The object of the invention is a method, as presented in the preamble of claim 1, for installing an elevator in the construction phase of a building.
Elevators are generally already needed in high-rise buildings already in the construction phase of the building, when the lower floors of the building are completed. In this case so-called jump-lifts are generally used, which enable use of the elevator in an unfinished elevator hoistway to as high in the building as the built floors allow. This type of jump-lift solution known in the art is, however, extremely complex and expensive because a temporary machine room plus associated machines and electrical connections are needed in it, which machine room is raised farther upwards from time to time as new floors are completed and the electrical connections have to be disconnected and reconnected in conjunction with each lift.
U.S. Pat. No. 5,033,586 presents one solution according to prior art, in which a temporary machine room module, formed from two decks and a frame connecting them, can be lifted to the desired height in the elevator hoistway and locked into its new position. The machine room module is disposed in the hoistway above the elevator car. The hoisting machine together with conventional machine room components and hoisting rope reels is disposed at a higher level than the module. When the machine room module is lifted upwards, the elevator car is locked into position and the additional length of hoisting ropes needed is taken from the reels from the top deck of the machine room module. A problem in this solution is that the whole amount of additional rope plus reels and also the machine room module with all its components must always be lifted upwards at the same time. In addition, the electrification must always be disconnected during a lift and reconnected when the machine room module has been lifted to its new position. Heavy-duty hoists are needed in the work due to the large masses and the whole installation job is slow and also dangerous. In addition, disassembly of the temporary machine room module at completion of installation produces a lot of waste material and also takes time.
The aim of the present invention is to eliminate the aforementioned drawbacks and to achieve an inexpensive and easy-to-implement method for installing an elevator in the construction phase of a building, said method enabling fast and safe installation. The method according to the invention is characterized by what is disclosed in the characterization part of claim 1. Other embodiments of the invention are characterized by what is disclosed in the other claims.
Some inventive embodiments are also discussed in the descriptive section of the present application. The inventive content of the application can also be defined differently than in the claims presented below. The inventive content may also consist of several separate inventions, especially if the invention is considered in the light of expressions or implicit sub-tasks or from the point of view of advantages or categories of advantages achieved. In this case, some of the attributes contained in the claims below may be superfluous from the point of view of separate inventive concepts. Likewise the different details presented in connection with each embodiment can also be applied in other embodiments. In addition it can be stated that at least some of the subordinate claims can, in at least some situations, be deemed to be inventive in their own right.
One advantage of the solution according to the invention is that in the construction phase the temporary hoisting machine of the elevator can be kept all the time in the same location in the bottom part of the elevator hoistway and likewise the electrical connection does not need to be disconnected and reconnected always in conjunction with a jump lift, i.e. in conjunction with a jump function. Another advantage is that the load to be lifted in conjunction with a jump function is significantly lighter than in current solutions according to prior art. In the solution according to the invention a smaller and more lightweight hoist can in this case be used for implementing the jump function. A further advantage of the solution is that it is significantly safer and faster than solutions that are currently known in the art.
In the method of the invention a construction-time elevator function is achieved in the construction phase of a building, the function having at least an elevator car adapted to move in an elevator hoistway, one or more compensating weights, which are for their part connected, via a suspension beam fixed above the elevator car, to support the elevator car by means of ropes or belts and also by means of a diverting pulley or diverting pulleys, and also a hoisting machine provided with one or more traction sheaves or corresponding, the hoisting machine being kept in its position in the construction phase, and at least one traction member, such as a belt, rope or chain, which is adapted to transmit the rotational movement of the traction sheave into movement of the elevator car and of the compensating weight in the direction of their trajectory, in which case in this elevator the supporting and the moving of the elevator car have been separated from each other. When taking the elevator into normal operation when the building is at its final height, the installation-time hoisting machine, i.e. the hoisting machine, plus traction sheave and traction member being held in position in the construction phase, is removed and the new hoisting machine plus traction sheave and hoisting roping is installed into position. The hoisting machine being kept in its position in the construction phase is disposed in the construction phase preferably in the proximity of the bottom part of the elevator track, most suitably in the bottom part or on the base of the elevator hoistway. The machine for the normal-drive elevator of the building will be in the top part of the elevator hoistway or in the proximity of the top part, most suitably in a machine room above the elevator hoistway. The elevator configuration in use during the construction time is well suited for lifting upwards from time to time according to the jump-lift concept. During the construction time of the building, the elevator car plus suspension beam is lifted by means of a so-called jump function to a new height position always after the building has reached the height of the next phase. After the building, or at least the part of the building comprising the elevator hoistway in question, has been completed to its final height, the new hoisting machine plus traction sheave is placed into position, preferably above the elevator car, and the elevator car is connected to the compensating weight by means of one or more hoisting ropes, which hoisting ropes are arranged to be driven by the hoisting machine on its traction sheave and to suspend the elevator car and the compensating weight or compensating weights. The elevator car and each compensating weight are preferably those that were used in the construction phase of the building or have been modified from them. Often it is advantageous to modernize the elevator car completely, at least in respect of the cabin.
In the following, the invention will be described in more detail by the aid of some examples of its embodiment with reference to the simplified and diagrammatic drawings attached, wherein
The method according to the invention is characterized in that a separate temporary machine room is not needed for performing jump functions nor is the hoisting machine lifted to anywhere during the jumps. A further essential point is that electrical connections do not need to be disconnected during the jumps and do not need to be reconnected again after the jumps.
In the solution according to the invention the elevator car 1 is arranged to travel upwards and downwards in the elevator hoistway guided by guide rails 2. The elevator car 1 is suspended with one or more suspension ropes 1a on a suspension beam 2a via the diverting pulleys 7 in such a way that the first ends of the suspension ropes 1a are fixed to the compensating weight 3, from where the suspension ropes 1a rise up and over the first and second diverting pulleys 7 and descend back towards the elevator car 1. The compensating weight 3 is arranged to travel upwards and downwards along its own guide rails as the elevator car 1 moves. For the sake of clarity the guide rails of the compensating weight 3 are not, however, presented in the figures. Instead of one or more compensating weights 3, one or more counterweights can also be used. Whenever hereinafter only one compensating weight 3 is mentioned, the simultaneous meaning intended is one or more compensating weights, or alternatively one or more counterweights.
After passing around the top of the second diverting pulley 7, the suspension ropes 1a descend to one or more feeder reels 9 for suspension rope, said reel(s) being fixed to the roof of the elevator car 1, from which reel(s) additional length for the suspension ropes is taken during a jump function being performed to a higher level. The designation first feeder reel is also used for the feeder reel 9 hereinafter. During normal operation of the elevator in the construction phase of the building the first feeder reel 9 is locked so that it does not rotate and the suspension ropes 1a are fixed with rope clamps, or in a corresponding manner, in such a way that the length of the suspension ropes 1a between the elevator car 1 and the compensating weight 3 does not unintentionally change. The overspeed governor 8 is fixed to the suspension beam 2a or preferably also to a guide rail 2.
In connection with the elevator car 1, e.g. on the roof of the elevator car 1, is also a pedal 12 of a bypass apparatus for the locking of the elevator car 1, by using which pedal the locking of the elevator car 1 implemented with the wedges of the safety gear can be temporarily removed, e.g. for performing a service drive. When pressing the pedal 12 and keeping the pedal 12 activated, i.e. pressed downwards, the locking-bypass apparatus detaches and keeps the safety gear wedges off the elevator guide rails 2, in which case the elevator car 1 can be driven e.g. on service drive.
In the construction phase of the building the supporting and the moving of the elevator car 1 are separated from each other. With the temporary hoisting machine 4, which is provided with one or more traction sheaves 5, service runs and normal runs are driven with the elevator car 1. The temporary hoisting machine 4 is disposed in the bottom part of the elevator hoistway below the elevator car 1 and likewise the electrification of the hoisting machine is in the bottom part of the elevator hoistway. The temporary hoisting machine 4 and its electrification are in the same location for essentially the whole duration of the installation of the elevator and, therefore, likewise for the whole construction time of the building. The traction member 1b is connected between the compensating weight 3 and the elevator car 1, from the bottom of one to the bottom of the other. The traction member 1b can be either an individual element or a plurality of parallel elements that are similar to each other. Whenever hereinafter only one traction member 1b is mentioned, the simultaneous meaning intended is one or more traction members, such as one or more toothed belts, chains, or some other type of elements that do not slide on the traction sheave 5.
The traction member 1b is on the feeder reel 10, which is fixed e.g. to the bottom part of the compensating weight 3. From the feeder reel 10 the traction member 1b has been led downwards around the bottom of the diverting pulley 6 that is in the bottom part of the elevator hoistway, from which diverting pulley 6 the traction member 1b has been led onwards around the bottom of the traction sheave 5 and from the traction sheave 5 onwards to its fixing point 1c on the bottom part or base of the elevator car 1, to which fixing point 1c the second end of the traction member 1b is fixed. The designation second feeder reel is also used for feeder reel 10 hereinafter. There can be more than one second reel 10, according to need.
During a jump to a higher level, the additional length needed for the traction member 1b is taken from the second feeder reel 10. During normal operation of the elevator in the construction phase of the building, the second feeder reel 10 is locked so that it does not rotate and the traction member 1b is fixed with rope clamps, or in a corresponding manner, in such a way that the length of the traction member 1b between the elevator car 1 and the compensating weight 3 does not unintentionally change.
The auxiliary hoist 11 to be used in the installation of the elevator is suspended by means of a hoisting rope 11a and a diverting pulley 11b on a fixed point in the building below the elevator car 1 in such a way that the auxiliary hoist 11 itself is fixed to the suspension beam 2a and the hoisting rope 11a of the auxiliary hoist 11 is led from the auxiliary hoist 11 over the top of the diverting pulley 11b back to the suspension beam 2a, to which the second end of the hoisting rope 11a is fixed. Here, the suspension ratio of the auxiliary hoist 11 is thus 2:1, but it could also just as well be 1:1. The auxiliary hoist is e.g. a TIRAK-type hoist, with the hoisting rope 11a passing through it. In conjunction with the lift the auxiliary hoist 11 remains fixed in its position and the length of the hoisting rope 11a between the auxiliary hoist 11 and the fixing point of the second end is shortened.
In the situation according to
Correspondingly, in the solution according to
In the situation according to
The traction ratio of the traction member 1b of the elevator and the suspension ratio of the suspension ropes 1a can be the same as or also different to each other. In the case according to
In the solution according to
The solution according to
In the solutions according to
In the arrangement according to the invention the traction member 1b is separated from the suspension members 1a only during use of the elevator while the building is still under construction and after the building has been completed the elevator is converted for normal operation by removing the temporary machine 4, plus traction sheave 5 and diverting pulley 6 and traction member 1b, and also by installing the new hoisting machine 4a plus traction sheave 5a above the elevator car 1.
The method according to the invention for installing an elevator and converting it for final use can be implemented following, for example, the phases hereunder:
This list of the different phases of the method is not exhaustive, neither do all the phases necessarily need to be present or in the sequence presented above. In addition, the phases can be different, and there can be more or fewer of them.
The installation of the elevator can also be implemented in such a way that the elevator hoistway plus elevator car 1, plus guide rails 2 plus compensating weight 3 and plus the temporary hoisting machine 4 with ropes and diverting pulleys are constructed to completion for their whole height, or for almost their whole height, and the building is constructed floor by floor around the elevator hoistway. In this case a jump function is not necessarily needed after a new floor or floors is/are completed, but instead the elevator car 1 is controlled only to travel higher when a new floor has been completed.
When the building is finished, the temporary hoisting machine 4 that is in the bottom part of the elevator hoistway is replaced with a new hoisting machine 4a plus traction sheave 5a and diverting pulley 6a in essentially the same manner as stated in the preceding. In this case, it can be replaced with a new elevator car 1, or the interior decoration of the elevator car that is in the hoistway can be replaced with the final interior decoration, because during the construction time the elevator car 1, or at least its interior decoration, could have been subjected to stress that may have damaged the elevator car 1 or its interior decoration.
It should also be noted that the different solutions presented above can be inventive features together with one or more other features of the invention.
It is obvious to the person skilled in the art that the invention is not limited solely to the examples described above, but that it may be varied within the scope of the claims presented below. Thus, for example, the suspension solutions as well as the number and sequence of the phases of the method can also be different to what is presented above.
This application is a continuation of PCT International Application No. PCT/FI2015/050641 which has an International filing date of Sep. 25, 2015, the entire contents of which are incorporated herein by reference.
Number | Name | Date | Kind |
---|---|---|---|
6364067 | Glassey | Apr 2002 | B1 |
8291568 | Barneman | Oct 2012 | B2 |
9415974 | Perala | Aug 2016 | B2 |
9834415 | Hense | Dec 2017 | B2 |
20070137946 | Aulanko | Jun 2007 | A1 |
20080308362 | Tucker | Dec 2008 | A1 |
20090223751 | Peacock | Sep 2009 | A1 |
20110113720 | Peacock | May 2011 | A1 |
20120023863 | Van Der Meijden | Feb 2012 | A1 |
20120291395 | Plathin | Nov 2012 | A1 |
20130118838 | Plathin | May 2013 | A1 |
20130248299 | Perala | Sep 2013 | A1 |
20140231179 | Alasentie | Aug 2014 | A1 |
20140231180 | Kallioniemi | Aug 2014 | A1 |
20180127244 | Fauconnet | May 2018 | A1 |
Number | Date | Country |
---|---|---|
104024141 | Sep 2014 | CN |
1785386 | May 2007 | EP |
2823734 | Oct 2002 | FR |
H03267283 | Nov 1991 | JP |
H10250958 | Sep 1998 | JP |
WO-9943596 | Sep 1999 | WO |
WO-03086937 | Oct 2003 | WO |
WO-2004113218 | Dec 2004 | WO |
WO-2009073010 | Jun 2009 | WO |
WO-2010139845 | Dec 2010 | WO |
WO-2011080387 | Jul 2011 | WO |
WO-2011148033 | Dec 2011 | WO |
WO-2012072860 | Jun 2012 | WO |
WO-2012089896 | Jul 2012 | WO |
WO-2013079790 | Jun 2013 | WO |
WO-2013110850 | Aug 2013 | WO |
WO-2016126933 | Aug 2016 | WO |
Entry |
---|
International Search Report PCT/ISA/210 for International Application No. PCT/FI2015/050641 dated Sep. 25, 2015. |
Written Opinion of the International Searching Authority PCT/ISA/237 for International Application No. PCT/FI2015/050641 dated Sep. 25, 2015. |
Office Action dated Dec. 27, 2018 by the Chinese Patent Office for Application No. CN 201580083321.5. |
Number | Date | Country | |
---|---|---|---|
20180186607 A1 | Jul 2018 | US |
Number | Date | Country | |
---|---|---|---|
Parent | PCT/FI2015/050641 | Sep 2015 | US |
Child | 15907813 | US |