Method for NC- programming and system for NC- machining

Abstract
In the present invention, for an NC program for controlling a machine tool, information for machining quality required by a machine tool is prewritten in the program. A measurement program for measuring the machining quality of the workpiece using a measuring machine is produced by analyzing the NC program. The machining quality of the workpiece is measured by the measurement program and the measuring machine. The machining quality of the workpiece can be judged by comparing the measurement results and the machining quality information included in the NC program. By utilizing this quality judgement, simple and effective system control can be achieved when a system such as CIM (Computer Integrated Manufacturing) is constructed in cooperation with other machine tools.
Description




TECHNICAL FIELD




The present invention relates to a method for producing a measurement program for measuring machining quality in an NC machining process in order to realize an effective NC machining system, and to an NC machining system utilizing the measurement results of the machining quality of the workpieces obtained by using the measurement program produced by this method.




BACKGROUND ART




With an NC machine tool, tool movement can be automatically controlled by an input NC program. In addition, in recent years, NC machine tools have come to be widely used in various industrial fields as computerized numerical control machines (CNC machine tools) in combination with advanced technology such as advanced microprocessor, power electronics, or software technology.




Typically, numerical control information such as an NC program includes individual information such as a tool indexing command, a main-spindle speed command, a feed-rate command, a traverse and interpolation command, an auxiliary function command and the like and a working history, and is formed as an NC program so as to be suitable for a machine tool that is a controlled system in machining.




NC programs produced in this manner are used in various machining processes. In order to perform high quality machining, it is necessary to measure the workpiece after a final machining process or at intermediate machining processes and to modify the machining control for the next workpiece or the following machining processes for the same workpiece according to the measured results. Conventionally, measurement is carried out so that sizes of the workpieces are partially measured at intermediate machining processes using simple instruments such as a micrometer or vernier calipers, and then all significant measurements of the workpieces are assessed in a final inspection. When there are any problems concerning the measured results, such a situation is fed back to the NC machining. This feedback of measured results to the machining control is carried out by experienced skilled workmen through oral or memo communication between the workmen. Consequently, with conventional systems it is not possible to automatically feedback the measured results to the machining control in real time.




Moreover, because in conventional simple measurement only limited measurements are made during the machining process,a final inspection is required for precise measurement. Therefore, there are disadvantages in that recognition of the problems is delayed and that the yield of the NC machining is lowered.




In order to solve such problems, an automatic measurement programming method has been proposed in which measurement programs for the finally finished workpieces or for the intermediate processes are prepared in advance, and the measurements are automatically and sequentially carried out during NC machining using an instrument such as a three-dimensional coordinate measuring machine or the like, and the measured results are fed back to the NC machining. According to such art, the measurement itself can quickly and accurately be carried out without relying upon skilled workmen.




However, such a conventional automatic programming requires complicated operations by a CAD/CAM system based on material data, final machined shapes, tool data, and the like. Therefore, there remain problems that the conventional automatic programming cannot be utilized in all NC machining processes, and that a large scale facility is required.This method is therefore rarely utilized only in certain cases where mass production is performed using one NC program.




There are further disadvantages in that a measurement program by an automatic programming is produced based on final shape data of a product, in particular working drawings, and that therefore the measurement program is not optimized for workpiece shapes during intermediate stages of each operation element, working element, or process during execution of an actual NC program.




The expression “working element” employed herein is defined as a group of a plurality of operation elements for the same machining position of a workpiece. In other words, the operation element is a single machining operation executed by each tool, for example, a single operation such as drilling, milling. Working element refers to a combined operation for completing machining for the same machining position of the workpiece by combining a plurality of operation elements. For example, in the case of machining a threaded hole, the working element is defined as the element composed of three operation elements such as center hole drilling, drilling of a hole before threading, and tapping. In addition, process refers to all of the groups of a series of machining operations to be carried out in the same chucking attitude of a workpiece on a machine tool.




In recent years, it has become common in NC machining to use NC programs that are open and flexible as far as possible. In actual machining, the NC program is often re-edited and modified to pursue an optimum machining method. In addition, NC programs are commonly modularized, or made flexible in order to achieve free modification. As a result, there is such a problem that a conventional machining program simply produced based on a working drawing cannot cope with the respective actual stages of the operation elements, working elements or processes, and cannot be used with advanced NC machine tools.




Furthermore, in recent years, advanced NC machining has come to be performed out not only by a single machine tool, but also by CIM (Computer Integrated Manufacturing) system coordinating a number of machine tools. In such cases, there is also such a problem that a conventional non-flexible measurement program cannot be imparted with learning ability to cope with the application to other machine tools or the application to new machine tools.




In an attempt to deal with such a problem, technology such as disclosed in PCT/JP96/03265 is proposed. However, while many of the problems described above are addressed by that technology, there remains many possible improvements for more efficiently producing a measurement program. The object of the present invention is to provide a new method and system for improving this technology.




DISCLOSURE OF THE INVENTION




A method for producing an NC program according to the present invention in order to achieve the object describe above is characterized in that machining quality information concerning the machining quality after machining a workpiece is written in the NC program. The machining quality information includes information on the tolerance and surface roughness required of the workpiece after machining.




In addition, the NC machining system according to the present invention may comprise the steps of producing a measurement program for measuring machining quality of a workpiece machined using a machine tool by a measuring machine through analyzing the NC program produced according to the method described above; measuring the machining quality of the workpiece using the produced measurement program and the measuring machine; and discriminating the machining quality of the workpiece by comparing the results of the machining quality of the workpiece measured by the measuring machine and the required machining quality information included in the NC program.




Furthermore, the NC machining apparatus according to the present invention may comprise measurement program producing means for producing a measurement program for measuring machining quality of the workpiece machined using a machine tool by a measuring machine through analyzing the NC program for executing a machining control of the machine tool for the workpiece; a measuring machine for measuring the machining quality of the workpiece using the produced measurement program; and discriminating means for discriminating the machining quality of the workpiece by comparing the results of the machining quality of the workpiece measured by the measuring machine and the required machining quality information included in the NC program.











BRIEF DESCRIPTION OF DRAWINGS





FIG. 1

is a block diagram showing the overall configuration of an NC system including the measurement program production and machining control according to the present invention.





FIG. 2

is a block diagram showing an apparatus for producing a measurement program according to the present invention.





FIG. 3

is a block diagram showing a division for extracting machining shape information according to the present invention in the system shown in FIG.


2


.




FIG.


4


A and

FIG. 4B

are examples of code for actual machining NC programs used in the embodiments of the present invention.





FIG. 5

is a figure showing a shape of a blank used to illustrate a preferred embodiment of the present invention.





FIG. 6

is a figure showing a final shape of a workpiece used to illustrate the preferred embodiment.





FIG. 7

is a figure showing a tool list used to illustrate the preferred embodiment.




FIG.


8


A and

FIG. 8B

are figures showing a part of a measurement program derived from the actual machining NC program of FIG.


4


A and

FIG. 4B

according to the preferred embodiment.





FIG. 9

is an explanatory figure showing the execution of the measurement program and the analyzing processes of the measured values according to the present invention.





FIG. 10

is an explanatory figure showing the flow of the measurement data between respective processes.





FIG. 11

is an explanatory diagram showing an example of measured results.











BEST MODE FOR CARRYING OUT THE INVENTION




A preferable embodiment of the present invention will be described in detail with reference to the drawings.





FIG. 1

shows the overall configuration of the NC machine tool system incorporating the measurement program producing method and the process management method according to the present invention.




An NC program producing means


20


produces an NC program based on blank (or workpiece) data, a final workpiece shape, and required quality information. This NC program is characterized in that quality information such as tolerances at various stages of machining each operation element, working element machining, and process machining for the workpiece is written in the program differently from a conventional NC program.




The NC program producing means


20


produces a required NC program based on, in addition to the input blank data, final workpiece shape, and required quality information, data for accumulated know-how obtained from various databases. In the example of the present embodiment, the blank data include shapes and materials of blanks. In the embodiment shown in

FIG. 1

, the databases comprise an operation development database


21


A, a cutting condition database


21


B, a tool database


21


C, a working history database


21


D, and a machine accuracy database


21


E. From each of these databases, conditions necessary for actual machining operations such as past know-how in a machining shop, specifications of the machine shop, conditions particular to the employed machine tools, and the like are supplied to the NC program producing means


20


as reference data for use in creating the NC program.




The NC program and the tool list created in such a manner are supplied to an NC apparatus


25


. Necessary idle operations, test cutting or simulations are performed. Then, an actual machining NC program to be used finally in a machining shop using the NC apparatus


25


is completed after modifying and re-editing of the NC program (not shown).




The NC apparatus


25


comprises an NC program execution means


27


, a servo control means


28


, and an error compensation means


29


to drive a machine tool


26


. The NC program, the tool list, and the blank data are input into the NC program execution means


27


. The NC program execution means


27


executes interpolation processing by the respective input data based on an appropriate feedrate and while referring to the measured results, as will be described below, and supplies a servo control signal to the servo control means


28


. Thus, the machine tool


26


can be controlled in a feed drive control by the drive signal output from the servo control means


28


so as to accurately fit the NC program. The error compensation means


29


is provided to compensate for size and position errors due to temperature change or the like in the machine tool


26


, and can compensate for such errors based upon an output signal of a measuring instrument mounted on the machine tool


26


.




In the manner described above, the machine tool


26


executes desired operation element machining, working element machining, and process machining for a workpiece


30


mounted on a worktable, and completes the machining in the first chucking attitude of the workpiece


30


.




When the process machining for the workpiece


30


in the first chucking attitude has been completed, a measuring machine


31


executes coordinate measurement of the workpiece


30


according to the measurement program of a measurement control apparatus


32


. The measured results are fed back to the NC program execution means


27


of the NC apparatus


25


in the next process via a measurement result analyzing means


33


, and are supplied to the respective databases,


21


A,


21


B,


21


C,


21


D, and


21


E, as necessary. When the quality information of the NC program includes not only information obtained from the coordinate measurement such as required tolerances, but also information about required surface roughness of the machined surface, information for executing the surface roughness measurement of the machined surface is written into the measurement program for the measurement control apparatus, and the surface roughness measurement of the machined surface is carried out by the measuring machine


31


.




Thus, according to the embodiment shown in

FIG. 1

, desired NC machining can be performed on the workpiece


30


based on the produced NC program. When the process machining for the workpiece


30


in the first chucking attitude has been finished, the workpiece is re-chucked for the second attitude, and similar machining operations are successively carried out in the second chucking attitude according to the NC program.




In the present invention, the measurement program to be supplied to the measurement control apparatus


32


is produced from the actual machining NC program to be supplied to the NC apparatus


25


. In order to realize the advantages of the present invention, a machining shape information extracting division


34


, a geometrical model producing division


35


, and a measurement program producing division


36


are provided.




The tool list and the actual machining NC program output from the NC program producing means


20


are supplied to the machining shape information extracting division


34


. The machining shape information extracting division


34


extracts machining shape information at appropriate stages of the machining of each operation element, working element, or process on the basis of these input data by analyzing the actual machining NC program. The extracted machining shape information is converted into a three-dimensional geometrical element, or to a geometrical model, at selected stages in the geometrical model producing division


35


. The measurement program producing division


36


can produce an optimum measurement program for the geometrical element, or a geometrical model by selecting a predetermined measurement path. Furthermore, the machining shape information extracting division


34


extracts the quality information from the actual machining NC program and directly outputs the quality information to the measurement program producing division


36


.




It can be clearly seen from

FIG. 1

that the measurement program produced in such a manner is supplied to the measurement control apparatus


32


, that the geometrical model produced in the geometrical model producing division


35


is supplied to the measurement result analyzing means


33


, and also that the measurement list output from the measurement program producing division


36


is similarly supplied to the measurement result analyzing means


33


. In the present invention, not just the tool list and the NC program described above, but also the blank data and the final workpiece shape may be supplied to the machining shape information extracting division


34


. It is thereby possible to further simply and accurately determine, for example, a travelling path of a measuring probe, or the like.




Therefore, according to the present invention, because the measurement program is always related to the actual machining NC program, it is possible to obtain an optimum measurement program according to the NC program used in actual machining. In addition, because the results measured by such a measurement program are always fed back to the NC apparatus


25


, it is possible to perform work control according to the measured results.




The results of the accuracy measured at every stage of the NC program are input to a work achievement analyzing means


22


shown in

FIG. 1

via the measurement result analyzing means


33


. The tool list and the actual machining NC program are also input to the work achievement analyzing means


22


. The work information is analyzed, and the information under various conditions is classified and output into the respective databases


21


A,


21


B,


21


C,


21


D, and


21


E for cutting conditions, tools, work history, machine accuracy, and the like. The present invention is characterized in that the machine accuracy database is provided. As used here, the term “machine accuracy” refers to the accuracy peculiar to the machine tool, and in general can be obtained from the actually measured machining accuracy and the machining conditions.





FIG. 2

shows detailed constitution of the measurement program producing division of the NC machine tool system described above (FIG.


1


). In this embodiment, the measurement is carried out by taking a working element during NC machining as a basic unit. Timing of the measurement is just after the working element has been obtained by completing a series of operation elements. Naturally, the measurement may be carried out at the stage just after the completion of a process that is a combination of a plurality of working elements. For practical purposes, in an actual measurement program, timing of the measurement is determined so as to be just after completion of a working element or a process.




In

FIG. 2

, an NC program


40


is supplied to an NC program analyzing division


41


of a machining shape information extracting division


34


. The NC program analyzing division


41


first divides the NC program into operation elements based on the tool data supplied separately and the NC program


40


, and then supplies the information of the operation elements to a working element extracting division


42


. The NC program analyzing division


41


extracts quality information from the NC program and outputs the extracted quality information to a measurement program producing division


36


. The working element extracting division


42


combines a plurality of operation elements, and extracts working elements from the NC program, and outputs them. The NC program analyzing division


41


supplies coordinate data existing in the NC program to a coordinate system conversion division


43


to convert the coordinate systems prepared for NC machining to the three-dimensional coordinate systems for measurement. A list of the extracted working elements and a list of the converted coordinate systems are supplied to a geometrical element producing division


44


of the geometrical model producing division


35


, and the working element designated by the NC program


40


is converted to a geometrical element in an ordinary three-dimensional coordinate system, and then output. Although in the example of the present embodiment, the geometrical element is further synthesized as a geometrical model in a geometrical model producing and processing division


45


, and the geometrical model is supplied to a measurement program producing division


36


, the conversion to the geometrical model is not always necessary with the present invention. The list of geometrical elements output from the geometrical element producing division


44


may be supplied to the measurement program producing division


36


intact. Further, the geometrical model


46


produced in the geometrical model producing and processing division


45


may be supplied to the measurement result analyzing means


33


as shown in FIG.


1


.




The geometrical model or the list of the geometrical elements is supplied to the measurement program producing division


36


, and probe information


47


of the measuring machine


31


, machining quality information, and other necessary information


49


are supplied to the measurement program producing division


36


. A measurement program


50


is produced based on these given input information and is supplied to the measurement control apparatus


32


.





FIG. 2

shows schematic steps for producing the measurement program


50


from the NC program


40


in the present embodiment. The respective steps will be described in detail in the following.




First, details of the NC program analyzing division


41


for extracting operation elements will be described with reference to

FIGS. 3

to


7


.





FIG. 3

exaggeratedly shows the respective components of the NC program analyzing division


41


in the machining shape information extracting division


34


(

FIG. 2

) according to the present invention. The actual machining NC program and the tool list are input to the NC program analyzing division


41


as described above. In addition, the blank data and the final workpiece shape are also input as necessary.




In the NC program analyzing division


41


, the respective input data are stored in a storage device


60


. The actual machining NC program is analyzed block by block, and is converted into numerical data by a numerical data conversion division


61


. The respective data are registered as a G-code development list in a G-code development list producing division


62


. In this case, when a plurality of operations are executed in one block as in a macro-program and a sub-program, the data are used to develop a basic command according to RS-274-D format, and then are registered as the G-code development list. Such G-code development is not always necessary in the present invention. In the present example, however, in order to process the actual machining NC program using a computer, the G-code development is adopted because of the easiness of the analysis.




In the NC program analyzing division


41


, the continuous actual machining program is divided for every operation element in an operation element dividing division


63


with reference to the G-code development list.




Preferably, in an ordinary case, the division of the program into every operation element machining in the operation element dividing division


63


is executed, taking notice of sequence number (N number), tool indexing (T code), tool changing (M


6


), and optional stop (M


01


). In practice, because only one tool is used during the period from the tool changing to the next tool changing, such a division of a program into every operation element can be executed by noting of tool changing to divide operation elements. However,because in some cases a plurality of operation elements are performed using a single tool, such as, for example, when a plurality of holes before threading are drilled using one drill, it is preferable to also read out a tool path pattern in addition to the tool changing to reliably execute the division of a program for every operation element.




FIG.


4


A and

FIG. 4B

show examples of actual machining NC programs used in the present embodiment. The program number is


00001


. A special point of this program is that machining quality information (tolerance information) is written in the lines of 50, 51, 52, 58, 59, and 60. The slash symbols/on the respective lines are disregarded in executing the NC program.





FIG. 5

shows the shape of the blank to be machined by the actual machining NC program.

FIG. 6

shows the final machined shape to be manufactured from the blank shown in FIG.


5


. The blank data (including materials) and the final machined surface are supplied to the NC program analyzing division


41


as the data as described above. As shown in

FIG. 6

, in this machining, face milling of the upper surface is required.




For such machining operations, the NC program producing means


20


determines machining procedures, develops the machining procedures for operation elements, determines an operation tool for every operation element, and further determines cutting conditions for the respective tools.





FIG. 7

shows a tool list used in the program


00001


. Respective tool numbers are shown by the T code, and tool data of the respective tools are listed as shown in FIG.


7


. This tool list is supplied to the NC program analyzing division


41


.




The measurement program producing division


36


creates the necessary measurement program


50


based on the required machining quality information input from the NC program analyzing division


41


and also based on the probe information


47


and the other information


49


as shown in

FIG. 2

, if necessary. In this case, referencing commands for comparing the required tolerances such as tolerances of holes, dimensional tolerances, or the like with the measured values are automatically determined. Necessary information other than theses tolerance information are as follows.




1. Information particular to measurement program




(a) Program name




(b) Program file name




(c) File name of output result




(d) Device for outputting result




(e) Format for outputting result




(f) Others (process control information, or the like)




2. Information particular to measuring machine




(a) Setting of datum surface




(b) Unit (mm/inch)




(c) Travelling and measuring speed




(d) Parameters of measuring operation




(e) Probe (measurement value) information




(f) Reference information




(g) others (a master ball for calibrating a probe, or the like)




3. Information particular to setting of initial coordinate systems




(a) Switching of automatic measurement and manual measurement




(b) Calling of coordinate systems




Because the respective information described above are not included in the NC program itself used in the present invention, an operator ordinarily inputs the information before machining is begun. For example, in the case of a measuring machine, because initial parameters are preset, it is unnecessary to particularly input the initial parameters individually. Furthermore, when the required values are different from the initial values, the initial values can easily be input by only selecting a prepared template having the initial values.




Thus, according to the present invention, the measurement program


50


can easily be produced by analyzing the NC program


40


. FIG.


8


A and

FIG. 8B

show a part of the measurement program produced by the measurement program producing method according to the present invention. A special point of this is that automatically produced tolerance information (quality information) is written in the lines of


72


,


73


,


74


,


85


,


86


,


87


,


98


,


99


, and


100


.




The present invention is characterized in that a measurement program is produced from an NC program as described above, and that a measurement program closely related to actual machining operation can be obtained. It is also possible to improve the relationship between the NC machining program and the measurement program by feeding-back the actual machining shapes to the work control by the machine tool while measuring the machining shapes during actual machining operation by the measurement program.





FIG. 9

shows a state in which the measurement control apparatus


32


controls the measuring machine


31


using the measurement program


50


. The measurement control apparatus


32


sends a command indicating measurement paths defined by the predetermined measurement program to the probe of the measuring machine


31


. The probe automatically measures a machining shape at directed stages. Then, the measured values are sent from the measurement control apparatus


32


to a measurement data collecting division


70


as measurement data, and are stored in a database


71


after header information is added. The measurement result analyzing means


33


includes a process analyzer


72


together with the measurement data collecting division


70


and the storage database


71


. The analyzed values of the measurement results can be fed back to the machine tool


26


to reflect the measurement results upon the following machining processes.





FIG. 10

shows the flow of the measurement results at each machining process. In the present embodiment, each measurement operation is carried out in any selected process, and the measurement results are immediately analyzed by the process analyzer


72


, and are fed back to the work control in the following process or the preceding process, as necessary.




Again,

FIG. 9

will be described in further detail.




When any one of the results measured by the measuring machine


31


exceeds the tolerance limit or exists within the dangerous range, the measurement result analyzing means


33


immediately informs the machine tool


26


of this measurement result as error measurement data, and gives an instruction to the machine tool


26


to temporarily stop machining operation, to change cutting amount at the following machining process, or to take other appropriate action.




The measurement control apparatus


32


sends ordinary data to the measurement data collecting division


70


. Header information such as the following are added to the measured data.




1. Information for header




(a) Title of header




(b) File name of header




(c) Date (data producing date)




(d) Names of parts




(e) Unit




(f) Number of measurement items




2. Information for measurement items




(a) Names of measurement items




(b) Names of features




(c) Value




(d) Upper allowable value




(e) Lower allowable value




(f) UCL (Upper Control Limit)




(g) LCL (Lower Control Limit)




3. Information for machining process




(a) Error factor




(b) Information related to errors




(c) Environment temperature




The process analyzer


72


executes statistics, analysis, and diagnosis using the measurement data stored in the database


71


, and produces control charts such as an {overscore (X)}-{overscore (R)} chart, an {overscore (X)}-S chart or a trend, and outputs the results to the NC apparatus


25


of the machine tool


26


.





FIG. 11

is a control chart showing the relationship between the measurement values and the nominal value. When the measurement value exceeds the upper limit or the lower limit of the tolerance, such a situation is sent to the NC apparatus


25


as a value outside the tolerance. Further, when the measurement value is within the dangerous range beyond the safety range near the tolerance limit, checking of the preceding process or notification to the next process is sent as a dangerous state.




With the present invention, because measurement results can be obtained during machining easily and in real time, it is possible to immediately indicate the measurement results to the following processes in order to easily feed the results to cutting conditions such as feedrate of a tool or the like at the next process.




In addition, control data obtained from the process analyzer


72


are analyzed by well known diagnosis programs such as FMEA (Failure Mode and Effect Analysis) and FTA (Failure Tree Analysis). The likelihood ratio of these diagnosis programs can be improved by successively determining the modification and change of the machining program and the measurement program according to the present invention. Furthermore, the power of the main spindle is collected as data in time series based on the motion dynamics of the machine tool


25


, and is analyzed by spectrum analysis using FFT (Fast Fourier Transform) and other hardware. Accordingly, higher harmonics of the waveform can be digitized and their variance can be calculated. In this case, it is possible to judge a drop of tool sharpness, wear of the tool, wrong chucking of a workpiece, and accuracy of the machine tool. It is preferable that these judging functions are included in the diagnosis programs such as FTA of the process analyzer described above.




Furthermore, information about a state of the machine tool


26


is supplied to the database


71


. In addition, various errors (except required tolerances) from an error database


73


and an error factor database


74


or error factor diagnosis program data are supplied to the database


71


. On the basis of these data, the process analyzer


72


can supply not only the analyzed information described above but also respective elements of the workpiece shape, such as a size, a shape, an attitude, a position or surface roughness, to the machine tool


26


as data. Consequently, the machine tool


26


can optimally carry out the working control at the next process based on these control data.




Effects of the Invention




As described above, the present invention makes it possible in NC-machining for a measurement program to directly be obtained from an actual machining NC program, and optimum and detailed measurement results are easily obtained in connection with required quality at any machining stage.




Further, because the measurement program according to the present invention does not require complicated automatic programming as in the known art, the measurement program can be produced regardless of a size of the NC program. Further, because the measurement program always corresponds to the actual machining NC program, when any conditions including required quality are modified, other conditions can be modified correspondingly. Therefore, a work control by a machine tool can be aided by both of the machining program and the measurement program in connection with each other.




Further, the measurement program according to the present invention can function for not only the machine tool adopting the NC machining program, but also other machine tools in the same manner. In addition, because the respective measurement programs are constructed as an assembly of modularized measurement programs at any stages for any of operation elements, working elements or processes, it is possible to produce a measurement program having very high flexibility. In addition, these measurement program always can include the know-how necessary for measurements in the latest state. The measurement program can be applied to other machine tools, while retaining acquired know-how. Therefore, there is such a advantage that the measurement program has not only superior flexibility but also wide expandability.




The measurement results obtained by using the measurement program according to the present invention can in all cases be fed to the next stage or the preceding stage, and can provide useful measurement data as work control data.



Claims
  • 1. A method for producing an NC program for automatically controlling a machine tool to machine a workpiece comprising a step of:writing machining quality information into the NC program, the machining quality information regarding machining quality after machining a workpiece.
  • 2. A method for producing an NC program according to claim 1, wherein the machining quality information includes required tolerance information.
  • 3. A method for producing an NC program according to claim 1, wherein the machining quality information includes required surface roughness information.
  • 4. An NC machining system comprising the steps of:producing a measurement program for measuring machining quality of a workpiece machined by a machine tool using a measuring machine through analyzing an NC program for carrying out machining control of the machine tool for the workpiece; measuring machining quality of the workpiece using the produced measurement program and the measuring machine; and judging machining quality of the workpiece by comparing the measurement results of machining quality of the workpiece measured by the measuring machine and machining quality information included in the NC program, the machining quality information regarding machining quality after machining a workpiece.
  • 5. An NC machining system according to claim 4, wherein the machining quality information includes required tolerance information.
  • 6. An NC machining system according to claim 4, wherein the machining quality information includes required surface roughness information.
  • 7. An NC machining apparatus comprising:means for producing a measurement program for measuring machining quality of a workpiece machined by a machine tool using a measuring machine through analyzing an NC program for carrying out machining control of a machine tool for a workpiece; a measuring machine for measuring machining quality of a workpiece using the produced measurement program; and means for judging machining quality of the workpiece by comparing the measurement results of machining quality of the workpiece measured by the measuring machine and required machining quality information included in the NC program, the machining quality information regarding machining quality after machining a workpiece.
  • 8. An NC machining system according to claim 4, further comprising the step of:determining a traveling path of a measuring probe of the measuring machine.
PCT Information
Filing Document Filing Date Country Kind
PCT/JP99/03618 WO 00
Publishing Document Publishing Date Country Kind
WO01/02914 1/11/2001 WO A
US Referenced Citations (13)
Number Name Date Kind
4977531 Ogata et al. Dec 1990 A
5029068 Miyata et al. Jul 1991 A
5288209 Therrien et al. Feb 1994 A
5291393 Matsumoto et al. Mar 1994 A
5378218 Daimaru et al. Jan 1995 A
5552688 Haga Sep 1996 A
5608641 Guhl et al. Mar 1997 A
5827020 Fujita et al. Oct 1998 A
6397123 Miyajima et al. May 2002 B1
6400998 Yamazaki et al. Jun 2002 B1
6401004 Yamazaki et al. Jun 2002 B1
6415191 Pryor Jul 2002 B1
6493594 Kraml Dec 2002 B1
Foreign Referenced Citations (4)
Number Date Country
4-138504 May 1992 JP
5-92349 Apr 1993 JP
10-258372 Sep 1998 JP
WO 9819821 May 1998 WO