retention and rotation-proof systems that are more reliable than the one described above.
Patent WO2009/128708 describes equipment furnished with two elements, one placed on the wind turbine hub, which grasps the blade from the bearings, and the other placed inside the blade. These elements work together to raise or lower a blade using some means of positioning and some means of lifting. The blade, secured by a winch, is lowered vertically (the tip pointing toward the ground) by engaging an actuator in one of the means that balances the blade toward a predetermined alignment with the tower. A winch is used to guarantee the vertical descent of the blade
Patent US2010/0253086 describes a system that incorporates some pulleys outside the hub, in the spaces existing between the blades, that are used for guiding a cable connected with a service crane located on the wind turbine nacelle or winch (W) installed on the ground. The blade is secured for lowering or raising by a pulley inside the hub.
In view of the drawbacks of the aforementioned solutions, a need is thus envisioned for implementing a solution that could guarantee the mounting and/or dismounting the blades at a minimum cost.
To do so, the replacement device of the invention comprises two elements, one upper and the other lower, which work together to raise and/or lower a wind turbine blade.
The upper element of the device, which will be referred to hereinafter as “top”, consists of some pulley elements and some means for fastening the blade, while the lower element, which will be referred to hereinafter as “ground”, consists of a structure that encompasses the wind turbine tower and is equipped with at least two winches and two deviation pulleys to connect cables between the device's “top” and “ground” elements.
One object of the invention is that the device can be used in any type of wind farm regardless of the type of installed wind turbines, thus the structure of the “ground” element of the device can be adjusted to fit different tower diameters.
One object of the invention is that the device can be used in any type of wind farm regardless of the type of installed wind turbines, thus the blade fastening element of the “top” element of the device can be adjusted to fit different blade diameters.
One object of the invention is that the device can be used at any wind farm site regardless of the climate conditions, thus the invention contemplates an inclinometer in the “ground” element that controls blade inclination during lowering and/or raising operations, as well as the load cells that measure the weight withstood by compression, and counterweights that counteract the blade's weight.
One object of the invention is that the system prevents the blade from turning over on itself or flipping, thus the device can be combined with any retention system and with any anti-rotation system.
One object of the invention is a method of raising and/or lowering a wind turbine blade using the device of the invention.
These and other aspects of the invention will be described in more detail with the help of the drawings shown below.
The present invention is related with a method and a device for replacing the blades of a wind turbine in wind farm maintenance or installation tasks.
A wind turbine consists of a tower (8) that elevates a nacelle (14) bearing an electrical generator attached to a rotor mechanically.
The rotor comprises a hub (15) that attaches at least one blade (13) bolted to the wind turbine hub (15) through some bearings (3) equipped with some studs inserted into the blade root (7).
The device in the present invention for replacing a blade (13) consists of two elements (1, 2) that work together to ensure the correct lifting/lowering of the wind turbine blade (13), namely, a “top” element (1) (see
The “top” element (1) comprises two parts (4, 5), one (4) that is attached to the bearing (3) of the hub (15) (
The part (4) of the “top” element (1) that is secured on the bearing (3) of the blade (see
The vertical movement pulleys (4.1) are employed for moving the cable (6) toward the flange (5) for the blade (13) and the winches (2.5) of the “ground” element (2), while the horizontal deviation pulleys (4.2) are employed for guiding the cables (6) horizontally around the bearing (3) and the fastening elements (4.3) for fastening the final end of the cables (6).
The flange (5) for the blade (13) on the “top” element (1) (
In order for the blade flange (5) to work correctly, it must be level with the blade bearing (3). Given that the blade root (7) usually has quite a few irregularities, the segments (5.1, 5.2) of the blade flange (5) have a series of orifices (11) for inserting some rods (12) (see
According to one embodiment of the invention, the part (4) of the “top” element (1) that attaches to the bearing (3) and the part (5) that constitutes the flange of the blade (13) must be perfectly aligned with each other so that the deviation of the cable (6) between the vertical pulleys (4.1) and the pulleys (9) of the flange (5) are perfectly aligned, hence the different elements (4, 5) that constitute the “top” element must be in a correct position and the blade in position 0°.
The “ground” element (2) consists of a structure (2.1) formed by sections comprising some fixed rollers (2.2), a centering roller (2.3), some deviation pulleys (2.4), some winches (2.5), a dismountable structure (2.1), a counterweight (2.6), an electrical panel (2.7) and control elements such as an inclinometer (not represented) and some load cells (not represented) mounted on the return pulleys (2.4) of the counterweights (2.6) for controlling the tension in the cable (6).
The main section of the structure (2.1) supports the winches (2.5), electrical panel (2.7) and the fixed rollers (2.2), and is positioned at the head, at the base of the tower (8). The parallel sections of the structure (2.1) are symmetrical and bolted to the main section perpendicular to it. The counterweights (2.6) are placed on the ends of the parallel sections and a front section equipped with an adjustable centering roller (2.3) is placed between them. The front section, once placed onto the spot nearest the tower (8), is bolted between the counterweights (2.6) to finally adjust the adjustable centering roller (2.3) to the tower (8) (see
The electrical panel (2.7) has a startup push-button and an emergency push-button (not represented), a touchscreen (not represented) to view the status of the various elements constituting the blade (13) replacement device in addition to indicators for the tension and movement of the cable (6) connected to the load cells of the pulleys (2.4) for the counterweights (2.6), a selector and some alarm pilot lights for the operation of the winches (2.5). The device is thus capable of configuring the working limits for the inclination of the blade (13) and the tension in the cables (6).
The method for replacing the blade (see
The hoisting of the blade (13) is done by following the blade lowering steps in the reverse order.
While this invention has been described entirely in connection with preferential embodiments, modifications may clearly be made within its scope, which is not restricted by the aforementioned embodiments, but rather by the content of the following claims.
Number | Date | Country | Kind |
---|---|---|---|
201400538 | Jul 2014 | ES | national |
Number | Name | Date | Kind |
---|---|---|---|
7785073 | Wobben | Aug 2010 | B2 |
8083212 | Numajiri | Dec 2011 | B2 |
8118552 | Nies | Feb 2012 | B2 |
8191253 | Vangsy | Jun 2012 | B2 |
8534421 | Teichert | Sep 2013 | B2 |
8595931 | Riddell | Dec 2013 | B2 |
8651462 | Van Berlo | Feb 2014 | B2 |
8939299 | Ahler | Jan 2015 | B2 |
8997350 | Trede | Apr 2015 | B2 |
9027243 | Neumann | May 2015 | B2 |
9115693 | Fenger | Aug 2015 | B2 |
9446446 | Gabeiras | Sep 2016 | B2 |
9476403 | Smith | Oct 2016 | B2 |
9638163 | Holloway | May 2017 | B2 |
9651021 | Neumann | May 2017 | B2 |
9745953 | Neumann | Aug 2017 | B2 |
9821417 | Neumann | Nov 2017 | B2 |
20060175465 | Teichert | Aug 2006 | A1 |
20060228220 | Wobben | Oct 2006 | A1 |
20070290426 | Trede | Dec 2007 | A1 |
20100005656 | Vangsy | Jan 2010 | A1 |
20100028152 | Numajiri | Feb 2010 | A1 |
20100139062 | Reed | Jun 2010 | A1 |
20100253086 | Song | Oct 2010 | A1 |
20100254813 | Dawson | Oct 2010 | A1 |
20120217089 | Fenger | Aug 2012 | A1 |
20130318789 | Gabeiras | Dec 2013 | A1 |
20140010658 | Nielsen | Jan 2014 | A1 |
20140109407 | Neumann | Apr 2014 | A1 |
20160010622 | Modrego Jimenez | Jan 2016 | A1 |
20160040649 | Smith | Feb 2016 | A1 |
20160146183 | Puls | May 2016 | A1 |
Number | Date | Country |
---|---|---|
2009128708 | Oct 2009 | WO |
2011095167 | Aug 2011 | WO |
Number | Date | Country | |
---|---|---|---|
20160010622 A1 | Jan 2016 | US |