A conventional method for making a prototype of a product employs CNC which cooperates with blades, molds and chuck to make the prototype. In other words, the method using CNC is very much limited by the blades, molds and chuck.
There are several rapid prototyping techniques developed such as SLA as shown in
The SLS employs laser to sinter the resin powder which then binds with the base material on the surface of the prototype. The Z axle is lowered to spread a filament of powder and repeat the sintering process by using laser beam to obtain the prototype. It is noted that the powder is not spread evenly by using the scraper or roller and it consumes a lot of time to pre-heat the power of the base material. The powder could be inhaled by the workers to harm their lungs. The powder is not suitable to be heated evenly so that it is difficult to make large piece of object by this method.
3DP builds a layer of powder and adherent is spread on the selected areas by injection technique such that the powder becomes the outer surface of the prototype. A complete prototype can be obtained by repeating the processes. As expected, the powder is difficult to be spread evenly on a surface and only some type of material can be chosen to be the base material. The precision of the injection machine has to be controlled at a highly precise condition and this increases the difficulties of the method.
LOM cuts a solid material by laser beam into thin layers which are then combined by adherent. The main problem is that extra material is difficult to be removed.
OBJet uses two different materials, one of which is the base material and the other one is used to build a support. The two materials are treated by ultraviolet beam and become gel-like material so as to be combined with each other. A final prototype can be obtained by repeating the processes. The precision of the nozzle to spread the material decides the final result and it requires frequent cleaning to the nozzle.
CLF adds inorganic binder and dissolving agent into the ceramic powder so as to become a plastic mixture. The mixture is mopped to be a flat layer and heated to be a dehydrated layer. The dehydrated layer is then hardened by laser beam at desired areas and is much harder than it is simply dehydrated. This method is not suitable to be used for making prototype.
In accordance with one aspect of the present invention, there is provided a method for forming objects and the method comprises the following steps:
step 1: spreading a base material layer on a surface by a nozzle;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by application of a laser beam to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in nature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
The present invention will become more obvious from the following description when taken in connection with the accompanying drawings which show, for purposes of illustration only, a preferred embodiment in accordance with the present invention.
Referring to
step 1: spreading a base material layer on a surface by a nozzle;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by application of a laser beam to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in mature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading a base material layer on a surface by a nozzle;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by adding a material composition to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in nature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading a base material layer on a surface and rolled the base material layer to define a flat surface by rollers;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by application of a laser beam to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in mature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading a base material layer on a surface and rolling the base material layer by rollers;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by adding a material composition to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in nature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading a base material layer on a surface by a nozzle and then the base material layer being rolled to be a flat surface by rollers.
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by application of a laser beam to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in mature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading a base material layer on a surface by a nozzle and the base material layer being roller to be a flat surface by rollers;
step 2: initiating a first physical or chemical change of the base material layer by exposure to one of ultra violet beams or infra-red beams, the base material layer thereby becoming a gelled material;
step 3: initiating a second physical or chemical change by adding a material composition to selected areas of the gelled base material layer, the second physical or chemical change being a change to the gelled material at each selected area to become hardened in nature;
step 4: repeating steps 1-3 a pre-determined number of times, each newly added base material layer being laminated on a preceding layer to form a plurality of stacked layers, the hardened selected areas of the plurality of stacked layers defining a solid object, and
step 5: removing the portions of base material layers remaining in gelled form after initiation of the second physical or chemical change to obtain a final prototype.
As shown in
step 1: spreading the base material layer on a surface by nozzles;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: selectively proceeding the second time of physical or chemical change by laser beam on the selected areas of the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
As shown in
step 1: spreading the base material on a limited area by nozzles;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: adding additional material to the base material so as to proceed the second time of physical or chemical change for the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
As shown in
step 1: spreading the base material on a limited area by rollers;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: selectively proceeding the second time of physical or chemical change by laser beam on the selected areas of the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
As shown in
step 1: spreading the base material on a limited area by rollers;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: adding additional material to the base material so as to proceed the second time of physical or chemical change for the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
As shown in
step 1: spreading the base material on a limited area by nozzles and rolling the limited area to be a flat surface by rollers;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: selectively proceeding the second time of physical or chemical change by laser beam on the selected areas of the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
As shown in
step 1: spreading the base material on a limited area by nozzles and rolling the limited area to be a flat surface by rollers;
step 2: proceeding the first time of physical or chemical change on the selected areas by the ultra violet beams or infra-red beams;
step 3: adding additional material to the base material so as to proceed the second time of physical or chemical change for the base material;
step 4: repeating steps 1-3 pre-determined times which are the number of layers of the two dimensional areas cut from the solid object, and building connection between the layers;
step 5: removing the base material after the first time of physical or chemical change from the result after the second time of physical or chemical change so as to obtain the final prototype.
Due to the nature of the material, the mechanical strength of the material is not strong enough after the first time of physical or chemical change and is stronger after the first time of physical or chemical change. The less strong material is enclosed by the stronger material. The two types of material can be separated after the object is finished so as to conveniently obtain a three dimensional prototype with less cost, time and higher precision.
While we have shown and described the embodiment in accordance with the present invention, it should be clear to those skilled in the art that further embodiments may be made without departing from the scope of the present invention.
This is a Continuation-In-Part application of U.S. patent application Ser. No. 10/692,813, filed on Oct. 27, 2003.
Number | Date | Country | |
---|---|---|---|
Parent | 10692813 | Oct 2003 | US |
Child | 11723048 | Mar 2007 | US |