Not applicable.
The present disclosure generally relates to repair of conduit in the field (in situ) and more particularly to repair of drain tile cut during the laying of utilities, such as, inter alia, large diameter gas pipe.
Large diameter gas pipeline, for example, is laid in ditches, usually over large distances. This also is true of other utilities. It would be uneconomic to circumvent each and every drain tile or drainage pipe encountered. Thus, the gas pipeline contractor during excavation of the ditch cuts the drain tiles encountered in order to save time and money. A crew, then, goes back and repairs each cut drain tile in the field.
Commonly owned U.S. Pat. No 8,939,680 discloses a spray-in-place or pre-formed polymer foam bridge overlaying the pipeline with weight (sandbags) placed on the foam bridge to counter buoyancy, and a support for the repaired drain tile laid atop the sandbag weight. For larger diameter drain tile or where best practices are not required, the support may not be needed.
Disclosed is a structure for repairing drain tile or any other conduit found in the construction of underground utilities, which conduit was severed by the digging of a ditch for the underground utility. A spray-in-place or pre-manufactured foamed polymer bridge is placed transverse to the longitudinal direction of the underground utility conduit and atop the underground utility pipe. The foamed polymer bridge has a cavity at its top and is semi-circular at its bottom for fitting over the underground utility conduit. Weight is placed in the polymeric foam cavity for countering water buoyancy forces on the polymer foam in the ditch after the ditch is back-filled with dirt.
Additionally, such pre-manufactured foam bridges can be used as breakers to support underground utilities, such as large pipe. Final height and/or slope can be achieved by use of polymeric spray foam or shims. Much cost savings and time can be realized by use of pre-manufactured breakers, foam shims, and/or polymeric foam spray.
For a fuller understanding of the nature and advantages of the present media and process, reference should be had to the following detailed description taken in connection with the accompanying drawings, in which:
These drawings will be further described below.
While the instant description relates to a gas pipe ditch wherein a drain tile has been severed while digging the ditch for the gas pipe, such description merely is for illustrating the precepts of the present disclosure, which in its broadest precepts relates to a conduit severed while digging a ditch.
Referring initially to
The structure for bridging the ditch for repair of the severed drain tile ends, 24 and 26 is illustrated in
It should be recognized that use of polymeric foam spray, polymeric shims, or other techniques might be used in place of the sandbags in order to achieve any desired slope.
The new drain tile section, 38, then, is placed across the ditch. Note that drain tile section 38 has a pair of slanted inspection ports, 40 and 42, on either end. A camera can be inserted into either port 40 and 42 for inspection purposes, such as, for example, to ensure that drain tile section 38 was properly installed, and mated with ends 24 and 26.
Referring to
It should be observed that with proper dimensioning, a total of 17 sandbags could fill the inner space of foam pieces 44 and 46. The weight of that number of sandbags counters the upward forces of water in the ditch that tend to cause the foam bridge to rise and press against new drain tile section 38. There must be about 60 pounds of weight capacity in the cavities per cubic foot of foam in order to overcome water buoyancy forces on the foam bridge.
Referring to
Referring to
An additional use of pre-formed foam structures is as a foam breaker and a pier. Cut to standard width and length with variable height (or some other standards), a crew can take a few sizes from the factor and place them in the ditch as breakers (water dams) rather than to create such breakers with polymeric foam spray. Cost and labor savings can be achieve with pre-formed breakers. As described above, small cans of spray polymeric foam and/or polymeric foam shims can be used as is necessary, desirable, and/or convenient to achieve a desired slope, ensure full contact of the pre-formed breaker with the pipeline, or the like.
While the method and structure has been described with reference to various embodiments, those skilled in the art will understand that various changes may be made and equivalents may be substituted for elements thereof without departing from the scope and essence of the disclosure. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the disclosure without departing from the essential scope thereof. Therefore, it is intended that the disclosure not be limited to the particular embodiments disclosed, but that the disclosure will include all embodiments falling within the scope of the appended claims. In this application all units are in the US Engineering system and all amounts and percentages are by weight, unless otherwise expressly indicated. Also, all citations referred herein are expressly incorporated herein by reference.
This application is a continuation-in-part of application Ser. No. 14/285,674, filed on May 23, 2014, which claims benefit of provisional application 61/826,518.
Number | Date | Country | |
---|---|---|---|
Parent | 14285674 | May 2014 | US |
Child | 14701916 | US |