This patent application claims priority to Chinese Patent Application Serial Number 202010851619.9, filed on Aug. 21, 2020; the content of which is hereby incorporated by reference herein in its entirety into this disclosure.
The present disclosure relates to the field of high power converter systems, and is mainly applied to calculation of a maximum short-time high current of multiple thyristor converters connected in parallel so as to meet shock requirements for type tests on equipment such as high power switches.
With the upgrading of the electric power industry, an increasing number of large-scale power equipments have been put into use. In order to verify the operational reliability of power equipment under severe working conditions, short-time pulse shock tests of tens of kA to hundreds of kA are required. Such a short-time pulse shock test can be supported by existing thyristor converters capable of providing an instantaneous high current while satisfying a rated output, without constructing an instantaneous current shock platform. There is a need to provide a method for measuring an output current of multiple thyristor converters connected in parallel to reduce the system simulation and design time of a converter and provide reliable and rapid guidance for actual shock tests.
An objective of the present disclosure is to calculate a maximum output current of multiple converters connected in parallel based on the short-time multi-fold overload withstanding characteristic of a high power thyristor converter, to meet the need of a high current shock test on large-scale power equipment. Short-time transient high current pulses are provided while steady-state output of a rated current is satisfied. A high current that multiple converters connected in parallel can withstand is calculated by using an equivalent impedance model for a converter system and a thyristor junction temperature model.
The technical solution of the present disclosure is as follows: a method for calculating a maximum output current of multiple thyristor converters connected in parallel includes the following steps:
step 1: setting an operating time t and determining a time for outputting a long pulse current according to an actual demand;
step 2: assuming a trigger angle for subsequent output current calculation;
step 3: calculating a maximum output current of a single converter according to an output current model for the single converter;
step 4: equally dividing a total output DC current into a plurality of parts according to a working duration of six converter bridge arms, thereby obtaining a pulse operating current of a single bridge arm;
step 5: checking whether a present junction temperature of a thyristor is below a limiting temperature using a current waveform obtained in step 4 based on a thermal resistance model for the thyristor, if no, correcting the trigger angle, and repeating step 2 to step 5 until the condition is met;
step 6: giving a present trigger angle to provide guidance for actual experimental operations;
and step 7: giving a maximum output current of multiple converters connected in parallel based on the maximum output current of the single converter in combination with a current-sharing coefficient for converters.
Further, the method includes establishing an equivalent impedance model by using a multiple parallel-connected converter system to obtain a calculation formula for the maximum output current of multiple converters connected in parallel. The model may be established as follows:
the converter system is divided into an alternating current (AC) side and a direct current (DC) side; on the AC side, the grid side is connected to step-down transformers through high voltage buses, and the step-down transformers are connected to rectifier transformers that are connected to input ends of converters through AC buses; and on the DC side, output ends of the converters are connected to DC reactors for balancing current through DC buses and finally connected to a load. The number of step-down transformers may be assumed as M, with each step-down transformer being connected with N converter branches and each branch including the rectifier transformer, the AC bus, the converter, the DC reactor, the DC bus and the load. Since a plurality of branches are connected in parallel, currents of all branches may be input together to the load by a DC busbar.
Further, the method includes implementing a system impedance connection based on a relationship between an output voltage and an input voltage of a thyristor converter.
Further, the method includes enabling AC side parameters to be equivalent to those of a secondary side of the rectifier transformer based on parameters of the converter system.
Further, the method includes checking a maximum withstand current of a single converter by using the thermal resistance model for the thyristor, and multiplying the maximum withstand current by the number of the converters connected in parallel and the current-sharing coefficient to obtain an actual maximum output current of the multiple converters connected in parallel.
Further, the method includes performing iteration to determine a trigger angle at the maximum withstand current of the single converter.
Further, the limiting temperature may be 125° C.
Beneficial Effects:
Compared with the prior art, the present disclosure has the following advantages: for maximum output currents, high pulse currents are mostly realized by means of capacitor or flywheel discharge at present. A high power thyristor converter is capable of realizing steady-state output of a current of tens of kA. Besides, a thyristor converter is capable of withstanding several times of a rated operating current in a short time. A plurality of converters can be connected in parallel to realize short-time high current output to meet the needs of most of situations in the power industry. The present disclosure provides a method for calculating a maximum output current of a plurality of converters, which can meet the requirements of improving the application functions of the converters and reducing the manufacturing cost of a pulse forming platform.
The technical solutions in embodiments of the present disclosure will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present disclosure. Apparently, the described embodiments are merely a part rather than all of the embodiments of the present disclosure. All other embodiments derived from the embodiments of the present disclosure by a person of ordinary skill in the art without creative efforts shall fall within the protection scope of the present disclosure.
According to one embodiment of the present disclosure, a method for calculating a maximum output current of multiple thyristor converters connected in parallel is provided. An equivalent impedance model may be built based on parameters of a power grid, a high voltage AC bus, a step-down transformer, a rectifier transformer, a rectifier, a reactor and a DC bus that are included in a multiple parallel-connected converter system, and a theoretical calculated value of a maximum output current of a single converter can be obtained from a relationship between a DC side output current and an AC side output voltage of a thyristor converter. With a thermal resistance model for a thyristor, an actual withstand current of a single converter is checked and a thyristor trigger angle is obtained in limited operating time. An actual withstand current of multiple thyristor converters connected in parallel is given with the consideration of a current-sharing coefficient for multiple converters connected in parallel. The specific calculation process, as shown in
step 1: set an operating time t and determine a time for outputting a long pulse current according to an actual demand;
step 2: assume a trigger angle for subsequent output current calculation;
step 3: calculate a maximum output current of a single converter according to an output current model for the single converter;
step 4: equally divide a total output DC current into six parts according to a working duration of six converter bridge arms, thereby obtaining a pulse operating current of a single bridge arm;
step 5: check whether a present junction temperature of a thyristor is below 125° C. using a current waveform obtained in step 4 based on a thermal resistance model for the thyristor, if no, correct the trigger angle, and repeat step 2 to step 5 until the condition is met;
step 6: give a present trigger angle to provide guidance for actual experimental operations; and
step 7: give a maximum output current of multiple converters connected in parallel based on the maximum output current of the single converter in combination with the current-sharing coefficient (typically 0.8-0.9) for converters.
The overall calculation can be achieved using MATLAB programming according to the flowchart of
Step 1: Setting of time t
The operating time t of a converter is determined according to the need of an experiment. In MATLAB, the time is set to 0 and a time interval is set to t.
Step 2: Setting of a trigger angle
The trigger angle is selected from a minimum angle according to an operating range of the converter. The trigger angle is typically 20° to 90°.
Step 3: Calculation of the maximum output current of the converter
Generally, a plurality of step-down transformers may be connected to a power grid, and one step-down transformer may be connected with a plurality of rectifier transformers, with each rectifier transformer being matched with one converter and a subsequent output device. After that, series-parallel connection control is carried out on the DC side to output required current and voltage parameters. For the convenience of calculation, the resistance of the AC side, which is very little, is ignored. The equivalent impedance of the converter system may be calculated from the grid side. Specific impedance distribution is as shown in
The converter system is divided into the AC side and the DC side. On the AC side, the grid side is connected to step-down transformers through high voltage buses, and the step-down transformers are connected to rectifier transformers that are connected to input ends of converters through AC buses. On the DC side, output ends of the converters are connected to DC reactors for balancing current through DC buses and finally connected to a load. In
Physical meanings of specific symbols in
Specific parameters can be substituted into the equivalent impedance model for the converter system to obtain an impedance and current distribution diagram as shown in
In
According to theories of power electronics, an equivalent converter model is as shown in
In the figure, RL represents equivalent internal resistance of the converter system, which is equivalent resistance on the secondary side of the rectifier transformer converted from the AC side reactance of the converter system. RL can be simplistically expressed as formula (1) by AC side impedance superposition, with specific parameters given below.
where M is the number of the step-down transformers in a power system, and N is the number of the converters in a branch.
The circuit as shown in
where U1 is a DC side voltage; id is an output current; the converter has a DC side output voltage U1 and an AC side input voltage U2 (U2 is a secondary side voltage of the rectifier transformer, i.e., an input voltage to the converter); and Ud is a DC side load voltage. U1 and U2 have a relationship as shown below:
U1=1.35U2 cos α1 (3)
where α1 is a trigger angle of the rectifier.
Therefore, the output current can be obtained as below:
where
Formula (5) presents merely a relationship between the maximum output current of the converter system and the equivalent impedance of each device. RL includes converted equivalent reactance values of the AC side power grid, the high voltage buses (cables), the step-down transformers, the AC buses and the rectifier transformers, and the specific conversion process is as follows:
The reduction of the reactance of the power grid system to the secondary side of the rectifier transformer (the voltage is expressed as U2Nz) gives:
where UN represents the voltage of the power grid, and S represents the capacity of the power grid.
The reduction of the leakage reactance of the step-down transformer to the secondary side of the rectifier transformer gives:
where ST1 represents short-circuit impedance of the step-down transformer (generally expressed in percentage); and SNj represents the capacity of the step-down transformer.
The reduction of the reactance of the high voltage cable to the secondary side of the rectifier transformer gives:
where XL1 represents an actual value of the reactance of the high voltage cable; and UNz represents the voltage of the high voltage bus.
The leakage reactance of the rectifier transformer is as follows:
where ST2 represents short-circuit impedance of the rectifier transformer (generally expressed in percentage); and SNZ represents the capacity of the step-down transformer.
The impedance of the AC busbar between the rectifier transformer and the rectifier is as follows:
XL2=2πfL2 (10)
where L2 is the inductance value of the bus; and f is the operating frequency of the converter, which is generally 50 Hz.
The specific parameters of the DC reactor are given by the designer or the manufacturer.
A water-cooled metal bus is used on the DC side of the converter. According to design requirements, the current-carrying section and length of each part of DC bus of the rectifier can be obtained. The formula of the resistivity of the electrically conductive metal bus at different temperatures is as follows:
ρm(10° C.)=ρm(10° C.)(1+ΔTαm) (11)
In the formula, ρm(10° C.) is the resistivity of the metal bus at 10° C.; ΔT is a difference between an actual temperature and 10° C.; and αm is a temperature coefficient of resistivity.
The resistance of the metal busbar is as follows:
Rbusbar=ρm(T° C.)l/S (12)
where l is the length of the busbar; and S is the sectional area of the busbar. Thus, Rb and Rb1 can be calculated.
The DC side bus in the converter can be equivalent to:
In the formula, the subscripts b and b1 represent corresponding parameters of the DC bus of a single converter and the overall busbar.
The resistance and inductance parameters of the load can be given by the manufacturer, which may not be considered in the calculation of the maximum output capacity of the converters.
The formulas (6) to (12) are substituted into the formula (1) to obtain the equivalent internal resistance of the converters:
A maximum output current under limited conditions can be obtained based on formula (15), and an operating current of a single bridge arm can be separated using this formula for subsequent thyristor junction temperature correction.
Step 4: Separation of current of bridge arm
The parameters of the converter system are substituted into the calculation formula (15) to obtain the maximum DC output current of the single converter, and the current of a bridge arm is separated in MATLAB according to ⅓ operating time of the bridge arm in one cycle (20 ms) in combination with the six-pulse characteristic of the converter. Let the current during non-operating time be 0, an operating current waveform for a single bridge arm is obtained.
Step 5: Check of thyristor junction temperature
A junction temperature in a fault state is calculated based on the calculated maximum output current of the bridge arm using a transient thermal resistance model for a thyristor as shown in
The following formula can be derived from the fourth-order equivalent circuit shown in
ZthJC(t)=Rth1(1−e−t/τ
In an RC parallel circuit, a time constant τ=RC.
in case of breakover overcurrent of the thyristor in a short time, transient power loss Pth may be expressed as:
Pth=VTiT=[A+B·iT+C·ln(iT+1)+D·√{square root over (iT)}]·iT (17)
where iT is a transient current flowing through the thyristor; A, B, C and D are special parameters and can be obtained from the thyristor data book.
Step 6: Determination of trigger angle
A converter circuit model is built using the thermal resistance model for the thyristor, where Pth is input as a controllable current source; and the junction temperature of the thyristor under transient pulses can be obtained by measuring an overall circuit voltage. A maximum output current in accordance with the time and the junction temperature can be obtained by scanning of parameters according to a trigger junction temperature limiting condition. A trigger angle satisfying the condition is given to provide reference for actual experimental operations.
Step 7: Determination of multiple parallel maximum output current
Based on the maximum output current of the single converter in combination with the current-sharing coefficient (kf) for multiple converters connected in parallel, a final maximum output current is obtained as follows:
ITotal=id×M×N×kf (18)
The present disclosure is described above in detail by means of specific embodiments and examples. However, the present disclosure is not limited thereto. A person skilled in the art can change and use different parameters of the thyristor and the converter system without departing from the principles of the present disclosure, or according to actual situations.
Number | Date | Country | Kind |
---|---|---|---|
202010851619.9 | Aug 2020 | CN | national |
Number | Name | Date | Kind |
---|---|---|---|
10141854 | Butler | Nov 2018 | B1 |
20140214343 | Bengtsson | Jul 2014 | A1 |
20170027025 | Kanai | Jan 2017 | A1 |
20190319523 | Jin | Oct 2019 | A1 |
20200044576 | Besselmann | Feb 2020 | A1 |
Number | Date | Country | |
---|---|---|---|
20220060106 A1 | Feb 2022 | US |