This invention relates to a method for hoisting an item by means of a crane. More particularly, it relates to a method for hoisting an item at sea with a hoisting device, comprising:
During hoisting operations at sea where heavy items having weights in the order of several hundred tonnes are to be disposed on the seabed, for example, the availability of steel ropes having sufficient combined strength and length has become a limiting factor for the size of items that can be handled. The seabed may be located several kilometres below sea level, and the weight of the steel rope therefore becomes significant.
It may therefore be necessary to use fibre ropes to allow the largest items to be submerged into deep waters.
The use of fibre ropes for operations of this type requires consideration of conditions not normally being limiting when using steel ropes. For example, the effective life of a fibre rope comprising a significant proportion of carbon fibre depends directly on the number of load-related flexures that the fibre rope is exposed to.
Oftentimes hoisting operations of this type are heave-compensated, and the lifting rope will therefore be continuously reeled in and out from the winch due to the heave motion of the lifting vessel. Even if the item being lifted is stationary relative to the seabed, the lifting rope will still be reeled in and out, whereby the effective life of a fibre rope is reduced relatively fast.
Moreover, fibre ropes do not possess sufficient shape stability for allowing them to be reeled in several layers onto a drum when full lifting power is applied to the fibre rope.
Similar to a belt, it is known to wind a fibre rope several turns around two parallel drums (traction winch) before pulling the fibre rope onto a storage reel, often in several layers, whilst using a relatively small force.
Such a solution, however, causes the fibre rope to be exposed to flexing every time it enters a drum and every time it leaves the drum. If the fibre rope is wound five parallel turns around the two drums, the rope will be continuously exposed to repeated flexing at ten places, which reduces the effective life to an unacceptable extent.
Fibre ropes designed to transmit the lifting power to a reel are relatively expensive.
It is known to pay out a relatively long rope, which carries a load, by means of a shorter rope. For example, U.S. Patent Application Pub. No. 2005/0191165 describes a method wherein a first length of fibre rope is paid out by means of a lifting wire on a vessel, and wherein the connection of the lifting wire to the fibre rope is moved before a next length of fibre rope, which is connected to the first length of fibre rope, is paid out by means of the lifting wire. The pay-out takes place in a fixed position relative to the vessel.
The object of the invention is to remedy or reduce at least one of the disadvantages of the prior art.
A method for hoisting an item at sea is provided, the method comprising:
Thereby, the second hoisting rope is exposed to a load from the item only when it is in an extended position, and not when it is paid out via a sheave, for example. By virtue of the hanger being connected to the crane, it is also possible to compensate for movements of the vessel in the horizontal plane.
The method may further comprise one or more of the following features:
Thus, a second hoisting rope, which for example is several thousand metres long, may be hoisted out by means of a substantially shorter first hoisting rope.
The hanger may be connected to a jib of the crane. Insofar as the first hoisting rope is reeled in and out over the jib, the load is connected to the jib independent of whether it is the first or the second hoisting rope that is carrying the load of the item, the step of which substantially facilitates the positioning of the item relative to the vessel.
The method may be practised by means of a device for hoisting an item at sea,
The hanger is structured in a manner allowing it to withstand the load of the item on the second hoisting rope.
The hanger is connected to a jib of the crane in order to achieve improved handling of the item, especially when it is suspended from the hanger.
The first hoisting rope may be releasably connected to the second hoisting rope. By so doing, the connection between the first hoisting rope and the second hoisting rope may be moved between different positions on the second hoisting rope.
The first hoisting rope may be releasably connected to the second hoisting rope by means of a connector located on the second hoisting rope. Each connector is structured to fit in a complementary manner with a lock connected to the lifting hook of the first hoisting rope. Alternatively, the first hoisting rope may be connected to the second hoisting rope by means of a clamping fastener or some other suitable device.
For example, the hanger and the lock may be formed with remote-operable latches/dogs which, when in their active positions, are engaged with the corresponding connector.
Usually, the second hoisting rope is formed with several connectors along the longitudinal extent thereof. The connectors may be structured to fit into the hanger. By means of the connectors, several consecutive rope lengths may be joined to form the second hoisting rope. The rope lengths may have different lengths, cross-sectional shapes and cross-sectional dimensions.
Embodiments of the methods and the devices disclosed herein render possible to use relatively inexpensive fibre ropes not capable of being exposed to repeated, load-related flexures.
The fibre rope is exposed to substantial load forces only when it is suspended in the sea with no flexure, and not when lying on a drum or over a sheave. Insofar as all components may be prepared before initiating the hoisting operation, which is carried out without requiring manual coupling work, the method and the device according to the embodiments described herein are suitable for remote-controlled work.
A non-limiting example of a preferred method and embodiment is described in the following and is depicted in the accompanying drawings, in which:
In the drawings, reference numeral 1 indicates a vessel provided with a hoisting device 2 in the form of a crane 4. In this preferred exemplary embodiment, the crane 4 is a pivotal, heave-compensated crane 4 comprising a main boom 6 and a jib 8.
A first hoisting rope 10 extends from a hoisting drum 12 on the crane 4, along the main boom 6, over the jib 8 and onto a lifting hook 13. A second hoisting rope 14 extends from a feed mechanism 16, which comprises a reel 18, over a sheave 20 and onto an item 22 to which it is attached by means of a leading device 24.
The sheave 20 is suspended from the jib 8 by means of a suspension support 26, a pivotal connector 28 and an auxiliary winch 30. The function of the auxiliary winch 30 is to keep the suspension support 26 in a desired position when changing the angle of the jib 8 relative to the horizontal plane.
A hanger 32 for the second hoisting rope 14 is connected to the pivotal connector 28. In order to withstand a tensile force from the second hoisting rope 14, the hanger 32 is structured in a manner allowing it to be releasably connected to the second hoisting rope 14 by means of connectors 34.
The second hoisting rope 14 is provided with several connectors 34 along the longitudinal extent thereof. For example, a connector 34 may comprise a joint piece (not shown) for the second hoisting rope.
The connector 34 is structured to fit in a complementary and releasable manner with a lock 36 connected to the first hoisting rope 10 by means of the lifting hook 13. When released, the lock 36 is movable along the second hoisting rope 14.
The connectors 34 are structured to fit in a lockable manner into the hanger 32, the second hoisting rope extending through the hanger 32.
When an item 22, which is located on the vessel 1 or some other nearby vessel (not shown), is to be submerged into relatively deep waters, the crane 4 is manoeuvred into a position above the item 22, after which the item 22 is connected to the second hoisting rope 14 by means of the leading device 24. The lock 36 on the first hoisting rope 10 is arranged in a movable manner around the second hoisting rope 14, see
The second hoisting rope 14 may be suspended in the hanger 32 by means of a connector 34. Alternatively, the first hoisting rope 10 may be tightened up so as to allow the lock 36 to engage a connector 34 before lifting the item from the vessel 1 and outwards above the sea 38.
The item 22 is then lowered into the sea 38 whilst the load of the item is taken by the first hoisting rope 10, and whilst the second hoisting rope 14 is being paid out from the feed mechanism 16 and over the sheave 20, see
When the first hoisting rope 10 is nearing its full pay-out, the hanger 32 engages a connector 34. By so doing, the load of the item 22 is transferred to the second hoisting rope 14, whereby the first hoisting rope 10 is relieved. The lock 36 is disconnected from the connector 34 to which it was engaged, for example by means of an ROV (Remotely Operated Vehicle) 35, see
Thereafter the lock 36 engages a connector 34 located at a level higher up, preferably in the hanger 32, after which the load of the item 22 once again is taken over by the first hoisting rope 10.
The hanger 32 is released from the connector 34 to which it was connected, and the item 22 may then be lowered further into the sea 38 until disposed on the seabed 40. The second hoisting rope 14 is disconnected from the item 22 and both hoisting ropes 10, 14 are reeled in.
Should the sea depth require further lowering beyond the length of the first hoisting rope 10, the operations above may be repeated. Should this not be required, the upper portion of the second hoisting rope 14 may be comprised of a more inexpensive fibre rope which is not designed to withstand the load of the item 22.
If an item is to be hoisted up from the seabed 40, the operations described above are carried out, however in the reverse order.
Number | Date | Country | Kind |
---|---|---|---|
20090729 | Feb 2009 | NO | national |
This application is the U.S. National Stage under 35 U.S.C. §371 of International Application No. PCT/NO2010/000045 filed Feb. 8, 2010, which claims priority to Norwegian Patent Application No. 20090729 filed Feb. 16, 2009, entitled “Method and Device For Hoisting An Item By Means Of A Crane.”
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/NO2010/000045 | 2/8/2010 | WO | 00 | 10/3/2011 |