Claims
- 1. A method of drilling a shallow-water offshore well and reinforcing a well structure from a jack-up type drilling platform having a derrick and associated drilling and hoisting systems, said platform being of a design providing for the derrick to be moved laterally on the platform within a prescribed work area so that the center line of the derrick is positioned over open water to one side of the platform, said method comprising the steps of:
- (a) drilling and completing the well by steps comprising:
- (1) locating the jack-up type drilling platform at a selected shallow-water drilling location with its leg footings on the ocean floor and its operating deck jacked-up to normal operating position above the water surface and wave action;
- (2) lowering a large-diameter well conductor through the water below the derrick and setting it in the ocean floor;
- (3) drilling a well through said well conductor and closing the top of the well with a wellhead above the water surface and wave action;
- (b) establishing an interconnecting reinforcing structure in which said well conductor and a plurality of piles form legs of the structure, comprising:
- (1) providing a pile guide template frame substantially polygonal in plan view comprising at least two spaced-apart vertical pile guides connected together by laterally-extending support members with additional laterally-extending support members arranged to extend between and be connected at one end to each of the pile guides and at the other end to the well conductor when positioned thereagainst, with the pile guides being at a selected distance from the well conductor;
- (2) transporting the pile guide template frame to the offshore well;
- (3) positioning and suspending said frame in a manner such that the other ends of the additional laterally-extending support members are operatively positioned adjacent the wall of said well conductor, said position being such that at least said other ends of said support members at the top of the frame are above the surface of the water and the lowermost portion of the frame does not rest upon the ocean floor;
- (4) lowering the piles through said pile guides of said suspended frame and driving said piles into the ocean floor;
- (5) securing the suspended pile guide template frame above the ocean floor by fixedly connecting each pile to its surrounding pile guide; and
- (6) operatively connecting at least said other ends of said laterally-extending support members at the top of the frame to the well conductor, whereby said frame forms the interconnecting reinforcing structure between the piles and the well conductor, substantially polygonal in plan view, to resist the effect of wind and wave forces encountered by said well conductor.
- 2. The method of claim 1 further comprising:
- providing a work platform at the base of said wellhead; and
- fixedly securing said work platform to at least said well conductor.
- 3. The method of claim 2 further comprising:
- providing a helicopter pad and a depending support frame; and
- fixedly securing said helicopter pad support frame to at least said work platform.
- 4. The method of claim 1 wherein the operation carried out in step b(6) is accomplished by providing a sliding connection permitting limited movement between the well conductor and the reinforcing frame.
- 5. The method of claim 1 wherein in step b(3) the frame is positioned by hanging it from the jack-up drilling platform beneath the derrick thereof while the pile guides are vertically-aligned in spaced relationship with said well conductor.
- 6. The method of claim 1 wherein between steps b(3) and b(4) the derrick is moved laterally on said drilling platform so that the travelling block of the hoist system is vertically aligned with said pile guides, one at a time, and further comprising:
- the step of connecting the derrick hoist system to one end of a pile to raise it within the derrick and lower it through a pile guide of said frame.
- 7. The method of claim 1 wherein between steps b(3) and b(4) at least the other ends of said support members at the top of the frame are connected to the well conductor by welding.
- 8. The method of claim 1 wherein each of said piles is connected to its pile guides by grouting.
- 9. The method of claim 1 wherein in step b(1) the dimensions of the pile guide template frame together with that of the well conductor, when taken in cross-sectional plan view, are small, less than that of a slot of a jack-up platform.
- 10. The method of claim 9 including the steps of lowering the jack-up platform of the water surface, comprising:
- retracting the leg footings to the travelling position; and
- moving the platform on the water in a direction such that the well conductor and the adjacent piles move out the open end of the platform slot.
- 11. The method of claim 1 wherein the jack-up drilling platform is provided with a drilling slot extending inwardly from the outer edge of the platform deck with the derrick and its hoist system spanning the drilling slot and being moveably positionable laterally so that the derrick hoist system may be moved to selected locations along at least portions of the width and length of the drilling slot, including the steps of:
- moving said derrick laterally to a position such that the derrick hoist system is above a vertical pile guide of said frame;
- picking up a length of pile with said derrick hoist system prior to lowering it through said pile guide as per step b(4), and, after driving the pile in the ocean floor; and
- repositioning said derrick and said hoist system to a position above another pile guide and repeating the pile installation operation.
Parent Case Info
This is a continuation of application Ser. No. 936,220, filed Dec. 1, 1986 now abandoned.
US Referenced Citations (17)
Foreign Referenced Citations (6)
Number |
Date |
Country |
019808 |
Feb 1985 |
JPX |
208513 |
Oct 1985 |
JPX |
8401934 |
Jan 1986 |
NLX |
628232 |
Oct 1978 |
SUX |
1563107 |
Mar 1980 |
GBX |
2153886 |
Aug 1985 |
GBX |
Continuations (1)
|
Number |
Date |
Country |
Parent |
936220 |
Dec 1986 |
|