Claims
- 1. A method for the production of heavy oil from a shallow subterranean tar sand bed penetrated by at least one injection well and at least one spaced apart production well, comprising:
- (a) forming a plurality of horizontal fractures spanning the distance between said injection well and said production well, said fractures being spaced apart in a vertical direction with respect to each other throughout the depth of the tar sand bed;
- (b) injecting a solvent for the heavy oil into said fractures via said injection well;
- (c) shutting in said injection well and said production well for a predetermined period of time to form a heavy oil/solvent mixture of reduced viscosity by gravity-driven convective mixing;
- (d) collapsing said fractures via fluid injection at lower than reservoir overburden pressures.
- (e) recovering said heavy oil/solvent mixture from said tar sand bed; and
- 2. The method according to claim 1 which comprises additionally injecting steam into said fractures via said injection wells in step b.
Parent Case Info
This is a continuation of copending application Ser. No. 229,804, filed Jan. 30, 1981.
US Referenced Citations (9)
Foreign Referenced Citations (1)
Number |
Date |
Country |
1495722 |
Dec 1977 |
GBX |
Continuations (1)
|
Number |
Date |
Country |
Parent |
229804 |
Jan 1981 |
|