Method and forming, installing and a system for attaching a pre-fabricated pavement slab to a subbase and the pre-fabricated pavement slab so formed

Information

  • Patent Grant
  • 6663315
  • Patent Number
    6,663,315
  • Date Filed
    Monday, December 10, 2001
    23 years ago
  • Date Issued
    Tuesday, December 16, 2003
    21 years ago
Abstract
A pre-fabricated pavement slab having a binder distribution system and an interconnection system formed for attachment of the bottom surface of the slab, wherein both the binder distribution system and the interconnection system are accessible from the top surface of the slab, such that the binder material may be injected into the binder distribution and interconnection systems from the top surface of the slab.
Description




BACKGROUND OF THE INVENTION




1. Technical Field




The present invention relates generally to roadway construction and repair, and more particularly, to the formation, installation and system for attaching a pre-fabricated pavement slab, and the slab so formed.




2. Related Art




Heretofore, attempts have been made to construct and install pre-fabricated or precast pavement slabs. However, most attempts have been relatively unsuccessful due to a combination of factors. For example, it is difficult to prepare and maintain a perfectly smooth sub-grade which is necessary to uniformly support the slab. Likewise, it is difficult to connect adjacent slabs in a manner that uniformly transfers shear loading from one slab to the next. Accordingly, there exists a need in the industry for a precast pavement slab and a method of installing the slab that solves these and other problems.




SUMMARY OF THE INVENTION




A first general aspect of the present invention provides a pre-fabricated pavement slab comprising: at least one connector extending from a first end of the slab; at least one mating interconnection formed within a second end thereof to receive the connector, wherein the interconnection is accessible from a top surface of the slab; and a plurality of channels formed within a bottom surface of the slab, wherein at least one channel is accessible from the top surface of the slab.




A second general aspect of the present invention provides a system for installation of a pre-fabricated pavement slab comprising: a binder distribution system formed for attachment of a bottom surface of the slab and accessible from a top surface of the slab; and an interconnection system along edges of the slab and accessible from the top surface of the slab.




A third general aspect of the present invention provides a method of installing a pre-fabricated pavement slab, comprising: placing the slab on a graded subbase; and uniformly distributing a binder material along a bottom surface of the slab via at least one access in a top surface of the slab.




A fourth general aspect of the present invention provides a method of forming a prefabricated pavement slab comprising: providing a form for forming binder distribution system within a bottom surface of the slab; pouring a pavement material into the form; and incorporating a plurality of interconnections within a first end of the slab.




A fifth general aspect of the present invention provides a device comprising: a first slab and a second slab, wherein the first and second slabs further comprise a binder distribution system formed within a bottom surface of the first and second slabs; and a shear transfer device between the first and second slabs.




The foregoing and other features of the invention will be apparent from the following more particular description of the embodiments of the invention.











BRIEF DESCRIPTION OF THE DRAWINGS




The embodiments of this invention will be described in detail, with reference to the following figures, wherein like designations denote like elements, and wherein:





FIG. 1

depicts a plan view of a pre-fabricated pavement slab in accordance with the present invention;





FIG. 2

depicts a cross-sectional view of the pre-fabricated pavement slab in accordance with the present invention;





FIG. 3

depicts a cross-sectional view of a transverse dowel bar in accordance with the present invention;





FIG. 4A

depicts a cross-sectional view taken along line


4





4


of

FIG. 1

, of a connector slot in accordance with embodiments of the present invention;





FIG. 4B

depicts

FIG. 4A

using an alternative connector slot in accordance with embodiments of the present invention;





FIG. 4C

depicts

FIG. 4A

using an alternative connector slot in accordance with embodiments of the present invention;





FIG. 5

depicts a cross-sectional view taken along line


5





5


of

FIG. 1

, of a channel in accordance with embodiments of the present invention;





FIG. 6

depicts a cross-sectional view taken along line


6





6


of

FIG. 1

, of the channel in accordance with embodiments of the present invention;





FIG. 7

depicts a cross-sectional view taken along line E—E of

FIG. 1

, of a connector slot in accordance with embodiments of the present invention;





FIG. 8A

depicts a cross-sectional view taken along line


8





8


of

FIG. 1

, of a connector slot in accordance with embodiments of the present invention;





FIG. 8B

depicts

FIG. 8A

using an alternative connector slot in accordance with embodiments of the present invention;





FIG. 8C

depicts

FIG. 8A

using an alternative connector slot in accordance with embodiments of the present invention;





FIG. 9

depicts a top mat in accordance with the present invention;





FIG. 10

depicts a bottom mat in accordance with the present invention;





FIG. 11

depicts a gasket in accordance with the present invention;





FIG. 12

depicts

FIG. 11

using additional sections of a gasket in accordance with embodiments of the present invention;





FIG. 13A

depicts a cross-sectional view of a connector and an existing slab in accordance with embodiments of the present invention;





FIG. 13B

depicts a cross-sectional view of a two piece connector and an existing slab in accordance with embodiments of the present invention;





FIG. 13C

depicts a plan view of a slot cut in an existing slab in accordance with the present invention;





FIG. 13D

depicts a cross-sectional view of a slot cut in an existing slab in accordance with the present invention;





FIG. 14

depicts a grading device used in accordance with the present invention; and





FIG. 15

depicts a form used to construct the slab in accordance with the present invention.











DESCRIPTION OF THE PREFERRED EMBODIMENTS




Although certain embodiments of the present invention will be shown and described in detail, it should be understood that various changes and modifications may be made without departing from the scope of the appended claims. The scope of the present invention will in no way be limited to the number of constituting components, the materials thereof, the shapes thereof, the relative arrangement thereof, etc. Although the drawings are intended to illustrate the present invention, the drawings are not necessarily drawn to scale.




Referring to the drawings,

FIG. 1

shows a plan view of a pre-fabricated pavement slab


10


. The slab


10


may be constructed by pouring a pavement material, such as concrete, or other similarly used material, into a form


60


, having a plurality of raised channel forming surfaces


62


, raised slot forming surfaces


64


, connector openings


66


and port forming surfaces


68


(refer to FIG.


15


). The raised channel forming surfaces may be independent from the raised slot forming surfaces as shown in FIG.


15


. The slab


10


may be used in high traffic areas, such as highways, on/off ramps, airport runways, toll booth areas, etc. The pavement slab


10


is approximately 10-12 feet (3.049-3.658 m) wide W, as required by the New York State Department of Transportation, and approximately 18 feet (5.486 m) in length L. The slabs


10


may range in thickness T from approximately 9-12 inches. These dimensions, L, W, T, however, may vary as desired, needed or required and are only stated here as an example.




The top surface


9


of the slab


10


is a roughened astroturf drag finish, while the sides


11




a


and


11




b


, the ends


11




c


and


11




d


, and bottom surface


13


of the slab


10


have a substantially smooth finish (refer to

FIG. 2

, which shows a cross-sectional view of a corner of the slab


10


). The side


11




a


or the side


11




b


may be a first edge and the end


11




c


or the end


11




d


may be a second edge. The bottom surface


13


, the sides


11




a


and


11




b


, and the ends


11




c


and


11




d


of the slab


10


come together to form a chamfer


15


around the perimeter of the slab


10


. The chamfer


15


prevents soil build-up between two mating slabs which may occur if the slab


10


is tipped slightly during installation.




The slab


10


further includes a plurality of connectors


12


that may comprise transverse slippable connecting rods or dowels. The plurality of connectors may be embedded within a first end of the slab


10


. In one embodiment, the connectors


12


are post tensioned interconnections, as known and used in the industry, wherein multiple slabs may be connected in compression. The connectors


12


are spaced approximately 1 ft. apart along the width W of the slab


10


, and comprise steel rods, or other similar material conventionally known and used. Each connector


12


is of standard dimensions, approximately 14 inches in length and 1.25 inches in diameter. The slippable connectors


12


are mounted truly parallel to the longitudinal axis L of the slab


10


to allow adjacent slabs


10


to expand and contract without inducing unwanted damaging stresses in the slabs


10


. The connectors


12


are preferentially mounted such that approximately half of the connector


12


is embedded within the pavement slab


10


and half of the connector


12


extends from the end of the slab


10


.





FIG. 3

shows a cross-sectional view (along line


3





3


of

FIG. 1

) of the slab


10


and a connector


12


extending therefrom. As illustrated, the connectors


12


are embedded within a first end


11




d


of the slab


10


at approximately the midpoint of the thickness T of the slab


10


. The connectors


12


aid in transferring an applied shear load, i.e., from traffic, evenly from one slab


10


to the adjacent slab, without causing damage to the slab


10


.




The slab


10


further includes a plurality of inverted interconnection slots


14


formed within the bottom surface


13


of the slab


10


at a second end


11




c


thereof. Each interconnection slot


14


is sized to accommodate the connectors


12


extending from the end of an adjacent slab


10


, thereby forming an interconnection between adjacent slabs once the slot


14


is filled around the connectors


12


with a binder material.

FIG. 4A

shows a cross-sectional view (along line


4





4


of

FIG. 1

) of an interconnection slot


14


, wherein the slot


14


is wider at the top of the slot


14


than at the bottom of the slot


14


. This wedged shape prevents the slab


10


from moving downward with respect to the adjacent slab with the application of a load once the binder material has reached sufficient strength.




In the alternative, the interconnection slots


14


may take the form of a “mouse hole” having a pair of cut-outs or holes


17


formed on both sides thereof, as illustrated in FIG.


4


B. In this case, when the slots


14


are filled with a binder material, the holes


17


form shear pins on the sides of the mouse hole that would have to be sheared in order for the slab


10


to move downward with respect to the adjacent slab. In the alternative, the slots


14


may have vertically oriented sides, as illustrated in FIG.


4


C. In this case the sides of the slot


14


are sandblasted to provide a roughened surface, thereby frictionally limiting the ability of the slab


10


to move downward with respect to the adjacent slab.




As illustrated in

FIGS. 4A-4C

, each interconnection slot


14


further includes an opening, access or port


16


. Tn particular, a binder material such as structural grout or concrete, a polymer foam material, or other similar material, may be injected within each port


16


thereby filling the interconnection slot


14


receiving the inserted connector


12


(not illustrated) to secure adjacent slabs end to end.




It has been previously noted that the connectors


12


are preferentially mounted as described above with approximately half of the connector


12


embedded in an adjacent slab while the other half is engaged and embedded in the interconnections slots


14


of slab


10


. Alternatively, the same connector


12


may be preplaced on the subgrade, not shown, such that interconnections slots


14


in both slabs engage the connectors


12


, such interconnection slots


14


being subsequently filled with binder material in the same manner described in the foregoing.




The slab


10


further includes a plurality, in this example three, channels


18


running longitudinally along the length L of the slab


10


. The channels


18


formed within the bottom surface


13


of the slab


10


facilitate the even dispersement of a bedding material, such as bedding grout or concrete, a polymer foam material, or other similar material, to the underside of the slab


10


. As shown in

FIG. 5

, which depicts a cross-sectional view of the slab


10


(along line


5





5


of FIG.


1


), each channel


18


includes a port


20


at each end of the channel


18


(one end shown in FIG.


5


). Each port


20


extends from the top surface


9


of the slab


10


to the channel


18


, thereby providing access to the channel


18


from the top surface


9


of the slab


10


. This facilitates the injection of bedding material beneath the bottom surface


13


of the slab


10


via ports


20


which are accessible from the top surface


9


after the slab


10


has been installed.




As illustrated in

FIG. 6

, which shows a cross-sectional view of the channels


18


along a line


6





6


of

FIG. 1

, the channels


18


are in the shape of half round voids. The rounded shape aids in the uniform distribution of bedding material along the bottom surface


13


of the slab


10


to fill any gaps between the slab


10


and the subbase (not shown). In the alternative, the channels


18


may take other shapes, such as rectangles, etc. Furthermore, instead of using channels


18


to facilitate the even dispersement of the bedding material beneath the slab


10


, a pipe system may be used. For instance, the pipe system (not shown) may comprise a plurality of pipes, approximately one inch in diameter, having holes or continuous slots formed therein.




The slab


10


further includes a plurality of interconnection slots


24


, shown in this example within a first side


11




a


of the slab


10


(FIG.


1


). The slots are illustrated more clearly in FIGS.


7


and


8


A-


8


C. In particular,

FIG. 7

shows a cross-sectional view of an interconnection slot


24


taken along a line


7





7


of FIG.


1


. As illustrated, each interconnection slot


24


comprises a pair of openings, accesses or ports


26


at each end of the slot


24


which extend from the top surface


9


of the slab


10


to the interconnection slot


24


thereunder.




The slab


10


further includes a plurality connectors


69


that may comprise, longitudinal connectors, non-slippable connecting rods, or dowels embedded within a second side


11




b


of slab


10


along the length L of the slab


10


. As with the connectors


12


, the connectors


69


may be post tensioned interconnections. The connectors


69


may be one-piece, where approximately half of the connector


69


is embedded within the pavement slab


10


and half of the connector


69


extends from the second side lib of the slab


10


. Alternatively, the connector


69


may be of a two-piece design comprising a first connector


54


and a second connector


56


as shown in FIG.


13


B. The two-piece design would be used if it is desirable to keep shipping width of slab


10


to a minimum.





FIG. 8A

depicts a cross-sectional view of the interconnection slot


24


and port


26


along line


8





8


of FIG.


1


. Similar to the interconnection slots


14


along the ends


11




c


and


11




d


of the slab


10


(shown in FIGS.


4


A-


4


C), the interconnection slots


24


along the sides


11




a


and


11




b


of the slab


10


may alternatively take the form of a mouse hole


24


having cut-outs or holes


25


(FIG.


8


B), or a slot


24


having vertically oriented sandblasted sides (FIG.


8


C). The interconnection slots


24


receive connectors


69


that may comprise non-slippable connecting rods or dowels located within and extending from an adjacent new slab


10


or from an existing slab


50


, such has been described embedded in the second side


11




b


of slab


10


.




After the slab has been installed and the connectors are in their final location, a binder material, such as structural cement-based grout, a polymer foam, etc., is then injected into the interconnection slots


24


, having the rods inserted therein, from the top surface


9


of the slab


10


via the ports


26


. This aids in rigidly interconnecting adjacent slabs of the roadway and facilitates a relatively even load transfer between lanes.




The slab


10


further includes a top mat


32


and a bottom mat


34


(

FIGS. 9 and 10

, respectively). Both mats


32


,


34


comprise reinforcing bars, or in the alternative reinforced steel mesh. The top mat


32


, comprising longitudinal bars


31


and at least two transverse or cross bars


29


, is formed within the slab


10


substantially near the top surface


9


of the slab


10


. The top mat


32


prevents the slab


10


from “curling” or bending at the edges as a result of cyclic loading produced by temperature differentials. Likewise, the bottom mat


34


comprises longitudinal bars


33


and transverse or cross bars


35


formed within the slab


10


substantially near the bottom surface


13


of the slab


10


. The bottom mat


34


provides the slab


10


with additional reinforcement and stability during handling.




A seal or gasket


36


, comprising a compressible closed cell foam material, such as neoprene foam rubber or other similar material, is attached to the bottom surface


13


of the slab


10


around the perimeter of the slab


10


, as illustrated in FIG.


11


. The gasket


36


is approximately 12 mm thick and 25 mm wide, and is soft enough to fully compress under the weight of the slab


10


. The gasket


36


forms a chamber or cavity


38


thereby sealing the boundary of the slab


10


. This allows for the application of pressure to the bedding material during installation to ensure that all voids between the bottom surface


13


of the slab


10


and the subbase are filled.




Optionally, additional sections of the gasket


36


, having the same or similar width and thickness, may be applied to the bottom surface


13


of the slab


10


to form a plurality of individual chambers or cavities


38


, as illustrated in FIG.


12


. The additional sections of the gasket


36


forming the cavities


38


reduce the amount of upward pressure exerted on the slab


10


during the injection of the bedding material as compared to that experienced by the slab


10


using one large sealed cavity (as illustrated in FIG.


11


). Forming at least 3 to 4 cavities


38


effectively reduces the lift force produced from below the slab


10


as the bedding material is being forced thereunder.




To install the slab


10


, connectors


12


may first need to be installed along the transverse end of an existing slab


50


and connectors


69


may need to be installed along the longitudinal side of the existing slabs


50


, to match interconnection slots


14


and


24


, respectively. If so, a hole may be drilled within the existing slab


50


, using carbide tipped drill bits, or other similar tools. Thereafter, the connector


12


or the connector


69


is inserted within each hole, along with a binder material, such as a cement-based or epoxy grout, polymer foam, etc., such that approximately one half of the connector


12


or the connector


69


extends therefrom, as illustrated in

FIGS. 3 and 13A

, respectively. Slab


10


and existing slab


50


may be the same structurally and both slab


10


and existing slab


50


may have interconnect slots and/or connectors.




Alternatively to installing connectors


12


and connectors


69


in the existing slab to mate with the interconnection slots


14


and


24


in the slab


10


, the same connectors


12


and connectors


69


may be embedded in the slab


10


such that they extend from the slab


10


as described above. In this case, a vertical slot


70


is cut in the existing slabs


50


using a diamond blade concrete saw, or other similar tool, in locations corresponding to the extended connectors


12


and connectors


69


in slab


10


(refer to FIGS.


13


C and


13


D). The sawing operation would be done ahead of the slab


10


installation operation. The slots


70


would be opened up and burrs removed using a light-weight pneumatic chipping hammer, or other similar tool. This option would be chosen to avoid the above described drilling process that should be done during the night-time grading operation.




In preparation for slab installation, the replacement area (the area in which the slab


10


will be placed) is cleaned of all excess material to provide a subbase or sub-grade approximately 25 mm below the theoretical bottom surface


13


of the slab


10


. The subbase is graded with conventional grading equipment such as a grader, skid steer loader, etc., and fully compacted with a vibratory roller or other similar device. The compacted subgrade is subsequently overlaid with approximately 30 mm of finely graded material such a stone dust that can be easily graded with the precision grading equipment described below.




The stone dust is then graded with a conventional screeding device or a laser-controlled screeding device, such as the Somero Laser Screed™ (Somero Enterprises of Jafrey, N.H.), as illustrated in FIG.


14


. The Somero Laser Screed™ is controlled by a rotating laser beam that is continuously emitted by a laser transmitter


42


, located at a remote location and at least 6-8 feet above ground level. The transmitter is adjusted to emit a beam of unique cross-slope and grade corresponding to the plane required for the slab


10


. The cross-slope allows for water run-off and the grade represents the longitudinal slope required for vertical alignment of the roadway.




For straight highways, where the cross-slope and the grade are constant, the rotating laser beam set as described above will serve to set multiple slabs. For both horizontally and vertically curved highways the rotating laser beam will have to be set to a distinct plane for each slab. This continuous adjustment may be done manually or automatically with software designed for that specific purpose. Alternatively, the screed may by controlled by other electronic means unique to the Somero Laser Screed™.




Specific to the Somero Laser Screed™, laser receivers


44


, mounted on posts


46


above the screed


48


, receive and follow the theoretical plane emitted from the transmitter


42


as the grading screed


48


is pulled over the replacement area. After the first grading pass, the stone dust layer is fully compacted with a vibratory roller or other similar device and a second grading pass is made in which the subbase is brought to within {fraction (1/16)}


th


of an inch (or “Super-graded”) of the required theoretical plane. After super-grading has been completed, the stone dust layer is dampened with water, as needed for the subsequent grouting process, in final preparation for installation of the slab


10


.




The slab


10


is placed within the replacement area such that the slab


10


contacts the subbase uniformly so as not to disrupt the subbase or damage the slab


10


. During placement, the slab


10


is lowered vertically to the exact location required to match the existing adjacent slabs


50


. Care is taken to insure the interconnection slots


14


and


24


, within the sides and end (if an adjacent slab


50


is present at the end of the slab


10


) of the slab


10


are lowered over the connectors


12


and connectors


69


extending from the ends and sides of the adjacent slabs


50


respectively. In the case where connectors


12


and connectors


69


extend from the slab


10


, the slab


10


is also lowered vertically and carefully to insure the connectors


12


and connectors


69


are set within the slots


70


of the adjacent existing slabs


50


. At this time, the slab


10


should be within 6+/− mm of the theoretical plane emitted from the rotating laser transmitter


42


. In the event the surface


9


of the slab


10


is out of the required tolerance it is planed with a conventional diamond grinder until it is brought within tolerance.




The interconnection slots


14


,


24


or


70


, as the case may be are filled from the top surface


9


of the slab


10


with a binder material such as structural grout, or in the alternative, a polymer foam material, thereby fastening the slab


10


to the connectors


12


,


54


,


56


,


69


or the slot


70


of the adjacent existing slabs


50


. In particular, the binder material is injected under pressure into a first port


16


,


26


of the interconnection slots


14


,


24


, respectively, until the binder material begins to exit the port


16


,


26


at the other end of the interconnection slot


14


,


24


. It is desirable for the binder material within the slots


14


,


24


to reach sufficient strength to transfer load from one slab to the other before opening the slab


10


to traffic.




The chamber(s)


38


formed by the gasket


36


on the bottom surface


13


of the slab


10


is/are then injected from the top surface


9


of the slab


10


with bedding material, such as grout including cement, water and fly ash, or in the alternative with a polymer foam material. In particular, starting from the lowest or downhill region, bedding material is injected into the port


20


at one end of the channel


18


until the bedding material begins to exit the port


20


at the other end of the channel


18


. The bedding material is injected into the channels


18


to ensure that all voids existing between the bottom surface


13


of the slab


10


and the subbase, regardless of size, are filled. The slab


10


should be monitored during injection of the bedding material to ensure the slab


10


is not vertically displaced due to the upward pressure created thereunder. It is desirable for the bedding material under the slab


10


to reach a minimum strength of approximately 10.3 MPa before opening the slab


10


to traffic.




It should be noted that due to the precision of the Super Graded subbase, the channels


18


may not need to be filled prior to exposure of the slab


10


to traffic. Rather, the channels


18


may be filled within 24-48 hours following installation of the slab


10


without damaging the slab


10


or the subbase. This is particularly useful due to time constraints.




While this invention has been described in conjunction with the specific embodiments outlined above, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art. Accordingly, the embodiments of the invention as set forth above are intended to be illustrative, not limiting. Various changes may be made without departing from the spirit and scope of the invention as defined in the following claims.



Claims
  • 1. A method of fabricating a prefabricated pavement slab with an area bounded by ends and sides comprising:providing a form for defining a binder distribution system within a bottom surface of the prefabricated pavement slab, wherein the binder distribution system does not allow a binder to be distributed beyond the area; providing within the form at least one surface for defining a raised slot; providing within the binder distribution system at least one surface for defining a raised channel that is independent from the raised slot; providing within the form at least one surface for defining a port extending from the raised slot to a top surface of the prefabricated pavement slab; providing within the form at least one surface for defining a port extending from the raiscd channel to the top surface of the prefabricated pavement slab; pouring a pavement material into the form; and incorporating a plurality of interconnections within a first end of the prefabricated pavement slab.
  • 2. The method of claim 1 further comprising, providing within the form a surface for defining a plurality of mating interconnection slots in a second end of the slab.
  • 3. The method of claim 1, wherein said plurality of interconnections comprise reinforcement rods.
  • 4. The method of claim 1, wherein the pavement material comprises a cementitious material.
  • 5. The method of claim 1 further comprising, providing within the form at least one surface for defining a rounded top section on the raised slot and at least one surface for defining a shear pin along a side of the raised slot.
  • 6. The method of claim 1 a surface to form, wherein the raised slot has a top width greater than a base width.
  • 7. A method of fabricating a prefabricated pavement slab with an area bounded by ends and sides comprising;providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab wherein said binder distribution system does not allow a binder to be distributed beyond said area, said form further having at least a second surface for defining an interconnection slot within the bottom surface of the prefabricated pavement slab; and pouring a pavement material into the form.
  • 8. The method of claim 7, wherein the at least first surface is a raised surface.
  • 9. The method of claim 7, wherein the at least second surface is a raised surface.
  • 10. The method of claim 7 further comprising, providing within the form at least one surface form for defining a port extending from the interconnection slot to a top surface of the slab.
  • 11. The method of claim 7 further comprising, providing within the form at least one surface for defining a port extending from the binder distribution system to a top surface of the slab.
  • 12. A method of fabricating a prefabricated pavement slab comprising:providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab and at least a second surface for defining an interconnection slot within a first side of the slab wherein said interconnection slot does not extend to a second side of the slab, wherein said interconnection slot includes a rounded top section and a shear pin along a side of the interconnection slot; and pouring a pavement material into the form.
  • 13. A method of fabricating a prefabricated pavement slab comprising:providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab and at least a second surface for forming defining an interconnection slot within a first side of the slab wherein said interconnection slot does not extend to a second side of the slab, wherein said interconnection slot includes a rounded top section and a shear pin along a side of the interconnection slot; and pouring a pavement material into the form.
  • 14. A method of fabricating a prefabricated pavement slab comprising;providing a form having a plurality of first surfaces for forming defining a plurality of first interconnection slots at a first edge of the slab and a plurality of second surfaces for forming defining a plurality of second interconnection slots at a second edge of the slab wherein said second edge is not parallel to said first edge of the slab, further wherein said plurality of first interconnection slots are open to a bottom surface of said prefabricated pavement slab and said plurality of first interconnection slots do not extend to the second edge of the slab; and pouring a pavement material into the form.
  • 15. The method of claim 14, wherein the first surface is a raised surface.
  • 16. The method of claim 14, wherein the second surface is a raised surface.
  • 17. The method of claim 14 further comprising, providing within the form at least one surface for defining a port extending from the plurality of first interconnection slots to a top surface of the slab.
  • 18. The method of claim 14 further comprising, providing within the form at least one surface for defining a port extending from the plurality of second interconnection slots to a top surface of the slab.
  • 19. A method of fabricating a prefabricated pavement slab comprising;providing a form having at least one surface for defining an interconnection slot on the bottom surface of the slab such that the interconnection slot comprises a geometry that will prohibit a binder material that is placed in the interconnection slot from moving in a vertical direction thereby preventing the slab from moving in a vertical direction with respect to an adjacent slab, further wherein said interconnection slot does not extend an entire length of said bottom surface of the slab; and pouring a pavement material into the form.
  • 20. The method of claim 19, wherein the at least one surface is a raised surface.
  • 21. The method of claim 19 further comprising, providing within the form at least one surface for defining a port extending from the interconnection slot to a top surface of the slab.
  • 22. The method of claim 19 further comprising, providing within the form at least one surface for defining a rounded top section on the interconnection slot and at least one surface for defining a shear pin along a side of the interconnection slot.
  • 23. The method of claim 19 further comprising, providing within the form a surface for defining the interconnection slot with a top width greater than a base width.
  • 24. The method of claim 19 further comprising, attaching a compressible material to a bottom surface of said prefabricated pavement slab.
  • 25. A method of forming a prefabricated pavement slab comprising:providing a form having at least one void for defining a binder distribution system within a bottom surface of the prefabricated pavement slab wherein the binder distribution system includes at least one channel, said form further having at least one surface for defining at least one interconnection slot along an edge of the slab, wherein said at least one channel is independent and not parallel with said at least one interconnection slot; and pouring a pavement material into the form.
  • 26. The method of claim 25, wherein said at least one interconnection slot is shaped to prevent vertical movement of the slab with respect to an adjacent slab.
  • 27. A method of fabricating a prefabricated pavement slab with an area bounded by the length and width, wherein said length exceeds about 13 feet, comprising;providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab wherein said binder distribution system does not allow a binder to be distributed beyond said area, said form further having at least a second surface for defining an interconnection slot within the bottom surface of the prefabricated pavement slab; and pouring a pavement material into the form.
  • 28. A method of fabricating a prefabricated pavement slab with an area bounded by the length and width, wherein said width exceeds about 9 feet, comprising;providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab wherein said binder distribution system does not allow a binder to be distributed beyond said area, said form further having at least a second surface for defining an interconnection slot within the bottom surface of the prefabricated pavement slab; and pouring a pavement material into the form.
  • 29. A method of fabricating a prefabricated pavement slab with an area bounded by the length and width, wherein a ratio of the width of the slab to the thickness of the slab is at least about 10:1, comprising;providing a form having at least a first surface for defining a binder distribution system within a bottom surface of the prefabricated pavement slab wherein said binder distribution system does not allow a binder to be distributed beyond said area, said form further having at least a second surface for defining an interconnection slot within the bottom surface of the prefabricated pavement slab; and pouring a pavement material into the form.
Parent Case Info

This application is a divisional of Ser. No. 09/655,129, filed on Sep. 5, 2000.

US Referenced Citations (28)
Number Name Date Kind
850948 Mohr Apr 1907 A
2780150 Yeoman Feb 1957 A
3072994 Brickman Jan 1963 A
3152421 Mittendorf Oct 1964 A
3503165 Hardt Mar 1970 A
3640040 MacLean et al. Feb 1972 A
3712187 Stelling Jan 1973 A
3918222 Bahramian Nov 1975 A
4087072 Olsen May 1978 A
4147009 Watry Apr 1979 A
4178343 Rojo, Jr. Dec 1979 A
4186160 Landreth Jan 1980 A
4239176 Salazar Dec 1980 A
4305680 Rauchfuss, Jr. Dec 1981 A
4353666 Brandley Oct 1982 A
4508308 Rossin et al. Apr 1985 A
4605336 Slaw, Sr. Aug 1986 A
4685264 Landis Aug 1987 A
4702048 Millman Oct 1987 A
4972537 Slaw, Sr. Nov 1990 A
5373675 Ellison, Jr. Dec 1994 A
5397096 Nelson Mar 1995 A
5443324 Sullivan Aug 1995 A
5588775 Hagenah Dec 1996 A
5797231 Kramer Aug 1998 A
5957619 Kinoshita et al. Sep 1999 A
6003278 Weaver et al. Dec 1999 A
6052960 Yonemura Apr 2000 A
Foreign Referenced Citations (2)
Number Date Country
406280328 Oct 1994 JP
11229306 Aug 1999 JP