Claims
- 1. A method for preparation of a cable, the method comprising the steps of:providing a first cable preparation device (1) and at least one second cable preparation device (2); operating the first cable preparation device (1) according to a first program control (3), and operating the at least one second cable preparation device (2) according to a separate, second program control (4) spatially separated from the first program control; connecting the at least one second cable preparation device (2) to the first cable preparation device (1) via a data transfer unit (5); transferring data from the first program control to the second program control via the data transfer unit; receiving all the transferred data in the second program control and selecting only a desired portion of the transferred data as control data for the second program control for controlling the second cable preparation device (2) during operation; and feeding at least a part of the control data for the second program control (4) back via the data transfer unit (5) to the first program control (3).
- 2. The method according to claim 1, further comprising the steps of selecting a third cable preparation device from the group of:a) a coiling device (2a) having a coiling pan or coiling plate (8a), b) a wire stacker (cable stacker), c) a prefeeder (cable unwinding unit), d) a cable marking device, e) a device for cable end preparation, comprising the operations of twisting, fluxing, tin-plating, soldering, welding, crimping, pressing-on of contacts or sleeves, mounting of seals, plug housings on the cable end, f) a device for cable layer preparation comprising mechanical or thermal tools, g) a cable transport device, h) a binding device, and effecting at least one of a preliminary, parallel and subsequent cable processing step based on the selected third device for cable processing.
- 3. The method according to claim 2, further comprising the steps of:selecting the coiling device as the third device for cable processing; gripping the cable in the coiling device (2a) with a clamping device (9) connected to the coiling device and clamping the cable; effecting acceleration and rotary movement of the cable with the coiling device (2a) in one of a feed direction (23) and an opposite direction to the feed direction during processing of the cable according to the second program control; producing one of a programmed tensile load on the cable within a defined tension range throughout the entire processing of the cable without any direct measurement of a cable tensile load, and a geometrically defined, tension-free laying of at least one cable end and cable windings of the coil during processing according to the second program control.
- 4. The method according to claim 2 further comprising the steps of:maintaining the rear end of a coiled cable in a cable feed arm (10) upon completion of cable processing; and rotating the coiling plate into a desired position wherein the ends of the cable comes to rest in a specific, preprogrammable position.
- 5. The method according to claim 4 further comprising the steps of:arranging a position detection sensor (7) on the coiling plate (8); controlling a coiling plate drive so that a rotary position of the coiling plate (8) can be fixed for cable feed, laying at least one of the cable ends of the coil in a defined position for removal or binding of the cable by one of a cable guide arm (19) and a rotary positioning of the coiling plate (8) according to the second program control (4a).
- 6. The method according to claim 5 further comprising the step of controlling the coiling plate drive according to at least one of tables and computational instructions with data for startup ramp controls.
- 7. The method according to claim 5 further comprising the steps of providing a braking mode to the coiling plate drive and equipping said coiling plate drive with a power consumption sensor which, during operation, monitors the power consumption of the coiling plate drive and feeds back the values for control purposes to the second program control.
- 8. The method according to claim 5 further comprising the step of positioning the third device for cable preparation is positioned one of upstream, downstream and parallel of the first device for cable preparation.
Priority Claims (1)
Number |
Date |
Country |
Kind |
654/99 |
Apr 1999 |
CH |
|
CROSS REFERENCE TO RELATED DOCUMENT
The present application is a 371 application of PCT/IB00/00214 filed Feb. 28th 2000, which claims the benefit of Switzerland Patent Application No. 654/99, filed Apr. 8th 1999.
PCT Information
Filing Document |
Filing Date |
Country |
Kind |
PCT/IB00/00214 |
|
WO |
00 |
Publishing Document |
Publishing Date |
Country |
Kind |
WO00/62381 |
10/19/2000 |
WO |
A |
US Referenced Citations (17)
Foreign Referenced Citations (5)
Number |
Date |
Country |
0 086 452 |
Aug 1983 |
EP |
0 330 840 |
Sep 1989 |
EP |
0 396 068 |
Nov 1990 |
EP |
0 474 152 |
Aug 1991 |
EP |
0 584 493 |
Mar 1994 |
EP |