This invention relates generally to pile anchor technology and a method for installing a pile anchor. The technology and deployment methods are particularly suited for installing suction pile anchors as anchoring devices for offshore petroleum structures, such as but not limited to floating structures, drilling or production risers, pipelines and other subsea structures.
Suction pile anchors are commonly used in the offshore petroleum industry to moor offshore structures. A suction pile anchor can generally be described as a tubular element, typically but not exclusively circular in cross section, with a closed top and an open bottom. Current practice in the petroleum industry is to install suction pile anchors in a vertical orientation (i.e., the longitudinal axis of the tubular element is installed substantially perpendicularly to the sea floor) at a prescribed distance from the offshore structure it is anchoring. Methods for installing a suction pile anchor in a vertical orientation are known in the industry. In general, after being lowered to the sea floor, the suction pile anchor is allowed to penetrate the soil in a controlled descent, with the weight of the anchor being a primary driving force. Cables are used to help control the descent of the pile anchor, and pressure release mechanisms, such as two-way flow valves on the pile anchor, are opened to allow water to evacuate from inside of the pile anchor, thereby allowing penetration of the pile anchor into the soil. This process is referred to as self-weight penetration. Typically, pile anchors are installed into the seafloor by a combination of self-weight penetration, i.e. the weight of the anchor itself imbeds it into the seafloor, followed by the application of a force on the anchor to obtain the final desired depth of the anchor into the seafloor, i.e. its final penetration. Typically, this force is applied by way of suction penetration. In suction penetration, a water evacuation pump is attached to the suction pile anchor and water pumped out from the anchor's interior. The differential water pressure that is created results in a net downward force that is used to push the suction pile anchor to final penetration. A direct force can also be applied on the anchor, such as using a pile-driving hammer, to achieve final penetration. The direct force can be used either alone or in combination with suction penetration.
Typically, the pile anchor is connected to the offshore structure being moored by an anchor line. This connection is usually accomplished in either a catenary or taut-line application. In a catenary application, the anchor line is usually attached to the suction pile anchor near its top, with the anchor line resting on the sea floor except when tensioned by movement of the structure being moored. In a tautline application, the anchor line is always in tension and it is usually attached to the pile anchor at a location below the sea floor, a distance of some 60% to 70% of the suction pile anchor length, in order to obtain maximum anchor loading capacity. Taut-line suction pile anchor systems have been found to provide maximum resistance for typical deepwater applications where the anchor line assumes an angle with the horizontal equal to about 35 to 45 degrees.
In operation, failure of an anchoring device occurs when it no longer provides resistance against either vertical or horizontal loads, or a combination of both. Of particular concern for pile anchors is preventing vertical load failure. This concern is highlighted during the period after installation when the pile anchor is limited in its ability to resist vertical loads, and therefore the risk of vertical load failure is high. This behavior can be attributed mainly to installation induced disturbance (loss of soil shear strength) in a relatively thin zone of soil that surrounds the pile anchor. Analyses and experience show that the pile anchor can take several months after installation for the soil to regain essentially all of its strength. The lateral resistance is mostly unaffected by the thin zone of disturbed soil, because it mobilizes its resistance from the surrounding undisturbed soil. Accordingly, there is a need in the industry for an installation method that will reduce the risk of vertical load failure of a pile anchor.
When a pile anchor is installed in a traditional vertical orientation, the holding capacity of the anchor will typically increase with the size of the anchor. However, increasing the size of the anchor will cause a corresponding increase in material, fabrication and installation costs. Accordingly, there is a need in the industry for a method of installing a pile anchor that will allow the pile anchor to maintain the same holding capacity at a reduced anchor size. A pile anchor of reduced dimensions can also provide the added benefit of being installed to deeper penetrations, where the soils are typically stronger, and where even greater holding capacity can be achieved.
Correspondingly, there is a need in the industry to increase the holding capacity of a pile anchor of a given dimension in order to reduce the total number of pile anchors required to moor a floating structure. Decreasing the number of pile anchors reduces the installation time, which is a significant cost component of offshore construction.
Accordingly, there is a need for a method of installing a pile anchor that will reduce the risk of vertical failure and increase holding capacity of a pile anchor, and a corresponding need for an installation method that reduces the size and costs of the pile anchor. The present invention satisfies these needs.
The invention is a method for installing a pile anchor into a sea floor. The pile anchor is positioned at an inclined angle with respect to the sea floor, with the top of the anchor inclined in a direction away from the direction of lateral loading, and then inserted at least partially into the seafloor while the angle of inclination is substantially maintained.
Another embodiment of the invention provides a method of producing offshore hydrocarbon resources. The method includes installing a pile anchor into a sea floor. The pile anchor is positioned at an inclined angle with respect to the sea floor, with the top of the anchor inclined in a direction away from the direction of lateral loading, and then inserted at least partially into the seafloor while the angle of inclination is substantially maintained. The method further includes connecting the anchor to an offshore structure that may support at least some equipment used for producing hydrocarbon resources and producing hydrocarbon resources.
The present invention will be described in connection with its preferred embodiments. However, to the extent that the following description is specific to a particular embodiment or a particular use of the invention, this is intended to be illustrative only and is not to be construed as limiting the scope of the invention. On the contrary, it is intended to cover all alternatives, modifications, and equivalents that are included within the spirit and scope of the invention, as defined by the appended claims.
The present invention is a method for installing a pile anchor into a sea floor, and in particular, the invention permits reducing or eliminating the vertical load acting upon a pile anchor and correspondingly increasing the lateral load component, thereby enhancing the anchor's holding capacity. Referring to
This invention provides a method for installing a pile anchor into a sea floor at an inclined angle with the top of the anchor tilted away from the offshore structure being moored, i.e. away from the direction of the applied load from the offshore structure. Pile anchors are commonly used in the offshore petroleum industry to moor offshore structures, including but not limited to floating structures, drilling or production risers, pipelines and other subsea structures. A pile anchor is typically a circular cylindrical member having a length to diameter ratio that is typically greater than 2. It can be fabricated in other geometries, however, such as an elliptical cylinder, 3-D rectangle, etc. and can have a smaller length to diameter ratio. An example of a pile anchor is provided in
When installing a pile anchor according to the method of this invention, care should be taken to ensure that minimal torsional forces (rotational forces about the longitudinal axis of the pile anchor) act upon the pile anchor (100) when it is in its final operating position. For example as shown in
The method of installation described herein also reduces or essentially eliminates the delay for the pile anchor (100) to obtain its maximum holding capacity. By installing the pile anchor in accordance with this invention, the pile anchor's resistance with the soil will be mainly lateral soil resistance, i.e. resistance perpendicular to the longitudinal axis of the pile anchor (100), rather than vertical soil resistance, i.e. resistance along the longitudinal axis of the pile anchor (100). Accordingly, the effect of installation induced disturbance of the soil is minimized. Moreover, because the external load acting on the pile (100) is directed laterally through the soil, the capacity of the pile anchor (100) will be greater than a conventionally (vertically) installed pile anchor even if there were no installation induced soil disturbance
Several embodiments for installing a pile anchor according to the present invention will now be discussed, with the specific examples of suction pile anchors. It should be recognized that this invention is not limited to methods for installation of suction pile anchors, but any type of pile anchor or other tubular member may be used. This invention is also applicable to pile anchor geometries other than cylinders. Moreover, it should be recognized that an anchor installed in accordance with this invention is capable of mooring floating offshore structures as well as other offshore structures, including but not limited to drilling or production risers (501), pipelines (500) and other subsea structures as depicted, for example, in
In one embodiment of the invention, shown in
Once installation of the pile anchor is complete, another suction anchor (100) can be latched into the installation guide frame (200), and the installation process repeated. Latching the pile anchor (100) to the guide frame (200) may be performed by retrieving the guide frame (200) to a surface vessel (not shown), or while the guide frame (200) rests on the sea floor (10). This installation process can be repeated as necessary.
In another embodiment of the invention, the desired angle of inclination is created and maintained by connecting a tensioning device (175) to provide upward tension to the side of the pile anchor (100) on which the lateral load connection is applied, i.e. padeye (120). For example, as shown in
Referring now to
The pile anchor (100) for this embodiment contains one or more internal structural member(s) (210), that form two or more internal compartments (200A, 200B) within the pile anchor (100). The internal structural members can be, but are not necessarily made of the same material as the pile anchor (100) itself. Two-way flow valves (110) are fluidly connected to each internal compartment (200A, 200B) through cap (150), and can be used to evacuate water from the individual compartments (200), using a water evacuation pump (not shown). In accordance with this embodiment of the invention, an impermeable membrane (220) is positioned within the lower portion of anchor (100) to prevent inflow of seawater. Gas lines (230) can be fluidly connected to each internal compartment (200A, 200B) being evacuated of water to provide air or other gases to the evacuated compartment(s) to prevent premature rupture of the membrane (220).
The compartments (200A, 200B) can be designed and arranged so that the selective evacuation of water from one or more of the compartments (200A, 200B) will allow for controlled changes to the anchor's (100) buoyancy. For example, referring again to
To install the pile anchor (100) in accordance with this embodiment, the anchor is lowered into the sea, and the internal compartments (200A, 200B) are allowed to fill with water through two-way flow valves (110). The suction pile anchor (100) can be lowered until it is within a few feet of the sea floor (10). Water is pumped out of internal compartment (200B), i.e. the compartment adjacent to the side of the pile anchor (100) on which the lateral load is to be applied, through the corresponding two-way flow valve (110). Air or another gas or gases can be provided through gas line (230) to the internal compartment being evacuated (200B). These selective changes to the anchor's buoyancy causes the suction pile anchor (100) to rotate about the axis of spreader bar (140), with the top of the anchor (100) moving in a direction away from the direction of the lateral load. Pumping is stopped when the desired pile anchor (100) inclination is achieved. The pile anchor (100) is then allowed to penetrate the sea floor (10) by self-weight penetration. Prior to self-penetration, slings or rigging cables (not shown) may be attached to stabilize the suction pile anchor (100) during initial self-weight penetration. During self-weight penetration, the impermeable membrane (220) will rupture automatically or be mechanically removed as the pile anchor (100) penetrates the sea floor (10). The impermeable membrane (220) should be positioned within the pile anchor (100) such that it will rupture only after the soil has formed a seal at the lower end of the anchor (100) to prevent inflow of water. If necessary, final installation can be achieved by direct force, suction penetration or a combination thereof, as previously described.
Other similar methods for installing a pile anchor (100) at an inclination can be used. Referring to
Another similar embodiment, shown in
Another embodiment is shown in
Another embodiment of the invention is shown in
The pile anchor (100) is initially contained within the mechanical installation mechanism (470) as depicted in FIG. 9. The pile anchor (100) and mechanical installation mechanism (470) may be lowered to the sea bed (10) separately or together with the pile anchor (100) contained within the structure of the mechanical installation mechanism (470). The skirt foundation (410) is imbedded into the sea bed (10) with the frame sections (420A & 420B) situated approximately perpendicular to the sea bed (10) while the jacking devices (440) are in the retracted position as depicted in FIG. 9. The jacking devices (440) can then be expanded hydraulically or by using an electric motor to push the upper ends of the frame sections (420A & 420B) apart thereby decreasing the angle between at least one of the frame sections (420B) and the sea bed (10) as depicted in FIG. 10. The mechanism used to expand the frame sections (420A & 420B) of the mechanical installation mechanism (470) can be activated by a ROV or acoustically from the water's surface. The pile anchor (100) will then lean against the declined frame section (420B) and will be able to slide in relation to such frame section (420B) through contact with the rollers (460) attached to the inner side of the frame section (420B). After being positioned in the desired angle, the pile anchor (100) may then be inserted a desired distance into the sea bed (10) through gravity and suction penetration.
The pile anchors may be used to anchor an offshore structure through use of anchor chains connected to such pile anchors. The anchor chains may be connected to the anchor using, for example, a padeye. The offshore structure may be a floating structure such as a spar (e.g. a deep draft caisson vessel (“DDCV”) or a truss spar) that is equipped with a deck. The deck can support offshore hydrocarbon resource (i.e. oil and gas) exploration, drilling and production operations. The deck may be use to conduct offshore seismic data collection. Alternatively, the deck can support offshore drilling equipment for oil and/or gas drilling operations. Alternatively, the deck may also support oil and/or gas production equipment for the production of offshore oil and gas hydrocarbon resources. Produced oil and/or gas may then be offloaded from the deck by, for example, pipeline to shore or a transport ship or barge and then moved to shore. The oil and gas may then be refined into usable petroleum products such as, for example, natural gas, liquefied petroleum gas, gasoline, jet fuel, diesel fuel, heating oil or other petroleum products.
The present invention has been described in connection with its preferred embodiments. However, to the extent that the foregoing description is specific to a particular embodiment or a particular use of the invention, this is intended to be illustrative only and is not to be construed as limiting the scope of the invention. On the contrary, it is intended to cover all alternatives, modifications, and equivalents that are included within the spirit and scope of the invention, as defined by the appended claims.
This application claims the benefit of U.S. Provisional Patent Application No. 60/362,875 filed Mar. 8, 2002.
Number | Name | Date | Kind |
---|---|---|---|
3852969 | Gibson et al. | Dec 1974 | A |
4131166 | Schnell | Dec 1978 | A |
4185694 | Horton | Jan 1980 | A |
4690586 | Oksuzler | Sep 1987 | A |
4702047 | Stokes | Oct 1987 | A |
5033908 | Auraen | Jul 1991 | A |
5127767 | Plagborg-Moller | Jul 1992 | A |
6122847 | Treu et al. | Sep 2000 | A |
6457908 | Bergeron | Oct 2002 | B1 |
Number | Date | Country |
---|---|---|
1269599 | Apr 1972 | GB |
WO 9925606 | May 1999 | WO |
Number | Date | Country | |
---|---|---|---|
20030167659 A1 | Sep 2003 | US |
Number | Date | Country | |
---|---|---|---|
60362875 | Mar 2002 | US |