The present invention relates to a method for filling deformable karst cave and is applicable to filling and reinforcement of the karst cave during excavation and construction of a tunnel at a karst area. The present invention may efficiently stabilize the karst cave, ensure safety construction of the tunnel and stabilization of surrounding rocks, reduce influences of the karst cave on tunnel construction and later operations, may reduce engineering construction costs and improve an engineering construction speed, and belongs to the field of underground engineering.
With the development of transportation power construction of China, a scale of tunnel construction involved in highway, railway and urban rail transit engineering is expanding, and the tunnel engineering construction inevitably passes through high-risk karst areas; karst caves have great hidden dangers to the safety of the tunnel engineering construction, and need to be filled and reinforced in an early stage; and if the karst caves cannot be effectively filled and reinforced, it is very easy to cause collapse of surrounding rocks or a bottom bearing stratum during excavation and construction of the tunnel, resulting in the burial of excavation machines or personnel, and endangering life safety of builders. However, a traditional karst cave filling method during the tunnel construction at the karst area is to use a grouting process to reinforce the karst cave by filling grout or mortar into the karst cave. This method has a long grouting time and large consumption of materials, and it is not easy to form a filling and reinforcement region in case of encountering a groundwater rich area; and if block stones can be put into the karst cave and then seriflux is injected into the karst cave, a complementary reinforcement effect between different sizes of block stones and the seriflux may be better implemented, and a filling and reinforcement effect of the karst cave may be improved more effectively. However, the size of the diameter of a grouting hole limits a passing property of the block stones, and only small size of block stones can be filled into the karst cave through the grouting hole, but a filling effect is not ideal.
Therefore, based on the limit of the diameter of the grouting hole and a deformable body theory, there is provided a technology for filling a deformable “block stone like” karst cave, the technology including a deformable bracket, an elastic silicone tube, a lock apparatus, and a filling material. The deformable bracket may pass through a limited space of the grouting hole and may be propped up to form a bracket with the filling of the filling material in the karst cave; the elastic silicone tube is a long film tube made of an elastic silicone material, and the long tube may be propped up without breaking with the filling of the filling material; the lock apparatus may cut the elastic silicone tube and implement sealing of the opening of the tube; and the filling material is that: silicate resin materials are filled into the elastic silicone tube first to implement fast expansion and reinforcement, and then a proper amount of grout is injected to implement the “block stone like” structure. The apparatus may efficiently stabilize the karst cave, ensure safety construction of the tunnel and stabilization of surrounding rocks, reduce influences of the karst cave on tunnel construction and later operations, and may reduce engineering construction costs and improve an engineering construction speed.
For the above questions, the present invention provides a method for filling deformable karst cave, and the present invention may efficiently stabilize the karst cave.
The technical solutions of the present invention are as follows:
Further, the deformable bracket is circular with a diameter of 40 cm after the deformable bracket is expanded, and the material thereof is steel wire.
Further, the elastic silicone tube has an inner diameter of 25 cm and a thickness of 2 cm.
Further, the filling material includes silicate resin, grout, and a small amount of steel fibers; and the filling steps of the filling material are:
The elastic silicone tube is expanded after the silicate resin is filled, and the deformable bracket is expanded at the same time, and then grout with the steel fiber is injected to form the “block stone like” structure.
Compared with the prior art, the present invention has the following advantages:
the present invention forms the “block stone like” structure after the filling, which may effectively stabilize the karst cave, ensure safety construction of the tunnel and stabilization of surrounding rocks and reduce influences of the karst cave on tunnel construction and later operations, may reduce engineering construction costs, and may improve an engineering construction speed.
1. block stone like structure, 2. karst cave, 3. borehole conduit, 4. grouting device, 5. console, 6. deformable bracket, 7. pipeline, 8. grouting pipe, 9. elastic silicone tube, 10. circumferential scissor apparatus, 11. circumferential lock apparatus, 12. circumferential scissor, and 13. circumferential lock close insert.
The present invention is further described below with reference to specific embodiments, and the advantages and features of the present invention will be more clear with the description. However, the embodiments are merely exemplary and do not constitute any limitations to the scope of the present invention. Those skilled in the art should understand that modifications and replacements may be made to details and forms of the technical solutions of the present invention without departing from the spirit and scope of the present invention, and these modifications and replacements all fall within the protection scope of the present invention.
As shown in
based on Embodiment 1, the deformable bracket 6 is circular with a diameter of 40 cm after the deformable bracket is expanded, and the material thereof is steel wire; the elastic silicone tube 9 has an inner diameter of 25 cm and a thickness of 2 cm; and filling steps of the filling material are:
Number | Date | Country | Kind |
---|---|---|---|
202110602950.1 | May 2021 | CN | national |
This application is a continuation of International Patent Application No. PCT/CN2021/098869 with a filing date of Jun. 8, 2021, designating the United States, and further claims priority to Chinese Patent Application No. 202110602950.1 with a filing date of May 31, 2021. The content of the aforementioned applications, including any intervening amendments thereto, are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
6322292 | Zenari | Nov 2001 | B1 |
20080205995 | Canteri | Aug 2008 | A1 |
20170058478 | Kirchendorfer | Mar 2017 | A1 |
Number | Date | Country |
---|---|---|
106498965 | Mar 2017 | CN |
109384879 | Feb 2019 | CN |
109750662 | May 2019 | CN |
109931077 | Jun 2019 | CN |
110080779 | Aug 2019 | CN |
110984120 | Apr 2020 | CN |
211621548 | Oct 2020 | CN |
112253227 | Jan 2021 | CN |
113217092 | Aug 2021 | CN |
3837655 | May 1990 | DE |
Entry |
---|
Internation Search Report of PCT/CN2021/098869, dated Feb. 28, 2022. |
Number | Date | Country | |
---|---|---|---|
20230407746 A1 | Dec 2023 | US |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/CN2021/098869 | Jun 2021 | US |
Child | 18456347 | US |