Claims
- 1. A method of operating a gas turbine comprising the steps of forming three separate combustion cells in a single vessel, forming a bed of particulate material including fuel in each of said cells, passing air through each of said beds, the quantity of air passed through two of said cells being sufficient to fluidize said particulate material in their respective beds and promote the combustion of said fuel, and the quantity of said air passed to the other of said cells being insufficient for complete combustion of said fuel but sufficient to generate a combustible off-gas, the flue gases from the combustion in said two cells passing through the length of said two cells and entraining a portion of said particulate material before discharging from an outlet in said vessel; discharging said off-gas from another outlet of said vessel, separating the entrained particulate material from said flue gases and from said off-gas, burning said separated off-gas in the presence of said flue gases to raise their temperature, and passing said high temperature gases to a turbine.
- 2. The method of claim 1 wherein there is one burner and where said flue gases and said off-gas are passed to said burner.
- 3. The method of claim 1 wherein there are two burners and wherein said flue gases are passed to one burner and said off-gas is passed to the other burner.
- 4. The method of claim 3 wherein the respective gases from said burners are respectively passed to a first stage and a second stage turbine.
- 5. The method of claim 1 further comprising the step of exchanging heat between the spent gases from said turbine and feedwater to raise the temperature of the feedwater, and passing the feedwater to at least one of said cells to convert said heated feedwater to steam.
Parent Case Info
This is a divisional of copending application(s) Ser. No. 07/166,573, filed on 03/10/88 (Abandoned).
US Referenced Citations (12)
Divisions (1)
|
Number |
Date |
Country |
Parent |
166573 |
Mar 1988 |
|