The present disclosure relates to a device and method for managing a construction project by establishing a project schedule and managing a performance status through exchange of information among design, procurement, and construction.
Construction project management systems do not consider drawings and material statuses or consider only material statuses or drawings. Thus, an integrated project management system configured to collect and combine together all drawings and material statues in real time is necessary for smooth construction.
In addition, because construction projects are carried out in dozens of areas at the same time, it is difficult to recognize the construction statuses and constructability of sub-projects in arbitrary areas, and information on the construction statuses and constructability of sub-projects in arbitrary areas is manually collected. In addition, it is difficult to intuitively recognize which sub-projects are highly risky.
Preferred embodiments of the present disclosure provide a device and method for managing a project by intuitively recognizing the construction status and constructability of the project and classifying and recognizing risk levels.
According to a preferred embodiment of the present disclosure, a project management device includes: a division unit configured to divide a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and a display unit configured to classify the n CWPs according to construction statuses and work front statuses and display the n CWPs in a grid form, wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.
In a preferred embodiment of the present disclosure, a horizontal axis of the grid form of the display unit indicates stage-based construction statuses, and a vertical axis of the grid form of the display unit indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status.
In a preferred embodiment of the present disclosure, the display unit shows risk information by using positions of the grid boxes of the grid form.
In a preferred embodiment of the present disclosure, when the information on the number of CWPs in each of the grid boxes is clicked, only CWPs corresponding to the grid box are selected from the n CWPs by filtering, and detailed information on the selected CWPs are shown.
In a preferred embodiment of the present disclosure, the construction type includes piping, a steel frame, machinery, and civil engineering, wherein work front statuses of individual constituent units are first calculated on a construction type basis while considering at least one of a drawing and a material according to the construction type of the project, and then the work front statuses of the individual constituent units are added up on a CWP basis to obtain the work front statuses based on the CWPs.
According to a preferred embodiment of the present disclosure, a project management method includes: dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit, wherein when the construction type is piping, the work front statuses are calculated separately based on present and future, wherein when the work front statuses are calculated based on the future, work front statuses of individual constituent units are calculated by matching a procurement arrival and a scheduled material to a line set according to priority through three independent sequential simulations, and then the work front statues of the individual constituent units are added up on a CWP basis to obtain CWP-based work front statuses, wherein the three independent sequential simulations are performed in an order of: a weld map that is a detailed drawing for performing an actual construction based on the line, which is an individual constituent unit of piping; an ISO drawing that is a drawing before preparing a detailed construction drawing; and 3D that is a drawing before preparing a line drawing.
According to a preferred embodiment of the present disclosure, a project management method includes: dividing, a division unit, a project into n construction work packages (CWPs) based on a construction type constituting the project, a minimum unit area for managing the project, and design information; and classifying, by a display unit, the n CWPs according to construction statuses and work front statuses and displaying the n CWPs in a grid form on the display unit, wherein a horizontal axis of the grid form indicates stage-based construction statuses, and a vertical axis of the grid form indicates stage-based work front statuses, wherein each of grid boxes of the grid form indicates information on a construction status and a work front status, and information on the number of CWPs having the construction status and the work front status.
In a preferred embodiment of the present disclosure, the project management device may collect construction schedules and performance data and may automatically calculate a daily work front quantity (constructible quantity). In addition, risk levels may be classified and managed based on a construction status and a work front status (constructible quantity status).
In a preferred embodiment of the present disclosure, the project management device may automatically collect and share information on design drawings, procurement materials, and constructions in a construction project, and thus it is substantially possible to establish a construction plan through proactive construction management.
In a preferred embodiment of the present disclosure, the project management device may prepare a schedule by defining construction work packages (CWPs) each corresponding to a bundle of individual constituent units defined in design as construction targets, and thus data on designs, procurement, constructions may be automatically collected through a given system based on the construction targets.
In a preferred embodiment of the present disclosure, the project management device may simultaneously reflect drawings and material data received from an operating system used by persons in charge, and thus work fronts of individual constituent units may be independently used according to three types: drawings, materials, and drawings & materials.
In addition, the project management device may automatically output six statuses (Before Start, Start in This Month, In Progress, Late Start, Late Finish, and Complete) of CWPs based on this month and a future time point (three months later) by using performance data (Start Date, Finish Date, and Actual Quantity) of individual construction targets which are automatically collected according to a planned schedule.
Hereinafter, the present disclosure will be described with reference to the drawings so that those of ordinary skill in the art to which the present disclosure pertains may easily understand and implement the present disclosure.
The project management device 100 may provide a platform for automatically collecting and sharing drawing data 210, material data 220, and construction information data 230 through an enterprise resource planning (ERP) database that is used by persons in charge of design, procurement, and construction for managing a construction project. The project management device 100 may calculate a work front quantity (constructible quantity) by performing a construction management in advance based on collected work data, and may prepare a construction schedule based on the calculated quantity.
In a preferred embodiment of the present disclosure, the project management device 100 includes a division unit 110 and a display unit 120.
The division unit 110 divides a project into n sub-projects (construction work packages: CWPs) based on the construction type of the project, minimum unit areas for managing the project, and design information. The display unit 120 classifies the n CWPs based on a construction status and a work front status (constructible quantity status) and displays the n CWPs in a grid form. Examples of the display unit 120 are shown in
In a preferred embodiment of the present disclosure, the CWPs may be used as basic units of project management. Referring to Table 1, each of the CWPs may be defined as a set of individual constituent units. Referring to
In Table 1, Mhr refers to the amount of work which one person does per hour.
In a preferred embodiment of the present disclosure, a database may automatically collect plans 321, 322, and 323 established for the CWPs. In the example shown in
When plans are established for each of the CWPs as shown in
As in the example shown in
Referring to
For proactive construction management, the project management device S-AWP calculates a work front quantity for each construction type based on construction, design, and procurement information collected from each ERP database. A work front status 621 is determined by comparing a CWP-based construction plan with a CWP-based work front quantity.
A target plan (construction plan) is established for each CWP by calculating a daily target construction quantity from a total construction quantity plan allocated for a period between the start and finish dates of the target plan and a today's target construction quantity. The daily target construction quantity may be determined by “planned total construction quantity/(start date of target plan−end date of target plan).” However, the daily target construction quantity may vary depending on a distribution method. A cumulative daily target construction quantity refers to a cumulative daily target construction quantity based on today.
CWP work fronts may be determined using different pieces of information according to characteristics of construction types. As shown in
An example of calculating work fronts according to individual constituent units is as follows.
When the weld map is prepared, piping work fronts are calculated for a shop and a field. Material lists are prepared individually for the shop and the field, and materials to be excluded from calculation simulation are set. The construction quantity calculation may be performed separately for the future and the present. A future-based calculation and a present-based calculation are performed by using different pieces of design information and different pieces of procurement information in simulations as shown in Table 4.
Table 4 shows, as an example, data required for calculating a future construction quantity status and a current construction quantity status. Table 5 shows, as an example, weld map material matching for calculating a construction quantity status based on the future. Table 6 shows, as an example, matching of ISO drawings and 3D materials for calculating a construction quantity status based on the future. Table 7 shows result data obtained by calculating a construction quantity status based on the future. Table 8 shows references for future construction quantity calculation.
In a preferred embodiment of the present disclosure, a simulation may be performed using only a weld map when calculating a current construction quantity status. Table 8 shows an example in which procured and received materials are matched to lines according to priorities through a weld map simulation based on current individual constituent units. Table 9 shows, as an example, results of calculation of a current construction quantity status. Table 10 shows, as an example, results of current construction quantity calculation. Table 11 shows criteria for current construction quantity calculation.
After construction quantity statuses are calculated and classified based on individual constituent units in steel frame, machinery, and civil engineering works, work fronts are classified on a CWP basis. In this case, as shown in the example of
An example in which CWPs are classified and displayed in a grid form based on a construction status and a work front status will be described with reference to
A display unit S1300 classifies n CWPs based on a construction status S1310 and a work front status S1320 and displays the CWPs in a grid form.
The display unit 1300 includes a group of grid boxes indicating only construction statuses, and each of the grid boxes contains information on the number of CWPs belonging to a corresponding construction progress stage. For example,
“Complete” 1311 refers to completion in performance. “Late Finish” 1312 refers to a state in which “Target Plan Finish” has come in the plan but the completion of at least one individual constituent unit is delayed in terms of performance. Among individual constituent units, Foundation refers to a civil engineering work, Assembly refers to a steel frame work, Item refers to machinery, and Line refers to piping. “Late Start” 1313 refers to a state in which “Target Plan Start” has come in the plan but the start of all individual constituent units is delayed in terms of performance. “In Progress” 1314 refers to a state in which “Target Plan Start” has come or has not yet come until a cut-off of this month, next month, or the month after next (M+1/2/3), and the construction of at least one individual constituent unit has started or completed in terms of performance. “Target Start” 1315 refers to a state in which “Target Plan Start” has come in the plan but construction has not been started in terms of performance. In addition, “Before Start” 1316 refers to a state in which “Target Plan Start” has not come in the plan, and construction has not been started in terms of performance.
The work front statuses S1320 are classified into “W/F C” 1321, “No W/F E” 1322, and “No W/F P” 1323.
“W/F C” 1321 refers to CWPs that are enough in work front, “No W/F E” 1322 refers to CWPs having drawing shortage or all shortage in work front, and “No W/F P” 1323 refers to CWPs having a material shortage or all shortage in work front.
In a preferred embodiment of the present disclosure, each grid box shows information on a construction status and a work front status. In addition, each grid box shows information on the number of CWPs having the construction status and the work front status.
For example, a first grid box 1341 indicates “Late Finish” as a construction status, “No W/F P” 1323 as a work front status, and 63 (1341a) as the number of CWPs. In a preferred embodiment of the present disclosure, risk levels may be known from the positions of grid boxes in the grid form.
Grid boxes 1341, 1342, 1343, and 1344 included in a first region 1340 of a grid board 1330 have High Risk 1345. In
In a preferred embodiment of the present disclosure, the grid board 1330 may show the first region 1340, the second region 1350, the third region 1360, and the other region 1370 with different colors.
Methods according to embodiments of the present disclosure may be implemented in the form of program instructions executable on various computers and may be recorded on a computer-readable medium. The computer-readable medium may store one or a combination of program instructions, data files, data structures, and the like. The program instructions recorded on the computer-readable medium may be specially designed and prepared for the present disclosure, or may be known and available to those skilled in the art of computer software.
While embodiments of the present disclosure have been described with reference to the accompanying drawings, the present disclosure is not limited to the embodiments, and those of ordinary skill in the art may make various changes in form and details therein.
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/IB2022/057916 | 8/24/2022 | WO |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2022/269584 | 12/29/2022 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
7409392 | Greer | Aug 2008 | B2 |
20050171790 | Blackmon | Aug 2005 | A1 |
20140229212 | MacElheron | Aug 2014 | A1 |
20160149974 | Abrams et al. | May 2016 | A1 |
20190057354 | McKenzie | Feb 2019 | A1 |
20190138667 | Benesh | May 2019 | A1 |
20220277268 | Kojima et al. | Sep 2022 | A1 |
20220300889 | Oosato et al. | Sep 2022 | A1 |
Number | Date | Country |
---|---|---|
107256318 | Oct 2017 | CN |
102222384 | Mar 2021 | KR |
20210023381 | Mar 2021 | KR |
102411939 | Jun 2022 | KR |
2021064876 | Apr 2021 | WO |
2021064877 | Apr 2021 | WO |
Entry |
---|
International Search Report and Written Opinion of the International Searching Authority, in corresponding International Application No. PCT/IB2022,057916, dated Nov. 30, 2022, 9 pgs. |
Advanced Work Packaging: Design through Workface Execution, Construction Industry Institute, Construction Owners Association of Alberta, Oct. 2013, vol. 1, 84 pgs. |
Number | Date | Country | |
---|---|---|---|
20240193547 A1 | Jun 2024 | US |