The invention relates to the field of the production of concrete products. Particularly, the invention relates to a method for the production of long, prestressed concrete products using mobile moulds.
Prestressed concrete products are traditionally prepared on long, mobile prestressing beds. Thereby, all production machines move along the casting beds, whereby their work area is very large. The concrete must be transferred to mobile casting machines in various parts of the production area, whereafter the fresh concrete is fed to moulds while the machines move across the mould. After hardening, the prestressing wires are cut, and the necessary cutting and boring operations are carried out in situ. The products are transferred to a store, and after cleaning, the prestressing wires can be fitted on the casting beds for the next casting.
A so-called carousel production system is known for short products, in which instead of fixed casting beds and mobile machines, mobile moulds and fixed casting and other work-stations are used. Said system is more flexible than the system with fixed casting beds, but when long prestressed products, or several elongated prestressed products are to be produced in series on the same casting bed, the hardening stage will slow down the production, because the filled moulds are to be left alone for a long time before the hardened product can be removed. From patent application GB 9607158.4 a plant for the production of prestressed concrete products is known, in which the concrete products are cast on beds provided with tensioning wires, while said beds move under the stationary casting machine. After the whole length of the product is cast, the whole product is pushed sideways in a heated hardening space. After hardening, the whole product passes through a sawing station in the direction opposite to the casting direction. The products, cut to their final length, are lifted from the bed and brought out of the circulation, after which the casting bed is transferred to a furnishing station by pushing sideways, cleaned and furnished for the next casting.
Said publication GB 9607157.4 discloses five parallel stations for the hardening stage, which arrangement is in harmony with the unloading and equipment stations of the other side of the circulation, but which considerably limits the amount of castings being at the same time in the hardening stage.
The present invention relates to a method for the production of prestressed concrete products. The method is based on a fixing casting station and mobile, long casting beds. All production machines remain at their work stations, and correspondingly the moulds and the products are moved. In addition, the invention relates to a plant for implementing the method of the invention.
The casting can be carried out by using an extruding technique or a slip casting technique, as has been disclosed e.g. in the FI patent 85350, or by using another slip casting technology, as described in the FI patent 101208. The casting speed of the casting machine is adapted according to the motion of the mould. The products can be, for example, ordinary prestressed hollow-core concrete slabs, or pretensioned beams. The prestressing is carried out against the mould, whereby no separate floor-based anchors are needed.
After the casting, the casting bed together with the product cast thereon, is transferred sideways from the casting line to a heat treatment using lifting equipment. The transfer of the casting beds sideways by lifting is advantageous in respect of space utilization, because in that case the moulds together with their cast products, can be stacked in a heat treatment space, and several stacks can be formed adjacent to each other. The lifting to the heat treatment space, and after hardening to a further processing line, can easily be automated. After hardening, the combination of mould and product is lifted to the beginning of a reinforcement line, where the product is lifted as a long uniform body sideways to a finishing processing line, where it moves forward along a roller track in order to be cut into pieces of a predetermined length. As the product is lifted off, the mould becomes free, and is thereafter transported along the roller track in order to be furnished with reinforcements, and further to a intermediate store to wait for the next casting. During said transfer the mould is cleaned and provided with prestressing wires. Thus, no separate operational steps are needed for said procedure.
All moulds to be used in the process are separate units of the desired length, which are circulated along with the production from the furnishing station of the mould to a casting station, from the casting station to heat treatment and from there further to an unloading station. Preferably, the casting length is more than 30 m. The moulds are designed to withstand the prestressing. Before the reinforcement, the mould is brushed and oiled mechanically. The prestressing wires are fitted to a mould in connection with the transfer of the mould at a station 5, near to which a wire store 21 is arranged. It is advantageous to assemble the wires during the transfer of the mould from a fixed feeding station, in contrast to the method of the above described prior art.
The
The mobile locking plates are thus constructed, that in addition to being wire fastening points, they also act directly as starting and finishing stopper plates during the casting.
The casting can be started directly from the starting stopper plate, and be finished directly at the finishing stopper plate. In this way, it is possible to entirely avoid starting and finishing reject, as well as, due to the movability of the locking plates, to minimize the amount of wasted wire.
The sidewise transfer from the reinforcement position 5 to the beginning of the casting line is carried out by means of sidewise transfer lifting equipment which is provided in the ceiling of the hall. The moulds already reinforced can be intermediately stored at the furnishing station of the hall before they are transferred to the beginning of the casting line.
On the casting line, the mould is moved by means of friction drives in longitudinal direction on the roller track 2 (FIG. 1). The concrete station 10 is placed partly on the side of the hall and partly above the casting station 3, whereby the concrete can be led directly to a casting machine. Therefore, no separate transfer conveyors are needed. The concrete station can be unattended, as can the casting station, whereby the operation of the various units is controlled from a common, suitably located control room.
The casting station comprises fixed casting machines operating in parallel, of which preferably 1 to 3 or even more are provided, depending on the capacity of the production plant. The functions related to the maintenance of the casting machines can be placed adjacently to the casting station, for example at station 11. At the casting station, several casting machines can operate simultaneously, whereby transfer roller tracks for the mould must be provided in the same number as casting machines.
Immediately after casting, as the concrete is still fresh, required openings are provided, for example according to markings made by a marking machine, or a machine for making openings is automatically controlled on the basis of slab data. The concrete removed from the openings can be returned into the concrete station mixer or directly into the casting machine. After hardening, the prestressing wires in the openings can be removed at the finishing processing station.
As the bed is completely cast and the possible openings are provided, the bed is moved to heat treatment space 4 (FIG. 1). Preferably, the heat treatment space is an isolated, closed space, separated from other spaces with a separation wall. Therefore, the temperature and moisture of the heat treatment space can be defined case by case, depending on the speed of the production cycle. The moulds can move along the roller tracks to the heat treatment space and from there through openings provided in the separation wall.
In the heat treatment space, the mould is moved by means of the transversal transfer lifting equipment to a pre-programmed hardening station 12.
The sufficient lifting precision can be obtained by using height measurement, for example a pulse sensor, in each of the lifting devices. In addition, frequency inverters are used in order to control the frequency of lifting and traversing motors, as well as by arranging one of the lifting devices as master and the others as so-called slave hoists. The precision of the sideway transfer can be achieved in the same manner.
At the cutting station, the plates are cut into their proper length, provided with water holes and, if required, the openings and the cuttings formed in the unhardened product are finished by using water cutting methods or mechanical machine tools. The device for making water holes, preferably automatic, can also operate using high-pressure water jet methods or boring.
The transversal and diagonal cutting is carried out by using an automatic saw with a folding blade, arranged at the beginning of the cutting station. The plates to be longitudinally split can be moved to the track 19 adjacent to the cutting station 20, on which track the split saw equipment is arranged.
The waste material resulting from the finishing treatment can be arranged to fall directly on transfer conveyors which automatically transfers it to a recycling point.
Compared to the arrangement according to the prior art, a considerably large capacity is achieved, because by means of the lifting and stacking technique, a large number of products can be simultaneously held in the hardening stage.
Number | Date | Country | Kind |
---|---|---|---|
20000489 | Mar 2000 | FI | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCTFI01/00208 | 3/2/2001 | WO | 00 | 8/29/2002 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO0164409 | 9/7/2001 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
2234663 | Anderegg | Mar 1941 | A |
3510107 | Fidler | May 1970 | A |
3523343 | Mitchell | Aug 1970 | A |
3947171 | Yasuda et al. | Mar 1976 | A |
3999913 | Branitzky | Dec 1976 | A |
4141946 | Rauenhorst | Feb 1979 | A |
4273740 | Marchesi et al. | Jun 1981 | A |
4337020 | Ito et al. | Jun 1982 | A |
4421710 | Borcoman | Dec 1983 | A |
5184924 | Takalo et al. | Feb 1993 | A |
5976442 | Manning | Nov 1999 | A |
Number | Date | Country |
---|---|---|
2931506 | Feb 1980 | DE |
29 31 506 | Feb 1980 | DE |
61653 | May 1982 | FI |
73383 | Jun 1987 | FI |
80846 | Apr 1990 | FI |
2573697 | May 1986 | FR |
2 573 697 | May 1986 | FR |
2231527 | Nov 1990 | GB |
2 311 747 | Oct 1997 | GB |
2311747 | Oct 1997 | GB |
WO 8504362 | Oct 1985 | WO |
Number | Date | Country | |
---|---|---|---|
20030057597 A1 | Mar 2003 | US |