Method for fabricating and assembling a floating offshore structure

Information

  • Patent Grant
  • 6565286
  • Patent Number
    6,565,286
  • Date Filed
    Friday, August 10, 2001
    23 years ago
  • Date Issued
    Tuesday, May 20, 2003
    21 years ago
Abstract
A method for fabricating sections of a floating offshore spar type structure and mating the sections offshore. A buoyant hard tank is fabricated vertically. The hard tank is then transported in a vertical orientation to a site where it is mated to a truss section of the spar structure offshore while the hard tank and truss section are both in the vertical orientation. The mated tank and truss sections are then towed in the vertical orientation to the operational site. The hard tank is fabricated with a larger diameter and correspondingly shallower draft than a more traditionally proportioned hard tank.
Description




BACKGROUND OF THE INVENTION




1. Field of the Invention




The invention is generally related to the construction and assembly of floating offshore structures and more particularly to the construction and assembly of a spar type structure.




2. General Background




Unlike ships which can be fully assembled at an inshore facility, many types of oil drilling and production facilities for the offshore oil production industry require part of the assembly to take place either at the field location itself or at another offshore site prior to the tow to the field location. Due to the deep draft of Spar type platforms, the traditional construction sequence involves joining the structural sections of the hull in the horizontal position, transporting the completed hull in the horizontal position, followed by upending of the entire Spar to the vertical position at a site with sufficiently deep water to accommodate the deep draft.




The structural sections may consist of either plated hull tank sections only or a combination of plated tank and truss type sections. Such Spar type platforms are described in U.S. Pat. Nos. 4,702,321 and 5,558,467.




As a consequence of a horizontal assembly and transport followed by an upending sequence, numerous restrictions come into play that complicate and limit the size of the hull that can be constructed. This can result, depending on geographical location, in any or all of the following.




Draft of the assembled hull in a horizontal orientation exceeds the dredged depths in inland navigable channels for wet tow to the offshore site.




Draft of hard tank or truss sections in horizontal orientation exceeds water depths in inshore assembly areas, dry dock sill clearance depths, and/or heavy lift vessel maximum deck submergence depths. The draft restrictions imposed by fabrication facilities and transportation equipment limit the size of hulls that can be constructed.




Assembly of hull marine systems and mooring equipment in the horizontal orientation rather than the vertical operating orientation complicates fabrication, fit-up, testing and pre-commissioning of this equipment, piping and wiring.




Size and weight of hull in horizontal orientation exceeds the hydrodynamic stability and strength capabilities of the largest existing heavy lift transport vessels. This dictates transportation in sections for final horizontal assembly in an erection facility an acceptably short distance from the offshore site.




SUMMARY OF THE INVENTION




The invention addresses the above needs. What is provided is a vertical construction method. The hard tank is fabricated vertically. The hard tank is then transported in a vertical orientation to a site where it is mated to the truss section of the spar structure offshore while the hard tank and truss section are both in the vertical orientation. The mated tank and truss sections are then towed in the vertical orientation to the operational site. The hard tank is fabricated with a larger diameter and correspondingly shallower draft than a more traditionally proportioned hard tank.











BRIEF DESCRIPTION OF THE DRAWINGS




For a further understanding of the nature and objects of the present invention reference should be made to the following description, taken in conjunction with the accompanying drawings in which like parts are given like reference numerals, and wherein:





FIG. 1

is a plan view that illustrates the fabrication of the hard tank in a dry dock.





FIG. 2

is an elevation view that illustrates the fabrication of the hard tank in a dry dock.





FIG. 3

is a plan view that illustrates the vertical tow out of the hard tank from the dry dock.





FIG. 4

illustrates the submergence of the heavy lift vessel in preparation for receiving the hard tank.





FIG. 5

is a plan view that illustrates the hard tank being moved into position over the deck of the heavy lift vessel.





FIG. 6

is a plan view that illustrates the hard tank in position on the deck of the heavy lift vessel after the heavy lift vessel has been deballasted.





FIG. 7

is an elevation view that illustrates the hard tank in position on the deck of the heavy lift vessel after the heavy lift vessel has been deballasted.





FIG. 8

illustrates the load out of the truss section of the spar onto a barge.





FIG. 9

illustrates the tow of the truss section of the spar to the assembly site.





FIG. 10

illustrates the launch of the truss section of the spar from the barge.





FIG. 11

illustrates the initial position of the truss section of the barge after it has been launched from the barge.





FIG. 12

illustrates the next position of the truss section of the spar after launch from the barge.





FIG. 13

illustrates the truss section of the spar after it has been upended.





FIG. 14

illustrates the truss section of the spar in preparation for lowering to the sea floor.





FIG. 15

illustrates the truss section of the spar after it has been set on the sea floor.





FIG. 16

illustrates the heavy lift vessel ballasted down in preparation to float off the hard tank.





FIG. 17

illustrates the hard tank being moved in position to receive the truss section of the spar.





FIG. 18

is a detail view that illustrates a means of connecting the truss section to winches on the hard tank.





FIG. 19

illustrates the truss section connected to the winches on the hard tank.





FIG. 20

illustrates the truss section being pulled up toward the hard tank.





FIG. 21

illustrates the truss section in the mated position with the hard tank.





FIG. 22

illustrates the tow of the mated truss section and hard tank to the operational site.











DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT





FIGS. 1 and 2

illustrate the hard tank


10


under construction in a dry dock


12


. During the construction phase, a movable gate


14


prevents seawater from entering the dry dock. As seen in

FIG. 2

, the hard tank


10


is fabricated in a vertical orientation by using a crane/trolley combination


16


to lift and position components


18


that are used to fabricate the hard tank


10


.




After the hard tank


10


is completed, the dry dock


12


is flooded with seawater by removing the gate


14


. Designed to be buoyant, the hard tank


10


floats in the flooded dry dock. The hard tank


10


is transported to a location for mating to the truss section. As seen in

FIG. 3

, lines


20


are attached between the hard tank


10


and tugboats


22


. The tugboats


22


are then used to tow the hard tank


10


to open water where it may be loaded onto a heavy lift vessel.




As seen in

FIGS. 4-7

, a heavy lift vessel


24


is ballasted such that the cargo deck


26


is below the water surface at a depth greater than the draft of the hard tank


10


. Lines


20


connected between the hard tank


10


, tugboats


22


, and the heavy lift vessel


24


are used to guide the hard tank


10


into position above the cargo deck


26


. Once in the proper position, as seen in

FIG. 6

, the heavy lift vessel


24


is deballasted to raise the cargo deck


26


and hard tank


10


above the surface of the water as seen in FIG.


7


. The hard tank


10


is secured in position and the heavy lift vessel


24


is used to transport the hard tank


10


to the site for mating with the truss section.




The truss section of the spar structure is constructed in a suitable location and manner. The truss section of a spar type structure is an open space frame such as that described in U.S. Pat. No. 5,558,467. Due to the height of the truss section, it is typically fabricated in a horizontal orientation.




As seen in

FIGS. 8 and 9

, the completed truss section


28


is skidded onto a barge


30


for transport to the assembly site. The truss section


28


is provided with one or more fixed ballast tanks


32


and mud mats


34


. At least one section


36


of the ballast tank is voided to provide temporary buoyancy after launch. The barge


30


is ballasted down to receive the truss section


28


and then deballasted to a shallower draft for transport of the truss section


28


to the assembly site.




Once at the assembly site, one end of the barge


30


is ballasted below the water surface as seen in

FIG. 10

to facilitate launching of the truss section


28


.

FIG. 11

illustrates the initial position of the truss section


28


after launch. The end of the truss section that defines the upper end of the truss section when in the vertical orientation is provided with a temporary buoyancy tank


38


to float that end of the truss section.




The ballast tanks


32


are flooded.

FIG. 12

illustrates the horizontal floating position of the truss section


28


after the ballast tanks


32


are beginning to flood.

FIG. 13

illustrates the truss section


28


after the ballast tanks


32


have been flooded and the truss section has been upended.




Slings


40


on the truss section


28


are attached to the crane


42


as seen in FIG.


14


. The slings may be preinstalled on the truss section


28


. The crane


42


is used to raise the truss section


28


such that it is vertically positioned in the water and the temporary buoyancy tank


38


is at or above the water surface. A line


20


is attached between the temporary buoyancy tank


38


and a tugboat


22


. The temporary buoyancy tank


38


is cut away from the truss section


28


. The truss section


28


is lowered as seen in

FIG. 15

, the temporary buoyancy tank


38


floats away, and the tugboat


22


and line


20


are used to tow the temporary buoyancy tank


38


away from the truss section


28


. The upper portion of the truss section


28


is lowered below the surface of the water to provide a zero water plane area such that the lower end sits on the sea floor


44


.




The positioning and mating of the hard tank


10


with the truss section


28


is illustrated in

FIGS. 18-22

. The heavy lift vessel


24


is ballasted down to a draft that allows floatation of the hard tank


10


off the heavy lift vessel


24


.




Lines


20


attached between the hard tank


10


and tugboats are used to position the hard tank


10


above the truss section


28


. Mating lines or chains


46


from winches


48


are run through the hard tank


10


and the stabbing receptacles


50


designed to receive stabbing posts


52


at the upper end of the truss section


28


. The chains


46


are attached to the stabbing posts


52


of the truss section


28


.




The winches


48


on the hard tank


10


are used to pull the truss section


28


up off the sea floor and the stabbing posts


52


of the truss section


28


into the stabbing receptacles


50


in the hard tank


10


. Once the stabbing posts


52


of the truss section


28


are fully received in the stabbing receptacles


50


, the stabbing posts


52


and the receptacles


50


are shimmed and welded as necessary and grouted together. After the grout has set and temporary equipment removed, the assembled structure


54


is towed to the installation site in a vertical orientation as seen in FIG.


22


.




An alternative to using winches to pull the hard tank and truss section together is to use a crane vessel to lift the truss section.




An alternative to launching the truss section at the mating site is to lift and lower the truss section using one or more crane barges.




An alternative to supporting the truss section on the sea floor at the mating site is to suspend the truss just off the sea floor by designing a slightly negative submerged weight pulling against clump weights suspended from the base of the truss section.




An alternative to fabricating the hard tank in a dry dock is to fabricate the hard tank in a fabrication yard and load it onto a submersible vessel by skidding. The submersible vessel is then used to transport the hard tank to a calm water location. The submersible vessel is submerged at the calm water location and the hard tank is floated off the vessel as illustrated in

FIGS. 4-7

.




The advantages of the vertical fabrication and assembly approach affect the fabricator, installer and operator, resulting in improvements in the reliability, operation and flexibility of both the design itself and the methods of construction.




There are several construction advantages for the hard tank.




Fabricating the cylindrical hard tank vertically is perfectly suited to shipyard, dry dock construction, including the use of normal dry dock supports due to the flat bottom of the hard tank.




The floating draft of the hard tank section can be controlled by the design to meet the draft restrictions of dredged navigation channels, dry dock sills, and heavy lift transport vessels.




Dimensional control, temporary erection steel, scaffolding and personnel access are all greatly simplified when erecting a cylinder upright instead of horizontally.




All the appurtenances, as well as all the hull systems and mooring equipment, can be installed and completely commissioned prior to shipment, since the hard tank is fabricated in its operating position.




The hull is delivered to the deepwater mating site without any remaining commissioning or structural work. There are no “field installed” appurtenances such as sections of strakes, boat landings, stairs and ladders, chain jacks, platforms, external casings, fire pumps, etc. There is no further commissioning needed for the hydraulic power unit, ballast pumps or the associated piping and instrumentation.




Load out and offload operations with the heavy lift transport vessel, as well as the associated support structure and tie downs, are intrinsically less complicated for the flat bottomed vertical cylinder while the VCG (vessel center of gravity) of the cargo is approximately the same as for the horizontal approach.




Vertical fabrication and assembly also provides design advantages. The affinity of the construction method for large diameters offers the Operator great latitude both in selecting the topside payload and in selecting the size of the center-well (moon pool) to accommodate any riser requirements.




The larger diameter hulls are more amenable to larger topside areas. Ultra large facilities may be required to accommodate two drilling rigs. The vertical configuration, with its larger center well, larger well spacing and larger deck areas, can be readily configured for two derricks plus the supporting packages and bulk storage.




Larger areas improve topside layout flexibility, including the opportunity to build in greater separation between the quarters and the hazardous areas.




Larger hull diameters provide more space on the top of the hull for equipment (chain, jacks, etc.) and piping.




Eccentric topside payloads have less impact on the static pitch response of the hull. This feature, like the larger available topside areas, also facilitates the use of dual rigs as they are skidded from well to well.




The shallower hard tank means there are fewer internal compartments, and those that remain are all closer to the water surface. This simplifies personnel access and reduces the number and lengths of the piping, access shafts, and other in hull appurtenances.




The construction method can be applied to hulls sized for fifty thousand to sixty thousand short ton topside payloads, and larger, with virtually no impact to the approach.




Because many varying and differing embodiments may be made within the scope of the inventive concept herein taught and because many modifications may be made in the embodiment herein detailed in accordance with the descriptive requirement of the law, it is to be understood that the details herein are to be interpreted as illustrative and not in a limiting sense.



Claims
  • 1. A method for fabricating sections of a floating spar type structure and mating the sections offshore, comprising the steps of:a. fabricating a buoyant hard tank section in a vertical orientation; b. fabricating a truss section; c. submerging the truss section in a vertical orientation that provides a zero water plane area; d. floating the hard tank above the truss section; and e. moving the truss section up to engage with the hard tank, with the hard tank section remaining in the water after engagement with the truss section and serving as the buoyant hull to support the floating spar type structure.
  • 2. The method of claim 1, further comprising forming a permanent attachment between the hard tank and the truss section.
  • 3. The method of claim 1, wherein the step of moving the truss section up to engage with the hard tank is accomplished using lifting equipment and lines.
  • 4. The method of claim 1, further comprising providing stabbing receptacles in the hard tank and stabbing posts in the truss section.
  • 5. A method for fabricating sections off a floating spar type structure and mating the sections offshore, comprising the steps of:a. fabricating a buoyant hard tank section in a vertical orientation; b. fabricating a truss section; c. transporting the hard tank and truss sections to an offshore site, wherein the hard tank section is transported in a vertical orientation; d. submerging the truss section in a vertical orientation that provides a zero water plane area; e. floating the hard tank above the truss section; and f. moving the truss section up to engage with the hard tank, with the hard tank section remaining in the water after engagement with the truss section and serving as the buoyant hull to support the floating spar type structure.
  • 6. The method of claim 5, further comprising providing stabbing receptacles in the hard tank and stabbing posts on the truss section.
  • 7. The method of claim 5, further comprising forming a permanent attachment between the hard tank and the truss section.
  • 8. The method of claim 5, wherein the step of moving the truss section up to engage with the hard tank is accomplished using lifting equipment and lines.
US Referenced Citations (10)
Number Name Date Kind
2586966 Kuss et al. Feb 1952 A
2857744 Swiger et al. Oct 1958 A
3572041 Graaf Mar 1971 A
3641774 Hekkanen et al. Feb 1972 A
3859806 Guy et al. Jan 1975 A
3876181 Lucas Apr 1975 A
4629365 Kuriiwa Dec 1986 A
4729695 Silvestri Mar 1988 A
4825791 Foster et al. May 1989 A
6135673 Horton et al. Oct 2000 A