Claims
- 1. A method for operating a casting and rolling plant with at least one slab production line, at least one rolling mill train, and at least one slab feed device, which in manufacturing terms is independent of the slab production line, comprising the step of:
during a pause in production of the slab production line, the slab feed device takes over the supply of slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 2. The method as claimed in claim 1, wherein the slab feed device of the casting and rolling plant receives its slabs from a further slab production line which, together with the slab feed device, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 3. The method as claimed in claim 1, wherein the slab production line of the casting and rolling plant is designed as a thin-slab production line.
- 4. The method as claimed in claim 2, wherein the further slab production line is designed as a thick-slab production line which, together with the slab production line, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 5. The method as claimed in claim 1, wherein the slab feed device of the casting and rolling plant receives its slabs from a slab store in which prefabricated slabs are temporarily stored for manufacturing purposes.
- 6. A method for operating a casting and rolling plant comprising the steps of:
providing at least one slab production line, providing at least one rolling mill train, providing at least one slab feed device, which in manufacturing terms is independent of the slab production line, and during a pause in production of the slab production line, taking over the supply of slabs to the rolling mill train by the slab feed device to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 7. The method as claimed in claim 6, wherein the slab feed device of the casting and rolling plant receives its slabs from a further slab production line which, together with the slab feed device, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 8. The method as claimed in claim 6, wherein the slab production line of the casting and rolling plant is designed as a thin-slab production line.
- 9. The method as claimed in claim 7, wherein the further slab production line is designed as a thick-slab production line which, together with the slab production line, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 10. The method as claimed in claim 6, wherein the slab feed device of the casting and rolling plant receives its slabs from a slab store in which prefabricated slabs are temporarily stored for manufacturing purposes.
- 11. A casting and rolling plant comprising:
at least one slab production line, at least one rolling mill train, at least one slab feed device, which in manufacturing terms is independent of the slab production line, and wherein the slab feed device comprises means that during a pause in production of the slab production line, take over the supply of slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 12. The plant as claimed in claim 11, further comprising a further slab production line, wherein the slab feed device of the casting and rolling plant receives its slabs from the further slab production line which, together with the slab feed device, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 13. The plant as claimed in claim 11, wherein the slab production line of the casting and rolling plant is designed as a thin-slab production line.
- 14. The plant as claimed in claim 12, wherein the further slab production line is designed as a thick-slab production line which, together with the slab production line, is responsible for supplying slabs to the rolling mill train to the maximum feasible extent in accordance with logistical and/or production engineering stipulations.
- 15. The plant as claimed in claim 11, wherein the slab feed device of the casting and rolling plant receives its slabs from a slab store in which prefabricated slabs are temporarily stored for manufacturing purposes.
Priority Claims (1)
Number |
Date |
Country |
Kind |
10109223.7 |
Feb 2001 |
DE |
|
CROSS REFERENCE TO RELATED APPLICATION
[0001] This application is a continuation of copending International Application No. PCT/DE02/00612 filed Feb. 20, 2002 and claiming a priority date of Feb. 26, 2001, which designates the United States.
Continuations (1)
|
Number |
Date |
Country |
Parent |
PCT/DE02/00612 |
Feb 2002 |
US |
Child |
10648574 |
Aug 2003 |
US |