The present invention relates to a technique of manufacturing a metal-plated steel pipe, of which inner and outer faces or any one of them are subjected to molten metal-plating, by a continuous steel pipe manufacturing line.
Hitherto, as one of representative methods of performing molten metal-plating on a steel pipe, there is a known hot-dipping method. Further, in recent years, a method of manufacturing a molten metal-plated steel pipe in a continuous steel pipe manufacturing line has been proposed from the viewpoint of a decrease in the cost. As one of the methods, Japanese Patent Application Publication No. S52-43454 discloses a technique of manufacturing an outer-face plated steel pipe in a manner such that a steel sheet is continuously cold-formed into a tubular shape and the result is welded and is plated with molten metal. Furthermore, there is a growing need to perform an inner-face metal plating in recent years. Therefore, JP-A No. H05-148607 discloses a method of easily plating both inner and outer faces of a steel pipe with molten metal in a continuous line in a manner such that one face in a steel sheet corresponding to the inner face of the steel pipe is subjected to plating in a steel pipe manufacturing line, the result is cold-formed into a tubular shape, a longitudinal end face of the steel sheet is welded, and the outer face of the steel pipe is subjected to molten metal-plating.
Various specifications are required in the steel pipe which is manufactured in the continuous line. That is, the diameter of the steel pipe and characteristics such as corrosion resistance thereof need to be changed depending on the requirements of the consumers. Thus, in the continuous line, a steel pipe according to one specification is manufactured, and thereafter a steel pipe according to another specification is manufactured. However, at this time, there is a need to adjust a molten metal dipping time in the plating. In the case of the general dipping plating, only the molten metal dipping time may be adjusted. However, in the plating of the continuous line, the line speed needs to be changed in order to adjust the dipping time, which affects the manufacturing efficiency and so on.
Thus, the present invention is directed to providing a system and a method capable of easily adjusting the dipping time in the continuous steel pipe manufacturing line.
Further, in the continuous line, the line needs to be stopped or the line speed needs to be decreased when any trouble occurs. When the line is temporarily stopped and restarted in order to perform plating in the continuous line, since the plating is performed after the pretreatment, an unplated portion may be generated in the length necessary for the spent time, which leads to an increase in the cost. Thus, the line speed may be decreased so that the continuous line does not stop. However, when the line speed is decreased in this way, the molten metal dipping time is extended at the time of processing the manufactured plated steel pipe, thereby causing a problem in that the plating is cracked or peeled.
Thus, the present invention is directed to providing a method and a system capable of making the plating dipping time constant so as to correspond to a change in the line speed without stopping the line in the method of manufacturing the steel pipe in the continuous line.
According to the present invention, there is provided a steel pipe manufacturing system that manufactures a steel pipe, of which inner and outer faces or any one face thereof is subjected to molten metal-plating, from a steel sheet in a continuous manufacturing line in which the system includes: an inner-face plating performing part (unit) such as the inner-face molten metal-plating device 5 that performs molten metal-plating by pouring molten metal to the upper side of the steel sheet corresponding to the inner face of the steel pipe; a steel pipe forming part such as the forming device 7 and the welding device 8 for obtaining a continuous steel pipe by continuously cold-forming the steel sheet subjected to the inner-face plating into a tubular shape and seam-welding a longitudinal end face joint portion of the steel sheet formed in the steel pipe; and an outer-face plating performing part such as the outer-face molten metal-plating device 13 that performs molten metal-plating by dipping the outer face of the steel pipe into molten metal, in which a dipping length of molten metal is adjustable in the inner-face plating performing part and/or the outer-face plating performing part.
The present invention further provides the above system in which the inner-face plating performing part such as the inner-face molten metal-plating device 5 includes a pouring part such as the pouring part 501 that pours molten metal to the upper side of the steel sheet, a molten metal supply part such as the molten metal pump 550 that supplies molten metal to the pouring part, and an inner-face wiping part such as the inner-face wiping part 503 that removes molten metal poured by the pouring part, and in which the relative distance between the initial molten metal pouring position and the position of the inner-face wiping part is adjustable.
The present invention further provides the above system of the invention in which the pouring part has a movable means such as the movable part 504 that is movable in parallel to a direction where the steel sheet advances.
The present invention further provides the above system in which the position of the inner-face wiping part is fixed.
The present invention further provides the above system in which the outer-face plating performing part includes a plurality of dipping parts such as the dipping parts 601 which have a space for allowing the continuous steel pipe to pass therethrough, allow the outer face of the continuous steel pipe to be dipped into molten metal when molten metal is introduced into the space, and are continuously arranged in a direction where the continuous steel pipe advances, an outer-face wiping part such as the wiping part 602 that removes surplus metal from the continuous steel pipe dipped into molten metal by the dipping part, and a molten metal supply part such as the molten metal pump 550 that can supply molten metal into the dipping part, in which the molten metal supply part is, on the supply, able to change the number of the dipping part (s) which molten metal is to be supplied.
The present invention further provides the above system in which the outer-face wiping part is installed immediately after each of the plurality of dipping parts, and which can determine that any wiping part(s) of the plurality of wiping parts is to be operated.
The present invention further provides the above system according to the invention in which the outer-face wiping part(s) installed between the dipping parts is(are) a movable open circular type wiping part(s) such as the movable open circular type wiping part 602-1 which includes an annular portion such as the annular portion 60201 surrounding the continuous steel pipe and a plurality of gas ejecting holes such as gas ejecting holes 60202 formed inside the annular portion and in which the annular portion is ring-opened and movable to a position distant from the continuous steel pipe.
According to the present invention, there is provided a method of manufacturing a steel pipe, of which inner and outer faces are subjected to molten metal-plating, from a steel sheet in a continuous manufacturing line, the method including: inner-face metal-plating of performing molten metal-plating by pouring molten metal to the upper side of the steel sheet corresponding to the inner face of the steel pipe; steel pipe forming of obtaining the continuous steel pipe by continuously cold-forming the steel sheet into a tubular shape after the inner-face metal-plating and seam-welding a longitudinal end face joint portion of the steel sheet formed as the steel pipe; outer-face metal-plating of performing molten metal-plating by dipping the continuous steel pipe after the steel pipe forming; and cutting of obtaining the steel pipe by cutting the continuous steel pipe into a predetermined length after the outer-face metal-plating, in which a dipping length of molten metal is adjusted in the inner-face plating and/or the outer-face plating.
According to the present invention, there is provided a method of manufacturing a steel pipe, of which an inner face is subjected to molten metal-plating, from a steel sheet in a continuous manufacturing line, the method including: inner-face metal-plating of performing molten metal-plating by pouring molten metal to the upper side of the steel sheet corresponding to the inner face of the steel pipe; steel pipe forming of obtaining the continuous steel pipe by continuously cold-forming the steel sheet into a tubular shape after the inner-face metal-plating and seam-welding a longitudinal end face joint portion of the steel sheet formed as the steel pipe; and cutting of obtaining the steel pipe by cutting the continuous steel pipe into a predetermined length after the steel pipe forming, in which a dipping length of molten metal is adjusted in the inner-face metal-plating.
According to the present invention, there is provided a method of manufacturing a steel pipe, of which an outer face is subjected to molten metal-plating, from a steel sheet in a continuous manufacturing line, the method including: steel pipe forming of obtaining the continuous steel pipe by continuously cold-forming the steel sheet into a tubular shape and seam-welding a longitudinal end face joint portion of the steel sheet formed as the steel pipe; outer-face metal-plating of performing molten metal-plating by dipping the continuous steel pipe after the steel pipe forming; and cutting of obtaining the steel pipe by cutting the continuous steel pipe into a predetermined length after the outer-face metal-plating, in which a dipping length of molten metal is adjusted in the outer-face metal-plating.
The present invention provides the above method according to the invention in which the inner-face metal-plating includes pouring of pouring molten metal to the upper side of the steel sheet, and inner-face wiping of removing extra metal after the pouring, and in which the distance between the pouring position and the inner-face wiping position is adjusted.
The present invention provides a method according to the invention above in which the outer-face metal-plating includes continuously installing a plurality of dipping troughs in a direction where the continuous steel pipe advances, the dipping trough having a space allowing the continuous steel pipe to pass therethrough and being able to dip the outer face of the continuous steel pipe into molten metal when molten metal is introduced into the space, supplying molten metal into the dipping trough(s), and dipping the outer face of the continuous steel pipe into molten metal, and outer-face wiping of removing extra metal from the continuous steel pipe dipped in molten metal by the dipping trough(s), and in which the number of the dipping trough(s), which molten metal is to be supplied, is determined, and the outer-face wiping is performed immediately after the trough positioned at the most rear stage among the dipping troughs to which molten metal is supplied.
The present invention provides a method according to the invention above, in which in the inner-face wiping, the molten plating attachment amount is adjusted by the air or inert gas wiping pressure using a blowing-off device.
The present invention provides a method according to the invention above in which the inner-face metal-plating further includes different metal plating of performing metal plating by pouring different molten metal after the pouring.
The present invention provides the method according to the invention above in which the outer-face metal-plating is different metal plating by supplying molten metal, to at least one of the dipping troughs, different from molten metal introduced into the other trough(s).
Herein, the meaning of various technical terms used in the specification will be described. The “dipping length (DLin or DLout) of molten metal” means the distance in which the steel sheet or the steel pipe is dipped into the molten metal and the extra molten metal is removed by the wiping. For example, in the case of the inner-face metal-plating, it means a distance from an initial treatment position (IPin) to the inner-face wiping position (WPin). In the case of the outer-face metal-plating, it means a distance from another initial treatment position (ITout) to the outer-face wiping position (WPout).
More specifically, in the case of the inner-face metal-plating, defining an area through which the steel sheet is treated by the molten metal as a treatment area (TAin), the initial treatment position is located most upstream in the area and, at the position, the poured molten metal comes to contact with the steel sheet. The position is denoted with IPin in
Also, in the case of the outer-face metal-plating, defining an area through which the steel pipe is treated by the molten metal as another treatment area (TAout), the initial treatment position is located most upstream in the area and, at the position, the steel pipe first enters a pool filled with molten metal. The position is denoted with IPout in
According to one or more aspects of the inventions as described above, in the continuous line for manufacturing the steel pipe, there is an effect that the dipping time according to the required specification may be easily obtained. Furthermore, there is an effect that the plating dipping time may be made constant so as to correspond to a change in the line speed without stopping the line even when any trouble occurs.
According to one or more aspects of the inventions as described above, there is an effect that the plating dipping time may be easily adjusted by adjusting the relative positional relation between the molten metal pouring position and the inner-face wiping part.
According to an aspect of the invention as described above, since the position of the wiping part is fixed, there is an effect that the dipping time may be changed without changing the distance between the wiping position and the subsequent process position.
According to one or more aspects of the inventions as described above, there is an effect that the dipping time may be easily adjusted by changing the number of the supplied dipping part(s).
According to an aspect of the invention as described above, since the distance from the dipping position to the wiping position may be made constant even when the number of the dipping part (s) to which molten metal is supplied is changed, there is an effect that the time from the dipping to the wiping may be made constant.
According to an aspect of the invention as described above, since the wiping part may be moved to a position distant from the exit and the entrance of the dipping part when the wiping part is not operated, there is an effect that the gas ejecting hole may not be blocked by molten metal, such as zinc, flowing out of the exit and the entrance thereof.
According to an aspect of the invention as described above, there is an effect that the plating thickness may be easily adjusted by adjusting the pressure of the blowing-off device.
According to one or more aspects of the inventions as described above, since the inner face or the outer face may be simultaneously plated with different metals, there is an effect that the process may be simplified.
a and 2b are schematic configuration diagrams illustrating an inner-face molten metal-plating device according to the invention.
a and 3b are schematic configuration diagrams illustrating a pouring part of the inner-face molten metal-plating device according to the invention.
a and 5b are schematic configuration diagrams illustrating an outer-face molten metal-plating device according to the invention.
Hereinafter, an embodiment of the invention will be described in detail.
If necessary, a shot blasting device 3, a pretreatment device 4 which performs an oxidization preventing flux liquid applying operation and a drying and preheating operation, a flux applying device 11 which continuously applies a flux liquid for cleaning the outer face of the tubular body and preventing the oxidization thereof, or a preheating device 12 which dries the outer face of the tubular body and preheats the tubular body may be provided. Herein, a length from the pretreatment device 4 to the initial treatment position (IPin) of the inner-face plating performance part is defined as a first length (PLin). More specifically, the length (PLin) is determined from a preheating end position (PPin) of the pretreatment device at which the preheating operation terminates or the steel sheet comes out of the pretreatment device 4. Another length from the preheating device 12 to the initial treatment position (IPout) of the outer-face plating performance part is defined as a second length (PLout). More specifically, the length (PLout) is determined from a preheating end position (PPout) of the preheating device at which the preheating operation terminates or the steel pipe comes out of the preheating device 12. Depending on the property of plating metal, a first cooling trough in an exemplary form of a tank 6 which cools the steel sheet after the molten metal-plating is performed thereon or a second cooling trough 14 which cools the tubular body after the molten metal-plating is performed thereon is provided. The cooling trough is essentially provided if the metal-plating is galvanizing.
Next, the configuration of the inner-face molten metal-plating device 5 which is the characteristic point of the invention will be described.
Next, the configuration of the outer-face molten metal-plating device 13 which is the characteristic point of the invention will be described. Here, the outer-face molten metal-plating device 13 includes plural, for example, four parts illustrated in
Next, the manufacturing method of the invention using the above-described manufacturing line will be described. First, the steel sheet which is wound in a coil shape is continuously supplied from the uncoiler 2 toward the downstream side of the line. Next, a predetermined pretreatment is performed on the steel sheet by the shot blasting device 3 or the pretreatment device 4, and then an inner-face plating treatment is performed on one face of the supplied the steel sheet by the inner-face molten metal-plating device 5. The inner-face plating treatment will be described later in detail. Next, after the steel sheet of which one face was plated is cooled by the cooling trough 6, the steel sheet is introduced into the forming device 7 and is formed in a tubular shape by cold-forming. Then, the longitudinal end face joint portion of the steel sheet is continuously welded by the welding device 8, so that a continuous single tubular body 9 is formed.
Next, the tubular body 9 is supplied to the cutting device 10 equipped with a blade having a shape according to the outer face of the tubular body 9. Then, the welded bead portion which is formed on the outer face of the tubular body 9 is cut away by the blade of the cutting device 10, so that the outer face of the tubular body 9 becomes smooth.
Subsequently, the tubular body is sent to the flux applying device 11, so that the flux liquid for cleaning the outer face of the tubular body and preventing the oxidization thereof is applied thereon. The tubular body 9 is sent to the preheating device 12 so that residual heat is applied thereto, thereby drying the outer face.
Subsequently, the tubular body is sent to the outer-face molten metal-plating device 13. The tubular body 9 is dipped into the dipping part filled with pumped molten metal in the outer-face molten metal-plating device 13, so that the entire outer face is subjected to the molten metal-plating. The tubular body 9 which was dipped into the dipping part is provided with a molten metal-plated layer having a strong alloy layer, and the surplus molten metal-plating is removed in the wiping device 602, so that the molten metal-plated steel pipe is formed. Subsequently, it is cooled by the cooling trough 14. Furthermore, the outer-face molten metal-plating treatment will be described later in detail.
Then, the molten metal-plated steel pipe is subjected to cold rolling in the sizing device 15 so that the outer diameter is formed into a standard dimension. In the embodiment, the cold rolling is also needed so that the molten metal-plated layer has a comparatively uniform thickness in the circumferential direction. That is, even when the molten metal-plated layer immediately after formed by the outer-face molten metal-plating device has an irregular thickness in the circumferential direction, the molten metal-plated layer may be made to have a comparatively uniform thickness through the subsequent cold rolling or the like. In this way, in the embodiment, after the molten metal-plated layer is formed by the outer-face molten metal-plating device, for example, it is desirable to perform a sizing process such as cold rolling and perform a process which allows the molten metal-plated layer formed by the molten metal-plating treatment to have a comparatively uniform thickness such as a process which equalizes the distribution of the thickness compared to the case immediately after the molten metal layer is formed.
The molten metal-plated steel pipe is cut into a predetermined length by the cutting device 16, so that a steel pipe product 17 is obtained.
Here, the inner-face plating treatment will be described in detail. The inner-face plating treatment is a process in which surplus metal of the molten metal poured from the pouring part 501 of the inner-face molten metal-plating treatment device 5 to the steel sheet B is removed by the wiping part 503. Here, in the invention, a fact is examined in which the molten metal dipping time is proportional to the thickness of the formed alloy layer at the time of performing the molten metal-plating. However, the inner-face plating method which is used in the continuous line is performed according to the method in which molten metal is poured to the steel sheet from the upper side thereof. Here, although “dipping” as the general meaning is not performed, under a premise that the conditions, where the molten-metal is on the steel sheet by pouring, is “dipping”, the distance between the pouring part and the wiping part is adjusted as the dipping length of the molten metal. That is, even when the line speed is not changed, the thickness of the plated alloy layer may be adjusted by adjusting the molten metal dipping time in a manner such that the distance between the pouring part 501 and the wiping part 503 is changed. For example, when the line speed is temporarily decreased, the thickness of the plated alloy layer may be maintained so as to be uniform by adjusting the distance between the pouring part 501 and the wiping part 503 to be short. That is, since the thickness of the plated alloy layer may be made to be substantially uniform, a problem such as cracking or peeling of the plated layer hardly occurs.
Further, in the method according to the embodiment, the thickness of the plated layer may be easily adjusted by only adjusting the pressure of air or N2 gas ejected from the wiping part 503. Incidentally, generally, with regard to the manufacturing of the plated steel sheet, the steel sheet is perpendicularly and rapidly raised from the molten metal pot in the case of so-called hot-dipping. At this time, the attachment amount of the molten metal which is raised together with the steel sheet by the viscosity is adjusted by the air or N2 gas wiping. Generally, in this type of process, there is a need to increase the amount of raised molten metal by increasing a speed at which the steel sheet is raised, that is, a speed at which the sheet passes in order to increase the plating attachment amount. However, since the heating capability for plating the steel sheet is determined according to the condition of the facility, the sheet passage speed decreases in the case of the thick-walled steel sheet. Accordingly, the raised molten metal amount decreases, and the plating attachment amount may not be easily increased. In the inner-face metal-plating of the method according to the embodiment, the attachment amount may be controlled by the air or N2 gas wiping pressure regardless or the amount of the raised molten metal and the thickness of the steel sheet in a manner such that the steel sheet passes in the horizontal direction instead of the perpendicular direction.
Next, the outer-face plating treatment will be described in detail. Even in the outer-face plating treatment, the dipping length of the molten metal is important. The thickness of the outer-face plated alloy layer may be adjusted in a manner such that molten metal is charged into the dipping part(s) by the number of the dipping part(s) necessitated to obtain the required thickness of the plated alloy layer among the plural outer-face molten metal-plating devices. Further, due to adjusting the thickness of the plated alloy layer in this way, even when the line speed changes, the thickness of the plated alloy layer of the outer face may be maintained to be uniform.
Furthermore, from the viewpoint of bending workability, the thickness of the alloy layer is desirably 4 μm or less, is more desirably 3 μm or less, and is further more desirably 2 μm or less. When the thickness of the alloy layer is set to be within this range, cracking or peeling of the plating hardly occurs due to the bending. Here, in order to adjust the thickness of the alloy layer, the plating dipping time is desirably 1 second or less, is more desirably 0.3 seconds or less, and is further more desirably 0.25 seconds or less.
Here, the invention is not limited to the above-described embodiment. For example, in the embodiment, although the molten metal-plated layer is formed on both inner and outer faces using the melting device, the molten metal-plated layer may be formed on only the inner face or the outer face using the molten metal-plating device.
Further, the upper face of the outer-face plated layer may be coated with a protection coating using a synthetic resin. In this way, the rust preventing effect of the molten metal-plated steel pipe may be further improved.
Furthermore, in the embodiment, the plating performed on the steel pipe is not particularly limited, and for example, zinc may be exemplified. However, if necessary, other metal may be applied. Further, the embodiment has been described on the assumption that the steel sheet is used, but the invention may be applied on the assumption that other metal sheets are used. As such a metal sheet, for example, a copper tape, an aluminum tape, or the like is supposed, but the invention is not limited thereto.
The rolled steel plate with a thickness of 1.2 mm and a width of 59.5 mm was set on a manufacturing line with the same configuration as that of
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/JP2009/065062 | 8/28/2009 | WO | 00 | 5/14/2012 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2011/024290 | 3/3/2011 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
2597811 | Nolan | Mar 1952 | A |
3597261 | Coburn et al. | Aug 1971 | A |
3956537 | Raymond | May 1976 | A |
5251804 | Nakamura | Oct 1993 | A |
5506002 | Maitra et al. | Apr 1996 | A |
5512321 | Paramonov et al. | Apr 1996 | A |
6242048 | Iida et al. | Jun 2001 | B1 |
Number | Date | Country |
---|---|---|
1290768 | Apr 2001 | CN |
52-043454 | Mar 1977 | JP |
56-116864 | Sep 1981 | JP |
1-149948 | Jun 1989 | JP |
5-148607 | Jun 1993 | JP |
5-287480 | Nov 1993 | JP |
7-243015 | Sep 1995 | JP |
9-241814 | Sep 1997 | JP |
2000-087203 | Mar 2000 | JP |
2000-219946 | Aug 2000 | JP |
2000-219947 | Aug 2000 | JP |
2004-083950 | Mar 2004 | JP |
WO 2007073060 | Jun 2007 | WO |
Number | Date | Country | |
---|---|---|---|
20120315398 A1 | Dec 2012 | US |