Method for producing concrete prefinished parts

Abstract
There is provided a process for producing precast concrete parts, in particular pylon segments. Concrete is poured into a casting mold with a planar bottom for producing a planar underside. After the concrete has reached at least a minimum strength an equalization layer is applied to a join surface of the precast concrete part that is opposite to the underside. As soon as the equalization layer has reached the minimum strength, the precast concrete part is placed on a horizontally oriented surface and the equalization layer on the top side is removed in a plane-parallel relationship with the underside.
Description
BACKGROUND

1. Technical Field


The present disclosure concerns a process for producing precast concrete parts, a precast concrete part and a wind power installation.


2. Description of the Related Art


When constructing high towers or pylons based on prefabricated segment parts or precast concrete parts, it can happen, because of production tolerances, that precast concrete parts which have to be placed one upon the other do not fit together in the optimum fashion.


To avoid that problem typically an equalization layer, for example mortar, is applied on the building site to a join surface or a flange of a precast concrete part, in which case that equalization layer must then harden on the building site, that is to say it must attain a minimum strength. That requires, inter alia, compliance with minimum meteorological demands which are dependent on the material of the equalization layer. If those minimum demands are not met or if the equalization layer is incorrectly applied then there is the risk of flaws or inadequate setting and so forth.


DE 101 33 607 A1 describes a process for the production of a precise precast concrete part.


BRIEF SUMMARY

In accordance with one aspect of the present disclosure a process is provided for producing precast concrete parts, which permits easier and faster erection of a pylon or tower from the precast concrete parts, with a quality that remains consistently high.


In accordance with another aspect of the present disclosure, a process for producing precast concrete parts in pylon segments is provided. The process includes casting concrete into a casting mold that has a planar floor for producing a planar underside; hardening the concrete to obtain a precast concrete part having a minimum strength; applying an equalization layer to a join surface that is opposite to the planar underside of the precast concrete part; placing the precast concrete part on a horizontal plane; and removing the equalization layer so that the join surface is in a plane-parallel relationship to the planar underside of the precast concrete part. In accordance with another aspect of the present disclosure, a process for producing precast concrete parts is provided. Concrete is cast in a casting mold with a planar floor to provide a planar underside. As soon as the concrete has reached a minimum strength and a precast concrete part of predetermined maximum strength is obtained an equalization layer is applied to a join surface of a hardened precast concrete part, that is opposite to the underside. The precast concrete part with its minimum strength is placed on a horizontal plane and the equalization layer is removed in plane-parallel relationship.


The prefabricated concrete parts can be pylon segments or parts of pylon segments.


In an aspect of the present disclosure, the equalization layer has synthetic resin.


In a further aspect of the present disclosure, removal of the equalization layer is effected by a milling unit having a displacement unit for displacement of the milling unit in the X-, Y- and Z-directions.


In a further aspect of the present disclosure a plurality of precast concrete parts which have hardened or which are of a minimum strength are arranged with an equalization layer on their respective join surface opposite to the underside on a horizontal plane and the equalization layers are machined in plane-parallel relationship by means of a milling unit.


The present disclosure also concerns a precast concrete part which has been produced as described hereinbefore. The present disclosure also concerns a pylon, in particular of a wind power installation, which has been erected with a plurality of the above-described precast concrete parts.


The present disclosure also concerns a wind power installation having an above-described pylon.


The present disclosure concerns the notion of providing precast concrete parts which are previously produced in a factory. In that case the precast concrete parts are produced in plane-parallel configuration in the factory. For that purpose the casting mold of the precast concrete part is arranged horizontally. In that situation the bottom of the casting mold is machined flat so that in the casting operation a flat underside is produced on the precast part, when for example concrete is introduced into the casting mold and remains in the mold until it has reached a minimum strength.


Then an equalization layer for example in the form of a synthetic resin is applied to the side of the precast concrete part that is opposite to the flat underside. As soon as the equalization layer has in turn reached a minimum strength the equalization layer is removed in a plane-parallel relationship so that the side of the precast concrete part that is opposite to the flat underside is in a plane-parallel relationship with the flat underside of the precast part. The precast concrete parts can then be transported to a building site.


As the precast concrete parts already leave the factory with plane-parallel join surfaces there is no need for post-treatment of the precast concrete parts on the building site. The precast concrete parts can thus be assembled to constitute a pylon without delay. In particular the step of applying an equalization material is omitted, and as a result, besides eliminating possible sources of error, the operating procedure on the building site is also accelerated and to a large extent made independent of the weather. The process according to the present disclosure provides a uniform quality for the precast concrete parts as complete production takes place in the factory under controlled conditions with quality assurance. In particular construction of the precast concrete parts to form a pylon can take place more quickly as there is no longer any need for any post-treatment operation or application of an equalization layer on the building site.


Further configurations of the present disclosure are subject-matter of the included claims.





BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS

Embodiments by way of example and advantages of the present disclosure are described more fully hereinafter with reference to the drawing.



FIG. 1 shows a diagrammatic perspective view of a precast concrete part and a removal unit in a first embodiment;



FIG. 2 shows a perspective view of a precast concrete part and a removal unit in the first embodiment;



FIG. 3 shows a perspective detail view of FIG. 2;



FIG. 4 shows a further perspective view of precast concrete parts and the removal unit in accordance with the first embodiment;



FIG. 5 shows a perspective view of a detail portion of FIG. 4; and



FIG. 6 shows a perspective view of a pylon in the construction phase in accordance with a second embodiment.





DETAILED DESCRIPTION


FIG. 1 shows a perspective view of a precast concrete part and a removal unit in accordance with the first embodiment. The precast concrete part 100 has a join surface or a flange 110, to which an equalization layer 500 is applied. In the first embodiment the removal unit 200 is in the form of a milling unit having a milling head 210 and a displacement unit 220. The displacement unit 220 has a Z-displacement unit 221 for displacement in the Z-direction, an X-displacement unit 222 for displacement in the X-direction and a Y-displacement unit 223 for displacement in the Y-direction. The milling head 210 can be accurately controlled by the X-, Y- and Z-displacement units so that the milling head 210 can remove the equalization layer 500 on the join surface or the flange 110 of the precast concrete part 100 in that way as soon as the equalization layer has reached a minimum strength required for the mechanical processing operation so that the join surface or the flange 110 is plane-parallel.


The equalization layer is preferably synthetic resin such as for example epoxy resin and is applied to the join surface 110 of the precast concrete part 100. After the equalization layer has reached a minimum strength it is then removed in plane-parallel relationship by means of the milling unit 200. Those working steps are preferably performed in a factory under defined conditions. That can thus reproduce desired quality.


After the conclusion of the removal operation the equalization layer can be of a layer thickness of 1 to 5 millimeters.



FIG. 2 shows a perspective view of a precast concrete part and a removal unit in accordance with the first embodiment. In this case the precast concrete part 100 is standing on a floor 300 which is oriented horizontal. The removal unit or the milling unit 200 has an X-displacement unit 222, a Y-displacement unit 223 and a Z-displacement unit 221. The Y-displacement unit 223 has two rails, along which a carriage of the milling unit 200 is movable. The X-displacement unit 222 has a rail which extends between the rails of the Y-displacement unit 223 and along which the milling head 210 is movable. The milling head 210 is coupled to the Z-displacement unit 221, by which the milling cutter can be adjusted in the Z-direction, that is to say vertically.



FIG. 3 shows a perspective view of a detail portion of FIG. 2. This Figure shows the X-displacement unit 222, the Z-displacement unit 221 and the milling head 210. In this case the milling head 210 removes an equalization layer 500 to a predetermined amount. As the precast part segment is standing on a flat floor, removal of the equalization material by the milling head 210, with the Z-setting remaining the same with respect to the floor, results in a plane-parallel flange or a plane-parallel join surface which is to be found on the top side 110 of the precast concrete part 100.



FIG. 4 shows a further perspective view of a plurality of precast concrete parts and a removal unit similar to the precast concrete part and removal unit shown in FIG. 2, except that FIG. 4 shows a plurality of precast concrete parts which have been placed in part one within the other. The numerals shown in FIG. 4 correspond to like numerals as shown in previous FIGS. 1-3. The plurality of precast concrete parts that are placed in part one within the other allows for a reasonable and fast removal operation. The precast concrete parts can represent complete segments or segment portions. All precast parts are processed in plane-parallel relationship at the same time by virtue of the horizontally oriented flat plane 300.



FIG. 5 shows a perspective view of a detail in FIG. 4.


In accordance with the first embodiment of the present disclosure plane-parallel removal of the equalization layer is already effected in the factory. The casting mold in which for example the concrete is cast makes it possible that the underside is of a planar configuration. That is a preferred prerequisite for plane-parallel processing of the oppositely disposed join surface or the oppositely disposed flange.



FIG. 6 shows a perspective view of a structure of a pylon comprising segments in accordance with the second embodiment. FIG. 6 shows a crane 400 with rigging portion 410. The crane 400 and rigging portion 410 as shown place a pylon storey portion comprising a plurality of precast concrete parts 100 on two pylon storey portions which have already been set in place and which have already been set up. In this case the precast concrete parts 100 in accordance with the second embodiment correspond to the precast concrete parts of the first embodiment.


It is thus possible to have a uniformly high quality for the precast concrete parts, wherein the bottom and the join surface or the flange of the precast concrete parts are in plane-parallel relationship with each other so that no further equalization layer has to be provided on the building site between two precast concrete parts, but the parts can be placed in a mutually fitting relationship in a mutually superposed relationship.


In a further embodiment of the present disclosure the precast parts can be lowered into the ground. For that purpose there can be provided for example a lifting platform which can be moved downwardly or which can be lowered into the ground. That is particularly advantageous because in that case no complicated and expensive X-, Y- and Z-displacement unit has to be used. In that way the displacement unit and the milling unit can be smaller. Optionally the displacement units and the milling unit can be adapted to be displaceable so that the precast parts which are to be milled or which have been milled can be placed on and removed from the lifting platform.

Claims
  • 1. A process for producing precast concrete pylon wall segments for a wind power installation pylon, each concrete pylon wall segment having a first end and a second end opposite the first end, the process comprising: casting concrete into a casting mold that has a planar floor to produce a concrete pylon wall segment having a planar underside at the first end;hardening the concrete to a predetermined minimum strength to obtain a precast concrete part having the predetermined minimum strength;applying an equalization layer to a join surface at the second end of the precast concrete pylon wall segment that is opposite to the planar underside of the precast concrete pylon wall segment at the first end;placing the precast concrete pylon wall segment of predetermined minimum strength on a horizontal plane; andremoving at least a portion of the equalization layer on the second end of the concrete pylon wall segment until the second end of the concrete pylon wall segment is plane-parallel to the first end so that the first and second ends of the concrete pylon wall segment are plane-parallel to each other.
  • 2. The process according to claim 1, wherein the equalization layer includes synthetic resin.
  • 3. The process according to claim 1, wherein removal of the equalization layer is effected by a milling unit having a displacement unit for displacement of the milling unit.
  • 4. The process according to claim 1 wherein a plurality of precast concrete pylon wall segments of predetermined minimum strength having a respective equalization layer on one end thereof are arranged on the horizontal plane and wherein the equalization layers are processed in plane-parallel relationship to the horizontal plane by a milling unit.
Priority Claims (1)
Number Date Country Kind
10 2008 016 828 Apr 2008 DE national
PCT Information
Filing Document Filing Date Country Kind 371c Date
PCT/EP2009/002374 4/1/2009 WO 00 12/6/2010
Publishing Document Publishing Date Country Kind
WO2009/121581 10/8/2009 WO A
US Referenced Citations (33)
Number Name Date Kind
1567301 Ross Dec 1925 A
1723216 Stam Aug 1929 A
2064791 Faber Dec 1936 A
2130911 Teunon Sep 1938 A
2413268 Unverferth Dec 1946 A
2756479 Garneau Jul 1956 A
2826800 Van Buren Mar 1958 A
3180570 Grabowski Apr 1965 A
3504500 Fristedt Apr 1970 A
3606666 Briggs, Jr. Sep 1971 A
3666606 Stokes May 1972 A
3721056 Toan Mar 1973 A
3967421 Dufossez Jul 1976 A
3977137 Patry Aug 1976 A
4272929 Hanson Jun 1981 A
4333660 Cupit Jun 1982 A
4386172 Yoshioka et al. May 1983 A
4890420 Azimi Jan 1990 A
5029879 Strang, Sr. et al. Jul 1991 A
5176408 Pedersen Jan 1993 A
5555697 Kim Sep 1996 A
5666774 Commins Sep 1997 A
5771518 Roberts Jun 1998 A
5860256 Humber Jan 1999 A
5934035 Rasmussen et al. Aug 1999 A
5944323 Cavka Aug 1999 A
6185885 Thaler Feb 2001 B1
6381912 Sorkin May 2002 B1
6389764 Stubler et al. May 2002 B1
7114295 Wobben Oct 2006 B2
7752825 Wobben Jul 2010 B2
20060254168 Wobben Nov 2006 A1
20110107708 Holscher May 2011 A1
Foreign Referenced Citations (35)
Number Date Country
1038743 Sep 1958 DE
6905988 Jul 1969 DE
4216367 Nov 1993 DE
29809541 Nov 1999 DE
19823650 Dec 1999 DE
19841047 Jan 2000 DE
10133607 Aug 2002 DE
10349155 May 2005 DE
202010000169 Jun 2010 DE
1249458 Nov 1959 FR
2775492 Sep 1999 FR
2783266 Mar 2000 FR
1349292 Apr 1974 GB
50133652 Oct 1975 JP
6015518 Feb 1985 JP
1147005 Oct 1989 JP
4118266 Oct 1992 JP
5346052 Dec 1993 JP
6101348 Apr 1994 JP
634014 May 1994 JP
08-323729 Dec 1996 JP
10205428 Aug 1998 JP
11029911 Feb 1999 JP
11172964 Jun 1999 JP
2000-283019 Oct 2000 JP
2001062814 Mar 2001 JP
200341897 Feb 2003 JP
2003245848 Sep 2003 JP
2005-030066 Feb 2005 JP
2007321710 Dec 2007 JP
8602689 May 1986 WO
9943910 Sep 1999 WO
0204766 Jan 2002 WO
2004007955 Jan 2004 WO
2009121581 Oct 2009 WO
Related Publications (1)
Number Date Country
20110107708 A1 May 2011 US