This disclosure relates to a method for constructing a bridge by launching a superstructure. The present disclosure relates to a “launching method of a composite concrete filled steel tube (CFT) truss girder bridge”, which is constructed by temporarily assembling the CFT truss girder and a precast concrete slab to form a “segment” and then launching a plurality of segments in sequence.
A CFT truss girder is a girder constructed by concrete filled steel tubes (CFTs), each being prepared by filling concrete in a steel tube, in a truss structure. An incremental launching method (hereinafter, referred to as “ILM”) has been used for constructing a bridge. In the ILM, a plurality of segment units, which will configure a superstructure of a bridge, is pre-fabricated at a casting bed built at the rear of an abutment, and then the segment units are pushed in a bridge axis direction in order by using an extrusion device such as a jack device to construct a bridge.
When constructing a bridge using the CFT truss girder and the concrete slab, it is desirable to use the ILM. However, an existing ILM has following problems, and these problems should be solved.
When a superstructure of a bridge, composed of a steel girder and a precast concrete slab, is constructed by means of an existing ILM, a unit of a superstructure should be completely pre-fabricated with a steel girder and an in-situ concrete slab before launching the unit. Thus, the existing technique has a drawback in an extended construction period. In addition, in the existing technique, while units of the superstructure are being launched in sequence, in order to offset a tensile stress applied to the concrete slab, a prestressing force should be continuously introduced to the concrete slab throughout the launching process. Thus, construction costs may be increased.
In the existing ILM, a steel girder may be launched in advance. However, in this case, a concrete slab should be fabricated with the steel girder by placing concrete in-site, and thus the extended construction period is not shortened. In addition, after the steel girder is launched, when the concrete slab is fabricated with the steel girder by placing concrete in-site, the fabrication work should be performed at a high place, which deteriorates construction efficiency and safety. Therefore, in order to construct a bridge having a superstructure bridge with a CFT truss girder and a concrete slab by means of the ILM, it is needed to solve the problems of the existing ILM as mentioned in the above.
This disclosure is designed to overcome the limit of the above existing technique. The present disclosure is directed to shortening a construction period, improving construction efficiency and ensuring improved safety during a construction process by minimizing works at the bridge construction site, when a bridge is constructed to have a superstructure with a CFT truss girder and a concrete slab by means of the ILM.
In addition, the present disclosure is directed to effectively suppressing a lateral torsional buckling caused at the girder and to ensuring stability for the lateral torsional buckling. In addition, the present disclosure is directed to preventing an excessive tensile force from being applied to a precast concrete slab during a launching process so that the concrete slab is not damaged due to the tensile force.
In one general aspect, there is provided a launching method of a bridge, which constructs a bridge to have a superstructure composed of a concrete filled steel tube (CFT) truss girder and a precast concrete slab, the launching method comprising: placing a precast concrete slab on a CFT truss girder at a casting bed to fabricate a segment including the CFT truss girder and the precast concrete slab in a temporarily assembled state, successively disposing segments to connect CFT truss girders integrally with each other, and launching the segments in order in a front direction to form a superstructure of a bridge; and after the segments are completely launched, integrally composing the CFT truss girders and the precast concrete slabs, wherein a prestressing force is applied to the precast concrete slabs in a longitudinal direction so that the precast concrete slabs are integrated with each other.
In the launching method of a bridge, a plurality of precast concrete slabs is successively disposed in a longitudinal direction at a single segment, and after the segments are completely launched, when the CFT truss girders and the precast concrete slabs are integrally composed, a prestressing force is applied to the plurality of precast concrete slabs in a longitudinal direction so that the precast concrete slabs are integrated with each other.
The CFT truss girder includes an upper beam, a lower beam, and a web beam connecting the upper and lower beams. Support members may be provided at an upper surface of the upper beam to support the precast concrete slab. A shear pocket may formed with a through hole is formed in the precast concrete slab at a location placed on the upper beam of the CFT truss girder and a stud inserted into the shear pocket is provided at the upper beam. Further, the process of temporarily assembling the CFT truss girder and the precast concrete slab by placing the precast concrete slab on the CFT truss girder includes placing the precast concrete slab on the support member so that the stud is inserted into the shear pocket, and coupling an extension rod to an upper portion of the stud and installing an anchor plate on an upper surface of the precast concrete slab so that the upper portion of the extension rod is coupled to the anchor plate.
In the launching method of a bridge, the process of integrally composing the CFT truss girders and the precast concrete slabs may include removing the extension rod and the anchor plate, and placing a grouting material in the shear pocket at which the stud is located so that the grouting material fills the upper space of the upper beam and the shear pocket and is cured. A through hole may be formed in the anchor plate so that the extension rod passes therethrough. The process of coupling the upper portion of the extension rod to the anchor plate may include placing the anchor plate on the shear pocket in a state where the extension rod is coupled to the stud so that the upper portion of the extension rod is inserted into the through hole and thus the anchor plate passing through the anchor plate is placed on the upper surface of the precast concrete slab, and coupling a coupling member to the extension rod protruding on an upper surface of the anchor plate to press the anchor plate toward the upper surface of the precast concrete slab.
In the launching method of a bridge, when the CFT truss girder and the precast concrete slab are integrally composed, after the extension rod and the anchor plate are removed, a head portion is coupled to a top of the stud, and then the grouting material is placed in the shear pocket.
In the launching method of a bridge, the process of fabricating segments and launching the segments in order in a front direction to form a superstructure of a bridge may include placing a precast concrete slab on a CFT truss girder and temporarily assembling the precast concrete slab and the CFT truss girder to fabricate a first segment; temporarily assembling a CFT truss girder and a precast concrete slab to fabricate a second segment, and disposing the second segment at the rear of the first segment to connect the CFT truss girders of the first and second segments; pushing the first and second segments to be launched in a front direction; and fabricating an additional segment by temporarily assembling a CFT truss girder and a precast concrete slab, disposing the additionally fabricated segment at the rear of the segment located at a rearmost side, connecting CFT truss girders of the segments, and then pushing the segments to be launched in a front direction.
In the launching method of a bridge, a winch is installed at an abutment of the bridge. In the process of pushing the segments to be launched in a front direction, a cross beam having a pulley is installed at a rear end of the segment located at a rearmost side, a wire is wound around the pulley, and the winch winds the wire to pull the wire so that the segment is moved forwards.
According to the present disclosure, a long-span bridge having a lightweight superstructure composed of a CFT truss girder and a precast concrete slab may be constructed.
In particular, in the present disclosure, since main members of the superstructure of a bridge are pre-fabricated at a factory, works at the bridge construction site may be minimized, and thus it is possible to greatly shorten a construction period required for constructing the bridge, improve construction efficiency by means of mechanized construction, and ensure safety during a construction process.
In addition, in the present disclosure, a precast concrete slab suppresses a lateral torsional buckling caused at the CFT truss girder while the superstructure of the bridge is being launched, and thus excellent stabilization may be ensured against the lateral torsional buckling.
Moreover, in the present disclosure, while the superstructure of the bridge is being launched, it is possible to prevent an excessive tensile force from being applied to the precast concrete slab, and thus it is possible to effectively prevent the precast concrete slab from being damaged due to a tensile force.
Hereinafter, an embodiment of the present disclosure will be described with reference to the accompanying drawings. Even though the present disclosure is described based on the embodiment depicted in the drawings, this is just an embodiment, and the technical features, essential configurations and operations of the present disclosure are not limited thereto. For reference, in the present disclosure, a direction for pushing a segment toward a bridge pier at an abutment along a bridge axis is described as a “front direction”, and its opposite direction is described as a “rear direction”. In addition, a bridge axis direction is described as “a longitudinal direction”, and a bridge transverse direction is described as a “transverse direction”.
Then, as shown in
During fabricating the segments as described above, only the CFT truss girders 1 are integrally connected to each other. In other words, when the second segment S2 is successively disposed at the rear of the first segment S1 and then the first and second segments S1, S2 are integrally connected, the precast concrete slabs 2 are not yet integrally connected, but only the CFT truss girder of the first segment S1 is integrally connected with the CFT truss girder of the second segment S2. The CFT truss girders may be integrally connected in various ways, for example by means of welding. When the second segment S2 is disposed at the rear of the first segment S1 and is connected thereto, a launching nose 9 is installed at the front of the first segment S1 and is connected thereto. The launching nose 9 is a member generally used in an incremental launching method (ILM) and thus is not described in detail here.
In a state where a plurality of segments is successively disposed and integrated as described above at a casting bed in a bridge axis direction, the segments are extruded forwards (Step 3). For this, as shown in
Then, as shown in
A series of processes for successively disposing a new segment at the rear of a rearmost segment among the segments launched forwards and integrally connecting thereto, and then installing an extrusion jack 39 thereto and operating to launch the segments forwards is repeated so that a plurality of segments is successively disposed all over the entire span of a designed bridge (Step 6).
While the plurality of segments is successively disposed all over the entire span of the designed bridge and is supported by bridge piers 32, in each segment, the CFT truss girder 1 and the precast concrete slab 2 are still in a temporarily assembled state. In other words, the CFT truss girder 1 and the precast concrete slab 2 are not yet perfectly integrally composed with each other. In addition, the precast concrete slabs 2 of the segments are not yet integrally composed with each other in a bridge axis direction. Therefore, after the plurality of segments is successively disposed all over the entire span of the designed bridge, in each segment, the CFT truss girder 1 and the precast concrete slab 2 are integrally composed, and in a bridge axis direction, the precast concrete slabs 2 of the segments are also integrally composed with each other (Step 7).
In the bridge launching construction method of the present disclosure, the segments are launched in a state where the precast concrete slab 2 is “temporarily assembled” to the CFT truss girder 1, and the CFT truss girder 1 and the precast concrete slab 2 are integrally composed after the segments are completely launched all over the entire span of the bridge. Now, a structure and method for temporarily assembling the CFT truss girder 1 and the precast concrete slab 2 will be described. In addition, a structure and method for integrally composing the CFT truss girder 1 and the precast concrete slab 2 will be described.
The precast concrete slab 2 is a rectangular concrete slab with a predetermined thickness. The precast concrete slab 2 is installed on the CFT truss girder 1 to configure a segment. In a single segment, a length of the precast concrete slab 2 in a bridge axis direction may be identical to a length of the CFT truss girder 1 in a bridge axis direction. However, in a single segment, a length of the precast concrete slab 2 in a bridge axis direction may be smaller than a length of the CFT truss girder 1 in a bridge axis direction. In this case, in a single segment, a plurality of precast concrete slabs 2 is successively located in a bridge axis direction and installed on the CFT truss girder 1. In addition, when forming a single segment, a plurality of precast concrete slabs 2 may be successively disposed in a longitudinal direction. In a single segment, a plurality of precast concrete slabs 2 may be successively disposed in a longitudinal direction on the upper beams 11 of the CFT truss girders 1 successively disposed in a longitudinal direction.
The precast concrete slab 2 is placed on the upper beam 11 of the CFT truss girder 1. The precast concrete slab 2 has a shear pocket 20 at a location where the precast concrete slab 2 is placed on the upper beam 11. The shear pocket 20 is a through hole formed through the precast concrete slab 2 in a thickness direction thereof. A plurality of shear pockets 20 is formed at intervals in a bridge axis direction.
At the upper surface of the upper beam 11, a vertical stud 14 is provided at a point where the shear pocket 20 is located when the precast concrete slab 2 is placed. In other words, the stud 14 made of a rod member stands vertically and is fixedly installed at the upper surface of the upper beam 11. A thread may be formed at a top of the stud 14.
A support member 15 may be provided at the upper surface of the upper beam 11 so that the precast concrete slab 2 may be stably placed on the upper surface of the upper beam 11. In the embodiment depicted in the drawings, the support member 15 has a bent beam which has a bent section with a “¬” shape to have a horizontal portion and a vertical portion and extends in a bridge axis direction. A lower end of the vertical portion of the support member 15 is coupled and fixed to the upper surface of the upper beam 11. Two support members 15 make a pair and are respectively provided at both sides in a bridge transverse direction on the upper beam 11. A sealing member 150 such as a rubber plate may be disposed at an upper surface of the horizontal portion of the support member 15. The support member 15 may extend in a bridge axis direction all over the entire length of the upper beam 11.
The CFT truss girder 1 having the upper beam 11, the stud 14 and the support member 15 is pre-fabricated at a factory and installed at the casting bed 31. The precast concrete slab 2 is also produced in advance at a factory in a precast manner and then fabricated with the CFT truss girder 1 at the casting bed 31.
The precast concrete slab 2 is lifted by means of a lifting device such as a crane, and then installed on the upper beam 11 of the CFT truss girder 1 at the casting bed 31. If the precast concrete slab 2 is moved down on the CFT truss girder 1 as shown in
Subsequently, an extension rod 16 is coupled to the upper portion of the stud 14, an anchor plate 17 is installed at the upper surface of the precast concrete slab 2, and the upper portion of the extension rod 16 is coupled to the anchor plate 17. As shown in
Then, the anchor plate 17 is installed and coupled to the extension rod 16. The anchor plate 17 is placed on the upper surface of the precast concrete slab 2 to traverse the shear pocket 20. A through hole 170 is formed in the anchor plate 17. As shown in
A coupling member 18 is coupled to the extension rod 16 formed through the anchor plate 17 and protruding on the upper surface of the anchor plate 17, as shown in
If the precast concrete slab 2 is installed on the CFT truss girder 1 as described above, the precast concrete slab 2 is supported by the support member 15, and the stud 14 is located in the shear pocket 20. In this state, if the extension rod 16 is coupled to the stud 14 and also the anchor plate 17 and the coupling member 18 are installed thereto, the CFT truss girder 1 and the precast concrete slab 2 are temporarily assembled. In other words, the CFT truss girder 1 and the precast concrete slab 2 are temporarily assembled to make a segment.
In a state where the CFT truss girder 1 and the precast concrete slab 2 are temporarily assembled, the CFT truss girder 1 and the precast concrete slab 2 are not perfectly integrated with each other, but when the segment is launched forwards, the CFT truss girder 1 and the precast concrete slab 2 move together. In particular, since the CFT truss girder 1 and the precast concrete slab 2 are temporarily assembled, it is possible to effectively prevent the lateral torsional buckling from occurring at the CFT truss girder 1 while the segment is being launched.
The CFT truss girder 1 includes the upper beam 11 and the lower beam 12 respectively located at upper and lower portions in a vertical direction, and also includes the web beams 13 connecting the upper and lower beams 11, 12 with each other. Therefore, if a force is applied to the CFT truss girder 1 in a vertical direction, the CFT truss girder 1 is likely to be distorted, which may generate lateral torsional buckling.
However, in the present disclosure, since the stud 14 is fixed by means of the extension rod 16, the anchor plate 17 and the coupling member 18 as shown in
Next, the work for integrally composing the CFT truss girder 1 and the precast concrete slab 2 in each segment and the work for integrally composing the precast concrete slabs 2 of segments in a longitudinal direction, performed in Step 7, will be described in detail.
In the present disclosure, since the stud 14 is fixed by means of the extension rod 16, the anchor plate 17 and the coupling member 18 as shown in
If the plurality of segments are completely launched and thus disposed successively all over the entire span of the designed bridge, the coupling member 18, the anchor plate 17 and the extension rod 16 are dissembled and removed. If required, in order to further reinforce the role of the stud 14 as a shear connector, a head portion 140 having a greater diameter than the stud 14 may be assembled to the top of the stud 14 after the extension rod 16 is removed.
A prestressing force is introduced to the precast concrete slab 2 in a bridge axis direction all over the entire span of the bridge to integrate the precast concrete slabs 2 of all segments. For this, when the precast concrete slab 2 is fabricated, a sheath pipe or the like may be buried in the precast concrete slab 2 in advance so that a tendon may be disposed therein.
After a prestressing force is introduced in a bridge axis direction to integrate the precast concrete slabs 2, the shear pocket 20 in which the stud 14 is located is filled with a grouting material 27.
As described above, in the present disclosure, a segment is fabricated using the CFT truss girder 1 and the precast concrete slab 2, such segments are successively disposed and the CFT truss girders 1 are connected in a bridge axis direction, and the segments connected to each other are launched forwards in order to construct a bridge. However, in the present disclosure, when the segments are launched, the CFT truss girder 1 and the precast concrete slab 2 are not yet perfectly coupled and integrally composed but are still in a temporarily assembled state. In this temporarily assembled state, while the segments are being launched, a tensile force applied to the CFT truss girder 1 is not transferred to the precast concrete slab 2. Therefore, when the segments are launched, it is possible to prevent an excessive tensile force from being applied to the precast concrete slab 2, and accordingly it is possible to effectively prevent the precast concrete slab 2 from being damaged by the tensile force.
In a state where the CFT truss girder 1 and the precast concrete slab 2 are temporarily assembled, the precast concrete slab 2 serves as a kind of bracing member to prevent lateral torsional buckling at the CFT truss girder 1. If only the CFT truss girder 1 is launched and then a slab is coupled to the CFT truss girder 1 after launching of the CFT truss girder 1, lateral torsional buckling is highly likely to occur at the CFT truss girder 1 while the CFT truss girder 1 is launched.
However, in the present disclosure, since the segment including the CFT truss girder 1 and the precast concrete slab 2 in a temporarily assembled state is launched, the precast concrete slab 2 suppresses lateral distortion of the CFT truss girder 1 while the CFT truss girder 1 is being launched. Therefore, in the present disclosure, it is possible to very effectively prevent the lateral torsional buckling from occurring at the CFT truss girder 1 during a launching process, thereby enhancing safety against the lateral torsional buckling.
In the embodiment of the present disclosure shown in
As shown in
As described above, in the bridge launching construction method according to the present disclosure, a precast concrete slab and a CFT truss girder fabricated at a factory are assembled at the casting bed to make each segment, and segments successively disposed are launched forwards to construct a bridge. Since main members of a superstructure of a bridge are pre-fabricated at a factory, works on the bridge construction site may be minimized, and thus it is possible to greatly shorten a construction period required for constructing the bridge, improve construction efficiency by means of mechanized construction, and ensure safety during a construction process.
In addition, in the present disclosure, the segment is launched in a state where the CFT truss girder and the precast concrete slab are “temporarily assembled”. Thus, during the launching process, the precast concrete slab suppresses a lateral torsional buckling phenomenon caused at the CFT truss girder, and thus excellent stabilization may be ensured against the lateral torsional buckling.
In particular, in the bridge launching construction method according to the present disclosure, it is possible to construct a long-span bridge, and thus the present disclosure may be very usefully applied to a large bridge or a railway bridge which crosses an obstacle such as a river or a valley.
Number | Date | Country | Kind |
---|---|---|---|
10-2015-0146405 | Oct 2015 | KR | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/KR2015/011324 | 10/26/2015 | WO | 00 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2017/069313 | 4/27/2017 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
4993094 | Muller | Feb 1991 | A |
5617599 | Smith | Apr 1997 | A |
5802652 | Smith | Sep 1998 | A |
5978997 | Grossman | Nov 1999 | A |
7546656 | Kim | Jun 2009 | B2 |
7669272 | Powers | Mar 2010 | B2 |
Number | Date | Country |
---|---|---|
2003-193430 | Jul 2003 | JP |
10-2011-0023334 | Mar 2011 | KR |
10-2011-0041144 | Apr 2011 | KR |
10-2011-0126866 | Nov 2011 | KR |
10-1245620 | Mar 2013 | KR |
10-2013-0141275 | Dec 2013 | KR |
Entry |
---|
PCT International Search Report, PCT/KR2015/011324, dated Sep. 1, 2016, 4 Pages. |
Number | Date | Country | |
---|---|---|---|
20180291570 A1 | Oct 2018 | US |