The invention relates to the construction of parking structures.
A method for producing parking structures is taught in U.S. Ser. No. 12/870,240.
Forming an aspect of the invention is an improved method for constructing parking structures.
Each structure has a site and is of the type including a plurality of parking decks, each deck being defined by a plurality of steel beams supporting a plurality of cementitious panels.
In the method, each panel is manufactured by pouring concrete into a form remote from the site.
The improvement comprises: transporting a plurality of forms to premises proximal to the site; and constructing the panels.
According to another aspect, the concrete can be: mixed remote from the premises and shipped to the premises in a ready-mix truck; or shipped to the premises in a mixer truck.
According to another aspect, the concrete can be delivered to a crane-supported bucket at the premises and delivered thereby to the form.
According to another aspect, the concrete poured into a form can be hardened to form a green panel and the green panel can be transformed by subsequent curing into a panel.
According to another aspect, curing of green panels can be carried out externally of the forms.
According to another aspect, removal of a green panel from a form can involve tilting the form and the green panel 90° by a tilt table.
According to another aspect, the panels can be cured at the premises in a comb.
According to another aspect, the green panel, once tilted by the tilt table, can be moved by a crane to the comb.
According to another aspect, the comb can be transported to the premises.
According to another aspect, the tilt table can be transported to the premises.
According to another aspect, parking structures can be completed in seriatim and, once the panels of a structure in the series have been completed, the forms and tilt table are transported to the next structure in the series to be completed.
According to another aspect, the granular material used for the concrete can be stored in a silo, the silo being enrobed in an electrical blanket, to provide for flowability of the granular material in cold conditions.
According to another aspect, the water used for the concrete mixture can be heated in cold conditions.
Advantages, features and characteristics of the present invention will become apparent upon a review of the following detailed description with reference to the accompanying drawings, the latter being briefly described hereinafter.
In the Appended Drawings:
In the example embodiment, the parking structures and the method for construction are of the type described in U.S. Ser. No. 12/870,240, incorporated herein by reference. By way of background, the prior art involves structures, a facility and a method.
The structures are each of the type having: a site; one or more parking decks, each deck being defined by a plurality of horizontal cementitious panels; for and supporting each of said one or more parking decks, a plurality of horizontal steel beams; and columns supporting the beams.
The facility has: a plurality of molds [
The method involves: producing the panels at the facility; installing the columns at the site; fixing cambered beams to the columns and jacking the ends of the beams; moving the panels to the site and placing them upon the cambered beams; grouting the interstices between the panels; and removing the jacks to allow gravity to remove the camber from the beams and the place the grout and the upper surfaces of the panels into compression.
Persons of ordinary skill will readily appreciate that the teachings of U.S. Ser. No. 12/870,240 represented a significant advantage over typical cast in place parking garages. By using principles of modular construction for the garage, and assembly line type manufacture for the modules, garages of relatively low cost and relatively high quality can be constructed within a relatively large area surrounding the manufacturing facility for the panels, basically, that area to which massive cementitious elements can be transported without undue cost. [The beams and columns will typically also be constructed at the facility, but, being substantially lighter, are relatively easily transported; where suitable heavy steel fabrication facilities existed near the construction site, that option would of course be employed.]
The improved method differs from the prior art method in several ways.
Tilt table [
Comb is adapted to support a panel in a vertical position [
Panel production involves: pouring concrete into a mold table; allow the concrete to harden to form a green panel; tilting the table and the green panel 90° with the tilt table; moving the green panel to the comb with a crane; curing the green panel in the comb to form a panel. When the panel is ready for installation, an extender is added to the tilt table; the panel is lifted by the crane from the comb, placed upon the upright table/extender and pivoted, along with the tilt table, to a horizontal position, to permit subsequent movement in the horizontal position by the crane or another steel carrier to a flatbed for shipment to the site.
In the improved method, the concrete is: mixed remote from the premises and shipped to the premises in a ready-mix truck; or shipped to the premises in a mixer truck; and delivered to a crane-supported bucket [
In the present method, the molds, tilt table, extender, thumper table, comb are transported [
Number | Date | Country | |
---|---|---|---|
63325306 | Mar 2022 | US |