This invention relates to the method of controlling pressure in blowout preventer rams seals, especially as it applies to a 20,000 p.s.i. blowout preventer stack.
Not applicable.
Not applicable
Not applicable
Deepwater offshore drilling requires that a vessel at the surface be connected through a drilling riser and a large blowout preventer stack to the seafloor wellhead. The seafloor wellhead is the structural anchor piece into the seabed and the basic support for the casing strings which are placed in the well bore as long tubular pressure vessels. During the process of drilling the well, the blowout preventer stack on the top of the subsea wellhead provides the second level of pressure control for the well. The first level being provided by the weighted drilling mud within the bore.
During the drilling process, weighted drilling mud circulates down a string of drill pipe to the drilling bit at the bottom of the hole and back up the annular area between the outside diameter of the drill pipe and the inside diameter of the drilled hole or the casing, depending on the depth.
Coming back up above the blowout preventer stack, the drilling mud will continue to travel back outside the drill pipe and inside the drilling riser, which is much large than the casing. The drilling riser has to be large enough to pass the casing strings run into the well, as well as the casing hangers which will suspend the casing strings. The bore in a contemporary riser will be at least twenty inches in diameter. It additionally has to be pressure competent to handle the pressure of the weighed mud, but does not have the same pressure requirement as the blowout preventer stack itself.
As wells are drilled into progressively deeper and deeper formations, the subsurface pressure and therefore the pressure which the blowout preventer stack must be able to withstand becomes greater and greater. This is the same for drilling on the surface of the land and subsea drilling on the surface of the seafloor. Early subsea blowout preventer stacks were of a 5,000 p.s.i. working pressure, and over time these evolved to 10,000 and 15,000 p.s.i. working pressure. As the working pressure of components becomes higher, the pressure holding components naturally become both heavier and taller. Additionally, in the higher pressure situations, redundant components have been added, again adding to the height. The 15,000 blowout preventer stacks have become in the range of 800,000 lbs. and 80 feet tall. This provides enormous complications on the ability to handle the equipment as well as the loadings on the seafloor wellhead. In addition to the direct weight load on the subsea wellheads, side angle loadings from the drilling riser when the surface vessel drifts off the well centerline are an enormous addition to the stresses on both the subsea wellhead and the seafloor formations.
When the blowout preventer stack working pressure is increased to 20,000 p.s.i. some estimates of the load is that it increases from 800,000 to 1,200,000 lbs. The height also increases, but how much is unclear at this time but it will likely approach 100 feet in height.
A complication is that the stresses in the seals on the face of the rams in annular blowout preventers becomes enormous. They are characteristically pressure energized by having a larger pressure area behind the rams than the area of the face seals. When the pressure behind the rams is 20,000 p.s.i., the pressure in the face seals is some high multiple of that. In the rams discussed following, the pressure in the resilient seals will exceed 68,000 p.s.i. Resilient materials at these pressures are likely to fail in various ways, including simply extruding through the smallest of available cracks.
Another complication is that the pressure energized characteristic of the blowout preventer rams is a necessary characteristic, especially at lower pressures. When sealing at lower pressures, the pressure energizing characteristic assists in the sealing and in retaining the seal integrity over a long period of time when the actuator pressure loading may be lost.
It has long been known that the pressure in the resilient seals at the front of blowout preventer rams has ben excessively high, especially as the working pressure has been increasing from 5,000 to 10,000 and then to 15,000 p.s.i., but the natural geometry of the blowout preventer rams and lack of an adequate solution has resulted in the industry simply accepting the situation as it was and accepting the risks.
The object of this invention is to provide a way to regulate the maximum pressure seen in blowout preventer ram seals.
A second object of this invention is to not restrict the necessary pressure energizing characteristic of the blowout preventer rams at low pressures.
A third object of this invention is allow the rams to come together face to face to prevent high pressure generation within the ram seals.
Another object of this invention is to prevent ultra-high pressures in the ram to ram cavity seals.
Referring now to
Blowout preventer stack 60 is landed on a subsea wellhead system 64 landed on the seafloor 66. The blowout preventer stack 60 includes pressurized accumulators 68, kill valves 70, choke valves 72, choke and kill lines 74, choke and kill connectors 76, choke and kill flex means 78, and control pods 80.
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
Referring now to
In the case of the ram which is used in these figures, the area of area 230 is 429.8 sq. in. and the area of areas 230 and 232 is 1477.2 sq. in. or a ratio of 3.437/1. This means that if there is 20,000 p.s.i. on the rear of the ram (and below the rams), the pressure in the seals resisting the force will be 68,739 p.s.i., an extremely high resilient seal pressure.
Referring now to
This allows the lower shear ram 200 to continue to move forward slightly until the face 214 of lower shear ram 200 and the face 272 of upper shear ram 274 contact at 276. Whereas in this view there does not appear to be a contact point due to the central clearance 278 are for the lower sheared pipe section 280, there are generous contact areas on each side of the clearance area. In this way the high energizing forces can energize the seal to a sealing pressure higher than the pressure to be sealed, but can avoid generating ultra-high pressures within the front seal as the rams 200 and 274 come face to face on metal portions.
Additionally as the body seals are connected to the face seal, this method also prevents ultra-high pressures in the seals between the blowout preventer ram and the ram body cavity.
The particular embodiments disclosed above are illustrative only, as the invention may be modified and practiced in different but equivalent manners apparent to those skilled in the art having the benefit of the teachings herein. Furthermore, no limitations are intended to the details of construction or design herein shown, other than as described in the claims below. It is therefore evident that the particular embodiments disclosed above may be altered or modified and all such variations are considered within the scope and spirit of the invention. Accordingly, the protection sought herein is as set forth in the claims below.
Number | Name | Date | Kind |
---|---|---|---|
2146470 | Grantham | Feb 1939 | A |
4229012 | Williams | Oct 1980 | A |
4492359 | Baugh | Jan 1985 | A |
4508312 | Williams | Apr 1985 | A |
4508313 | Jones | Apr 1985 | A |
4541639 | Williams | Sep 1985 | A |
4579314 | Williams | Apr 1986 | A |
4582293 | Jones | Apr 1986 | A |
20160032677 | Hopson | Feb 2016 | A1 |
20190100974 | Mozisek | Apr 2019 | A1 |
20190203555 | Gallagher | Jul 2019 | A1 |
Number | Date | Country | |
---|---|---|---|
20230030422 A1 | Feb 2023 | US |