Method and device for managing project

Information

  • Patent Grant
  • 12159263
  • Patent Number
    12,159,263
  • Date Filed
    Wednesday, August 24, 2022
    2 years ago
  • Date Issued
    Tuesday, December 3, 2024
    19 days ago
Abstract
According to a preferred embodiment of the present disclosure, a project management device includes: a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and a display unit configured to classify the n CWPs according to construction statuses and work front statuses and display the n CWPs in a grid form.
Description
TECHNICAL FIELD

The present disclosure relates to a device and method for managing a construction project by establishing a project schedule and managing a performance status through exchange of information among design, procurement, and construction.


DESCRIPTION OF RELATED ART

Construction project management systems do not consider drawings and material statuses or consider only material statuses or drawings. Thus, an integrated project management system configured to collect and combine together all drawings and material statues in real time is necessary for smooth construction.


In addition, because construction projects are carried out in dozens of areas at the same time, it is difficult to recognize the construction statuses and constructability of sub-projects in arbitrary areas, and information on the construction statuses and constructability of sub-projects in arbitrary areas is manually collected. In addition, it is difficult to intuitively recognize which sub-projects are highly risky.


PRIOR ART DOCUMENTS
Patent Documents





    • (Patent Document 1) KR 10-2222384 B1





CONTENT OF DISCLOSURE
Problems to be Addressed

Preferred embodiments of the present disclosure provide a device and method for managing a project by intuitively recognizing the construction status and constructability of the project and classifying and recognizing risk levels.


Solution to Problem

According to a preferred embodiment of the present disclosure, a project management device includes: a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and a display unit configured to classify the n CWPs according to construction statuses and work front statuses and display the n CWPs in a grid form, wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.


In a preferred embodiment of the present disclosure, a horizontal axis of the grid form of the display unit indicates stage-based construction statuses, and a vertical axis of the grid form of the display unit indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status.


In a preferred embodiment of the present disclosure, the display unit shows risk information by using positions of the grid boxes of the grid form.


In a preferred embodiment of the present disclosure, when the information on the number of CWPs in each of the grid boxes is clicked, only CWPs corresponding to the grid box are selected from the n CWPs by filtering, and detailed information on the selected CWPs are shown.


In a preferred embodiment of the present disclosure, the construction type includes piping, a steel frame, machinery, and civil engineering, wherein work front statuses of individual constituent units are first calculated on a construction type basis while considering at least one of a drawing and a material according to the construction type of the project, and then the work front statuses of the individual constituent units are added up on a CWP basis to obtain the work front statuses based on the CWPs.


According to a preferred embodiment of the present disclosure, a project management method includes: dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit, wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.


According to a preferred embodiment of the present disclosure, a project management method includes: dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit, wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status.


Advantageous Effects of Disclosure

In a preferred embodiment of the present disclosure, the project management device may collect construction schedules and performance data and may automatically calculate a daily work front quantity (constructible quantity). In addition, risk levels may be classified and managed based on a construction status and a work front status (constructible quantity status).


In a preferred embodiment of the present disclosure, the project management device may automatically collect and share information on design drawings, procurement materials, and constructions in a construction project, and thus it is substantially possible to establish a construction plan through proactive construction management.


In a preferred embodiment of the present disclosure, the project management device may prepare a schedule by defining construction work packages (CWPs) each corresponding to a bundle of individual constituent units defined in design as construction targets, and thus data on designs, procurement, constructions may be automatically collected through a given system based on the construction targets.


In a preferred embodiment of the present disclosure, the project management device may simultaneously reflect drawings and material data received from an operating system used by persons in charge, and thus work fronts of individual constituent units may be independently used according to three types: drawings, materials, and drawings & materials.


In addition, the project management device may automatically output six statuses (Before Start, Start in This Month, In Progress, Late Start, Late Finish, and Complete) of CWPs based on this month and a future time point (three months later) by using performance data (Start Date, Finish Date, and Actual Quantity) of individual construction targets which are automatically collected according to a planned schedule.





BRIEF DESCRIPTION OF DRAWINGS


FIG. 1 is a view illustrating an internal configuration of a project management device according to a preferred embodiment of the present disclosure.



FIG. 2 illustrates a systemic view illustrating the project management device according to a preferred embodiment of the present disclosure.



FIGS. 3A to 3C are views illustrating the order and criteria for calculating construction statuses in the project management device according to a preferred embodiment of the present disclosure.



FIG. 4 is a view illustrating planning criteria for construction work packages (CWPs) according to a preferred embodiment of the present disclosure.



FIG. 5 is a view illustrating an example in which an enterprise resource planning (ERP) database automatically collects construction performance, design performance, and procurement performance based on individual constituent units according to a preferred embodiment of the present disclosure.



FIG. 6 is a view illustrating necessary data and result data, which are required to output a work front status according to a preferred embodiment of the present disclosure.



FIG. 7 is an example view illustrating necessary data required for calculating a work front status, and work front types according to constructions, according to a preferred embodiment of the present disclosure.



FIG. 8 is a view illustrating an example of calculating a CWP work front quantity based on construction types according to a preferred embodiment of the present disclosure.



FIGS. 9A and 9B are views illustrating an example of determining a construction status on a CWP basis after determining construction statuses of individual constituent units, according to a preferred embodiment of the present disclosure.



FIGS. 10A to 10C are views illustrating an example in which three simulations are sequentially performed according to the order of drawings (3D, ISO, and Weld map) with respect to a line, which is an individual constituent unit, for calculating a future construction quantity according to a preferred embodiment of the present disclosure.



FIGS. 11A and 11B are flowcharts illustrating a process of simulating a current work front quantity according to a preferred embodiment of the present disclosure.



FIGS. 12A and 12B are views illustrating an example in which work front statuses of CWPs for piping and steel frames are classified according to Work Front Type 1 based on the future, according to a preferred embodiment of the present disclosure.



FIGS. 13 to 15 are views illustrating a display unit of the project management device according to preferred embodiments of the present disclosure.





DETAILED DESCRIPTION

Hereinafter, the present disclosure will be described with reference to the drawings so that those of ordinary skill in the art to which the present disclosure pertains may easily understand and implement the present disclosure.



FIG. 1 is a view illustrating an internal configuration of a project management device 100 according to a preferred embodiment of the present disclosure. FIG. 2 is a systematic view illustrating the project management device 100 according to a preferred embodiment of the present disclosure.


The project management device 100 may provide a platform for automatically collecting and sharing drawing data 210, material data 220, and construction information data 230 through an enterprise resource planning (ERP) database that is used by persons in charge of design, procurement, and construction for managing a construction project. The project management device 100 may calculate a work front quantity (constructible quantity) by performing a construction management in advance based on collected work data, and may prepare a construction schedule based on the calculated quantity.


In a preferred embodiment of the present disclosure, the project management device 100 includes a division unit 110 and a display unit 120.


The division unit 110 divides a project into n sub-projects (construction work packages: CWPs) based on the construction type of the project, minimum unit areas for managing the project, and design information. The display unit 120 classifies the n CWPs based on a construction status and a work front status (constructible quantity status) and displays the n CWPs in a grid form. Examples of the display unit 120 are shown in FIGS. 13 to 15.


In a preferred embodiment of the present disclosure, the CWPs may be used as basic units of project management. Referring to Table 1, each of the CWPs may be defined as a set of individual constituent units. Referring to FIGS. 3A to 3C, for example, one construction project 310 may be divided into 70 to 90 CWPs 311 based on minimum unit areas, and then into 700 to 900 CWPs 312 based on design information. Identification codes may be allocated to the CWPs 312 for distinguishment. In addition, each CWP may be mapped with information about a zone to which the CWP belongs and a project to which the CWP belongs.













TABLE 1







Based on design
Based on one





information
CWP definition




(drawing)
(a set of


Construction
Project
(=individual
individual


types
area
constituent units)
constituent units)
Meanings







Piping
Common
Line
Construction scale:
1 CWP =





about 4,000 Mhr
n Lines





Line bundle


Steel frame

Assembly
Construction scale:
1 CWP =





about 4,000 Mhr
n assemblies





Assembly bundle


Machinery,

Item
Construction scale:
1 CWP =


equipment


about 4,000 Mhr
n items





Item bundle


Civil

Foundation
Construction scale:
1 CWP =


engineering


about 4,000 Mhr
n foundations





Foundation bundle









In Table 1, Mhr refers to the amount of work which one person does per hour.


In a preferred embodiment of the present disclosure, a database may automatically collect plans 321, 322, and 323 established for the CWPs. In the example shown in FIG. 4, criteria for a construction plan 410, a design plan 420, and a procurement plan 430 are based on CWPs. Each of the CWPs is planned based on the same design information. In this case, the design information may be information on individual constituent units 401 such as lines, assemblies, items, and foundations.


When plans are established for each of the CWPs as shown in FIG. 4, performance information input by persons in charge of design, construction, and procurement is automatically collected in an ERP database according to the plans. An example of collecting performance information in a database ERP is shown in FIG. 5. A project management device S-AWP performs matching with the performance information which is automatically collected through the ERP database.


As in the example shown in FIG. 5, when results of performance are input by each person in charge to individual constituent units 501 of a company database ERP 500 and are collected, the construction statuses of CWPs may be classified according to the collected results of performance. Based on the construction statuses of the CWPs, as in the embodiment shown in FIGS. 9A and 9B, the construction statuses of the respective individual constituent units of the CWPs are collected (S910), and results thereof are output on a CWP basis (S920). As shown in Table 2, the construction status of each CWP may be shown based on monthly cut-offs: a progress status based on a future cut-off as well as a progress status of this month based on today.









TABLE 2







Data for automatic classification of construction statues












Individual


Construction
Construction



constituent
Construction
Construction
performance
performance
Today's


units
plan start date
plan finish date
start date
finish date
date











CWP-based
Construction statuses of individual constituent units



Daily cut-off date



Present (this month): output based on today's date



Future: output based on monthly cut-off after this month









Referring to FIGS. 9A and 9B, the project management device S-AWP may divide the construction schedule of a CWP into six stages 921 to 926. The construction status of each CWP shown in FIG. 4 may also be used for filtering CWPs based on a cut-off. The six stages shown in FIGS. 9A and 9B are “Before Start” 921, “Target Start until Cut-off” 922, “In Progress” 923, “Late Start” 924, “Late Finish” 925, and “Complete” 926. “Before Start” 921 refers to a state in which all individual constituent units of the CWP are not started. “Target Start until Cut-off” 922 refers to a state in which the start date of a CWP construction plan is until a cut-off of, for example, this month M, next month M+1, the month after next M+2, or the like, and all individual constituent units are not started. “In Progress” 923 refers to a state in which at least one of the individual constituent units of the CWP is progressing or complete without Late Finish. “Late Start” 924 refers to a state in which all individual constituent units are delayed in starting and thus there is no delay in progress, no delay in termination, or no termination. “Late Finish” 925 refers to a state in which one or more individual constituent units are delayed in termination. Finally, “Complete” 926 refers to a state in which all individual structural units are complete.



FIG. 6 shows necessary data 610 and result data 620 required to output a work front status (constructionable quantity status) according to a preferred embodiment of the present disclosure. The project management device S-AWP may calculate a future work front status 612 independently based on a current cut-off and a future cut-off by using a current work front status 611 indicating prepared drawings and materials, and an estimated time of arrival (ETA) of materials and an expected drawing issue date 613 that are future-based data. The current work front status 611 refers to a quantity available for starting construction, and the future front work status 612 is used for determining the priorities of designs and procurement work.


For proactive construction management, the project management device S-AWP calculates a work front quantity for each construction type based on construction, design, and procurement information collected from each ERP database. A work front status 621 is determined by comparing a CWP-based construction plan with a CWP-based work front quantity.


A target plan (construction plan) is established for each CWP by calculating a daily target construction quantity from a total construction quantity plan allocated for a period between the start and finish dates of the target plan and a today's target construction quantity. The daily target construction quantity may be determined by “planned total construction quantity/(start date of target plan−end date of target plan).” However, the daily target construction quantity may vary depending on a distribution method. A cumulative daily target construction quantity refers to a cumulative daily target construction quantity based on today.


CWP work fronts may be determined using different pieces of information according to characteristics of construction types. As shown in FIG. 7, according to characteristics of construction types, CWP work fronts may be classified into a first work front type 710 (type 1) considering drawings and materials, a second work front type 720 (type 2) considering only materials, and a third work front type 730 (type 3) considering only drawings. As shown in FIG. 8, a CWP work front may be calculated through an operation 810 of calculating work fronts of individual constituent units according to construction types and an operation 820 of adding up the work fronts 810 on a CWP basis.


An example of calculating work fronts according to individual constituent units is as follows. FIGS. 10A to 10C shows an example in which a future construction quantity is calculated according to a preferred embodiment of the present disclosure by performing three sequential simulations according to the order of drawings (3D, ISO, and weld map) for lines which are an individual constituent units. Referring to FIGS. 10A to 10C, in an example of piping construction, the priority of construction of lines, which are individual constituent units, is set between the start date and the end date of a piping CWP plan. In addition, after collecting information on the drawing status, material list (BOM), and welding quantity of each line from ERP, a weld map is prepared using the information through the statuses shown in Table 3. In Table 3, “Spool” refers to line segment units for line manufacturing and construction when the weld map is output, and “Joint” refers to weld joint zones indicated in the weld map for actual construction.













TABLE 3





Line-






based


drawing



Design (drawing)


statuses
Description
Drawings
Units
information







3D
Before line
X
Line
Line-based necessary



drawing


materials (BOM)



preparation


Welding quantity






(temporary quantity)






calculated based on






materials


ISO
Before

Line
Line-based necessary


Drawing
detailed


materials (BOM)



construction


Welding quantity



drawing


(temporary quantity)



preparation


calculated based on






materials


Weld Map
Detailed

Line
Spool list of line-


(Shop
drawing
(for
segment
based segments


Drawing)
state
construction)
Spool
Spool-based necessary



for actual

unit
materials (BOM)



construction


Spool-based welding






positions and list






Welding quantity






(actual quantity)






calculated based on






joints









When the weld map is prepared, piping work fronts are calculated for a shop and a field. Material lists are prepared individually for the shop and the field, and materials to be excluded from calculation simulation are set. The construction quantity calculation may be performed separately for the future and the present. A future-based calculation and a present-based calculation are performed by using different pieces of design information and different pieces of procurement information in simulations as shown in Table 4.


Table 4 shows, as an example, data required for calculating a future construction quantity status and a current construction quantity status. Table 5 shows, as an example, weld map material matching for calculating a construction quantity status based on the future. Table 6 shows, as an example, matching of ISO drawings and 3D materials for calculating a construction quantity status based on the future. Table 7 shows result data obtained by calculating a construction quantity status based on the future. Table 8 shows references for future construction quantity calculation.











TABLE 4









Information necessary for simulation














Basic

Design
Procurement


Simulation
Proactive
calculation
Drawing
(drawing)
(material)


Reference
settings
methods
State
information
information





Future
Line priority +
Work front
3D
Line-based
Arrived and



Shop/Field
quantity =
(Line)
necessary
Arrival-expected



Materials +
satisfying the

materials (BOM)
material list, and



Simulation
following

Welding quantity
Receive date



exception
condition:

(temporary
And



material
Line-based

quantity) calculated
Estimated time of



reflection
(temporary)

based on materials
arrival (ETA)




quantity sum +
ISO Drawing
Line-based




spool-based
(Line)
necessary




weld quantity

materials (BOM)




sum

Welding quantity




(materials

(temporary




necessary for

quantity) calculated




each line in ISO

based on materials




and 3D states

Expected issue




and materials

date/issue date of




necessary for

ISO drawings




each spool in
Weld Map(Spool)
Spool list of line-




weld-map state

based segments






Spool-based




materials arrived

necessary




and to be

materials (BOM)




arrived)

Spool-based






welding positions






and list






Welding quantity






(actual quantity)






Weld Map issue






date


Present

Work front
3D
unused
Arrived material list




quantity =
(Line)

and arrival date




Satisfying the
ISO Drawings
unused
(Receive Date)




following
(Line)




condition:
Weld Map
Spool list of line-




Spool-based
(Spool)
based segments




Weld Quantity

Spool-based




sum

necessary




(materials

materials (BOM)




necessary for

Spool-based




spool in Weld

welding positions




Map State

and list






Welding quantity




Arrived

(actual quantity)




materials)

Weld Map issue






date

















TABLE 5







Design information
Procurement information (arrival,


Line for which weld map is issued
expected arrival) matching


(Spool-based matching)
Field arrival (stock) 90′ Elbow 12



EA + expected arrival (ETA) 3 EA










Line of first
Spool 1 materials for
90′ Elbow 4EA
4 EA Work Front/11 EA remains


priority
line of first priority
needed



Spool 2 materials for
90′ Elbow 5EA
5 EA Work Front/6 EA remains



line of first priority
needed



. . .
. . .
. . .


Line of second
Spool 1 materials for
90′ Elbow 12EA
12 EA allocation shortage/No Work


priority
line of second priority
needed
Front



Spool 2 materials for
90′ Elbow 2EA
2 EA Work Front/4 EA remains



line of second priority
needed


. . .
. . .
. . .
. . .

















TABLE 6







Design information
Matching of procurement information


ISO Drawing, Line in 3D state
(arrived, expected arrival)


(Line-based matching)
Field arrival (Stock) 90′ Elbow 12 EA



+ Expected time of arrival (ETA) 3 EA










Line of first priority
Materials for line of
90′ Elbow 4EA
4 EA Work Front/11 EA remains



first priority
needed


Line of second
Materials for line of
90′ Elbow 5EA
5 EA Work Front/6 EA remains


priority
second priority
needed


Line of third
Materials for line of
90′ Elbow 12EA
12 EA allocation shortage/No Work Front


priority
third priority
needed


Line of fourth
Materials for line of
90′ Elbow 2EA
2 EA Work Front/4 EA remains


priority
fourth priority
needed


. . .
. . .
. . .
. . .


















TABLE 7





Drawing




status
Work front conditions
Work front results







Weld Map
Materials for each spool
Work Front Date = Matching Satisfaction Time



Match all
Work Front Quantity = Welding quantity (actual quantity)


ISO, 3D
Materials for each line
Work Front Date = Matching Satisfaction Time



match all
Work Front Quantity = Welding quantity (temporary




quantity) calculated based on materials


















TABLE 8







Material Matching Information

Final












drawing
Welding
Work front quantity (W/F w/Actual)
result












Units
state
Quantity
Material matching target
Matching result values
values

















Line
3D/ISO
doesn't
Shop: Shop
matching
Application of
Construction
Conversion



Drawing
exist
making
satisfied
conversation
performance
summation





materials

formula for
No
for materials





Field: Field

each material

(temporary)





installation

((temporary)

Quantity





materials

quantity)





(Erection) +

90 Elbow





Spool List

28″ - >56 DI







Sum of







converted







quantities for







materials > 0












Matching
0
Construction performance
Welding



dissatisfactory

Yes
Performance














Spool
Weld Map
Yes
Shop: Shop making materials
Matching
Quantities
Construction
Welding




Welding
Field: Field installation
Satisfactory
of welding
performance
Joint




Joint
materials (Erection) +

joints
No
Sum




Quantity
Spool List

(actual

Actual













quantities)

quantity




Welding




Joint




Quantity




Sum > 0



matching
0
Construction
Welding



Dissatisfactory

performance
Performance





Yes










In a preferred embodiment of the present disclosure, a simulation may be performed using only a weld map when calculating a current construction quantity status. Table 8 shows an example in which procured and received materials are matched to lines according to priorities through a weld map simulation based on current individual constituent units. Table 9 shows, as an example, results of calculation of a current construction quantity status. Table 10 shows, as an example, results of current construction quantity calculation. Table 11 shows criteria for current construction quantity calculation. FIGS. 11A and 11B is a flowchart illustrating a process of simulating a current piping work front according to a preferred embodiment of the present disclosure. Even in steel frame, machinery, and civil engineering works, construction quantity statuses are calculated and classified based on individual constituent units.










TABLE 9







Line for which Weld Map is issued
Procurement information (arrival)


(Spool-based matching)
matching



Stock 90′ Elbow 12 EA










Line of first
Spool 1 materials for line
90′ Elbow 4EA
4 EA Work Front/8 EA remains


priority
of first priority
needed



Spool 2 materials for line
90′ Elbow 5EA
5 EA Work Front/3 EA remains



of first priority
needed



. . .
. . .
. . .


Line of second
Spool 1 materials for line
90′ Elbow 12EA
12 EA allocation shortage/No Work


priority
of second priority
needed
Front



Spool 2 materials for line
90′ Elbow 2EA
2 EA Work Front/1 EA remains



of second priority
needed


. . .
. . .
. . .
. . .



















TABLE 10





drawing





state
Place
Work Front Conditions
Work Front Results







Weld
Shop
Materials necessary
Work Front Date = Matching


Map

for each spool
Satisfaction Time




match all
Work Front Quantity = Welding



Field
Shop production
quantity (actual quantity)




completed Spool




Materials necessary




for each line




match all

















TABLE 11







Material Matching Information










Material










drawing
Welding
Matching
Work front quantity (W/F w/Actual)











state
Quantity
Target
Matching result values
final result values
















Weld
Yes
Shop: Shop
matching
Quantities of
Construction
Total Welding


Map
Welding
manufactured
satisfactory
welding joints
performance
Joint Quantity



Joint
materials

(actual quantities)
No



Quantity
Field: Field

Welding Joint



Yes
installation

Quantity Sum > 0




materials
Matching
0
Construction
Welding




(Erection) +
Dissatisfactory

performance
performance




Spool List


Yes









After construction quantity statuses are calculated and classified based on individual constituent units in steel frame, machinery, and civil engineering works, work fronts are classified on a CWP basis. In this case, as shown in the example of FIG. 8, work front types are classified and applied according to construction types. FIGS. 12A and 12B show examples in which work front statuses based on the future and the present are classified as work front type 1 on a CWP basis in piping and steel frame works according to preferred embodiments of the present disclosure.



FIGS. 13 to 15 show a display unit of the project management device according to preferred embodiments of the present disclosure.


An example in which CWPs are classified and displayed in a grid form based on a construction status and a work front status will be described with reference to FIGS. 13 and 14.


A display unit S1300 classifies n CWPs based on a construction status S1310 and a work front status S1320 and displays the CWPs in a grid form. FIG. 13 shows an example in which 792 CWPs 1301 are classified based on construction statuses and work front statuses. In FIG. 13, the horizontal axis of the grid form indicates construction statuses S1310 according to stages, and the vertical axis of the grid form indicates work front statuses S1320 according to stages. Referring to FIG. 14, in the rightward direction along the horizontal axis (x-axis), construction statuses S1410 of started constructions are shown, and then construction statuses S1420 of non-started constructions are shown.


The display unit 1300 includes a group of grid boxes indicating only construction statuses, and each of the grid boxes contains information on the number of CWPs belonging to a corresponding construction progress stage. For example, FIG. 13 shows a group of six grid boxes: “Complete” 1311, “Late Finish” 1312, “Late Start” 1313, “In Progress” 1314, “Target Start” 1315, and “Before Start” 1316. Referring to FIG. 13, among the 792 CWPs 1301, 175 CWPs are in “Late Finish” 1312, 95 CWPs are in “Late Start” 1313, 138 CWPs are in “In Progress” 1314, 57 CWPs are in “Target Start” 1315, and 105 CWPs are in “Before Start” 1316.


“Complete” 1311 refers to completion in performance. “Late Finish” 1312 refers to a state in which “Target Plan Finish” has come in the plan but the completion of at least one individual constituent unit is delayed in terms of performance. Among individual constituent units, Foundation refers to a civil engineering work, Assembly refers to a steel frame work, Item refers to machinery, and Line refers to piping. “Late Start” 1313 refers to a state in which “Target Plan Start” has come in the plan but the start of all individual constituent units is delayed in terms of performance. “In Progress” 1314 refers to a state in which “Target Plan Start” has come or has not yet come until a cut-off of this month, next month, or the month after next (M+1/2/3), and the construction of at least one individual constituent unit has started or completed in terms of performance. “Target Start” 1315 refers to a state in which “Target Plan Start” has come in the plan but construction has not been started in terms of performance. In addition, “Before Start” 1316 refers to a state in which “Target Plan Start” has not come in the plan, and construction has not been started in terms of performance.


The work front statuses S1320 are classified into “W/F C” 1321, “No W/F E” 1322, and “No W/F P” 1323.


“W/F C” 1321 refers to CWPs that are enough in work front, “No W/F E” 1322 refers to CWPs having drawing shortage or all shortage in work front, and “No W/F P” 1323 refers to CWPs having a material shortage or all shortage in work front.


In a preferred embodiment of the present disclosure, each grid box shows information on a construction status and a work front status. In addition, each grid box shows information on the number of CWPs having the construction status and the work front status.


For example, a first grid box 1341 indicates “Late Finish” as a construction status, “No W/F P” 1323 as a work front status, and 63 (1341a) as the number of CWPs. In a preferred embodiment of the present disclosure, risk levels may be known from the positions of grid boxes in the grid form.


Grid boxes 1341, 1342, 1343, and 1344 included in a first region 1340 of a grid board 1330 have High Risk 1345. In FIG. 13, among the 792 CWPs, 570 CWPs are in progress except for 222 CWPs that have been completed. Among the 570 CWPs, 138 CWPs are included in the first region 1340. That is, about 25% of the 570 CWPs are classified as high-risk CWPs. Grid boxes 1351, 1352, 1353, and 1354 included in a second region 1350 have Medium Risk 1355. In FIG. 13, among the 570 CWPs which are in progress, 161 CWPs are included in the second region 1350. That is, about 29% of the 570 CWPs are classified as medium-risk CWPs. Grid boxes 1361, 1362, 1363, and 1364 included in a third region 1360 have Low Risk 1365. In FIG. 13, among the 570 CWPs which are in progress, 78 CWPs are included in the third second region 1360. That is, about 15% of the 570 CWPs are classified as low-risk CWPs. Grid boxes 1371, 1372, and 1373 included in another region 1370 have No Risk 1375. In FIG. 13, about 31% of the 570 CWPs which are in progress are classified as no-risk CWPs.


In a preferred embodiment of the present disclosure, the grid board 1330 may show the first region 1340, the second region 1350, the third region 1360, and the other region 1370 with different colors.



FIG. 15 illustrates an example in which grid boxes of a display unit have a filtering function according to a preferred embodiment of the present disclosure. When information 1542a indicating the number of CWPs in a grid box 1542 of a grid board is clicked, only a CWP corresponding to the grid box 1542 is selected from n CWPs by filtering, and detailed information on the CWP is displayed. When a plurality of CWPs are selected by filtering, detailed information on each of the plurality of CWPs is displayed. The detailed information includes a construction type 1501, a CWP boundary 1502 indicating a minimum unit area for project management, a CWP identification code 1503 for identifying each CWP, a CWP category 1504, an individual constituent unit identification number 1505, construction schedule information 1520, and material quantity information 1530. The construction schedule information 1520 includes information on a construction status 1521, a target plan start date 1522, a target plan finish date 1523, an actual construction start date 1524, and an actual construction finish date 1525. The material quantity information 1530 includes a work front status information 1531, total material quantity information 1532, and target material quantity information 1533.


Methods according to embodiments of the present disclosure may be implemented in the form of program instructions executable on various computers and may be recorded on a computer-readable medium. The computer-readable medium may store one or a combination of program instructions, data files, data structures, and the like. The program instructions recorded on the computer-readable medium may be specially designed and prepared for the present disclosure, or may be known and available to those skilled in the art of computer software.


While embodiments of the present disclosure have been described with reference to the accompanying drawings, the present disclosure is not limited to the embodiments, and those of ordinary skill in the art may make various changes in form and details therein.

Claims
  • 1. A project management device comprising: a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; anda display unit that is separated into three distinct areas including (1) a first area displaying a total number of CWPs, (2) a second area displaying a grid board in which the n CWPs are displayed in a grid form, and (3) a third area displaying classifications of work front statuses,wherein the second area of the display unit includes at least four distinct regions in which grid boxes are positioned, each region of the four distinct regions being associated with a different risk level;wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses,wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,wherein in a rightward direction along the horizontal axis, a construction status of a started construction is shown, and then a construction status of a non-started construction is shown,wherein the construction type includes piping, a steel frame, machinery, and civil engineering, and the work front statuses are calculated separately based on present and future,wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, andwherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.
  • 2. The project management device of claim 1, wherein when the information on the number of CWPs in each of the grid boxes is clicked, only CWPs corresponding to the grid box are selected from the n CWPs by filtering, and detailed information on the selected CWPs are shown.
  • 3. The project management device of claim 1, wherein the display unit further comprises a group of grid boxes indicating only construction statuses, the grid boxes of the group comprise information on the number of CWPs having the construction statues.
  • 4. The project management device of claim 1, wherein when calculating the work front statuses based on the present, only the weld map is simulated to match a received procurement material to the line set according to priority.
  • 5. The project management device of claim 1, wherein work front statuses of individual constituent units are first calculated on a construction type basis while considering at least one of a drawing and a material according to the construction type of the project, and then the work front statuses of the individual constituent units are added up on a CWP basis to obtain the work front statuses based on the CWPs.
  • 6. A project management method comprising: dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; andclassifying, by a display unit that is separated into three distinct areas, the n CWPs according to construction statuses and work front statuses, by (1) displaying, in a first area of the three distinct areas, a total number of CWPs, (2) displaying, in a second area of the three distinct areas, a grid board in which the n CWPs are displayed in a grid form, and (3) displaying, in a third area of the three distinct areas, classifications of work front statuses,wherein the second area of the display unit includes at least four distinct regions in which grid boxes are positioned, each region of the four distinct regions being associated with a different risk level;wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,wherein in a rightward direction along the horizontal axis, a construction status of a started construction is shown, and then a construction status of a non-started construction is shown,wherein the construction type includes piping, a steel frame, machinery, and civil engineering, and the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, andwherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.
  • 7. A project management method comprising: dividing, by a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; andclassifying, by a display unit that is separated into three distinct areas, the n CWPs according to construction statuses and work front statuses, by (1) displaying, in a first area of the three distinct areas, a total number of CWPs, (2) displaying, in a second area of the three distinct areas, a grid board in which the n CWPs are displayed in a grid form, and (3) displaying, in a third area of the three distinct areas, classifications of the construction statuses and work front statuses,wherein the second area of the display unit is further separated into four distinct regions in which grid boxes are positioned, each region of the four distinct regions being associated with a different risk level;wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses,wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status,wherein in a rightward direction along the horizontal axis, a construction status of a started construction is shown, and then a construction status of a non-started construction is shown, andwherein the project management method further comprises selecting only CWPs corresponding to a grid box from the n CWPs by filtering when the information on the number of CWPs in the grid box is clicked by a user, wherein detailed information on the selected CWPs are shown.
  • 8. A computer readable recording medium having recorded therein a program for executing the project management method of claim 6.
  • 9. A computer readable recording medium having recorded therein a program for executing the project management method of claim 7.
PCT Information
Filing Document Filing Date Country Kind
PCT/IB2022/057916 8/24/2022 WO
Publishing Document Publishing Date Country Kind
WO2022/269584 12/29/2022 WO A
US Referenced Citations (8)
Number Name Date Kind
7409392 Greer Aug 2008 B2
20050171790 Blackmon Aug 2005 A1
20140229212 MacElheron Aug 2014 A1
20160149974 Abrams et al. May 2016 A1
20190057354 McKenzie Feb 2019 A1
20190138667 Benesh May 2019 A1
20220277268 Kojima et al. Sep 2022 A1
20220300889 Oosato et al. Sep 2022 A1
Foreign Referenced Citations (6)
Number Date Country
107256318 Oct 2017 CN
102222384 Mar 2021 KR
20210023381 Mar 2021 KR
102411939 Jun 2022 KR
2021064876 Apr 2021 WO
2021064877 Apr 2021 WO
Non-Patent Literature Citations (2)
Entry
International Search Report and Written Opinion of the International Searching Authority, in corresponding International Application No. PCT/IB2022,057916, dated Nov. 30, 2022, 9 pgs.
Advanced Work Packaging: Design through Workface Execution, Construction Industry Institute, Construction Owners Association of Alberta, Oct. 2013, vol. 1, 84 pgs.
Related Publications (1)
Number Date Country
20240193547 A1 Jun 2024 US