METHOD FOR RENEWAL OF A TRACK

Information

  • Patent Application
  • 20170121915
  • Publication Number
    20170121915
  • Date Filed
    May 22, 2015
    9 years ago
  • Date Published
    May 04, 2017
    7 years ago
Abstract
A method for renewal of a track includes picking up a plurality of old track panels using a crane jib projecting over the track from a train end of a work train and depositing the old track panels on the work train, thus creating a renewal gap delimited by a gap beginning and a gap end. New ballast is introduced with the aid of the crane jib into the gap end of the renewal gap. Subsequently, a new track panel pre-deposited on the work train is placed by the crane jib on the graded ballast of the gap end. A work train for renewal of a track is also provided.
Description

The invention relates to a method for renewal of a track, wherein old track panels are removed by an on-track work train and ballast thus exposed is renewed on which, after grading, new track panels are placed. The invention also relates to a work train for renewal of a track.


EP 0 108 168 B1 discloses a work train having a gantry crane for the transport of track panels.


According to U.S. Pat. No. 4,502,389, a work train is also known which has devices for the transport of track panels and ballast.


It is the object of the present invention to provide a method or a work train with which a simplified track renewal is possible.


According to the invention, this object is achieved with a method or work train of the specified type by way of the features cited in the characterizing part of claim 1 or 3, respectively.


By means of this solution according to the invention, a simplified renewal of a track section can be carried out with relatively little structural expense.


Additional advantages of the invention become apparent from the dependent claims and the drawing description.





The invention will be described in more detail below with reference to an embodiment represented in the drawing in which FIGS. 1 and 2 show a side view of the front or rear section, respectively, of a work train for renewal of a track.





A work train 1, shown in FIGS. 1 and 2, is composed of a number of loading cars 3, arranged one following the other with regard to a longitudinal direction 2 of the train, which are equipped with crane rails 4 for mobility of a gantry crane 5 and with loading areas 6.


The gantry crane 5—having two crane ends 7,8 spaced from one another in the longitudinal direction 2 of the train—is equipped with a crane jib 9. The latter has a first end 10 fastened in a pivotable manner to one of the two crane ends 7,8 and, at a further, second end 11 spaced from the gantry crane 5 in the longitudinal direction 2 of the train, comprises a gripping device 12 for grasping track panels 13.


Arranged at the first end 7 of the gantry crane 5 are vertically adjustable supporting devices 14 for support on a track 15. At the second end 8 of the gantry crane 5, counterweights 16 and gripping devices 17 are provided. The latter are designed to be pivotable perpendicularly to the longitudinal direction 2 of the train for form-locking connection—with regard to avertical—to the crane rails 4.


New ballast 19 is pre-deposited in a number of containers 18 placed on the loading area 6 of a loading car 3. Situated on an adjoining loading car 3 are new track panels 13 stacked one upon the other. The adjacent loading car 3 is provided for depositing old track panels 13.


The method, according to the invention, for renewing the track 15 will now be described in more detail.


At the beginning of operations, the gantry crane 5 is moved to a train end 22, so that the crane jib 9 projects from the work train 1 over the track 15. By means of the crane jib 9 which is vertically adjustable by drives 23 and transversely pivotable, an old track panel 13 is seized by the gripping device 12, picked up and placed on the work train 1, or rather on the loading car 3 provided for that purpose, thus creating a renewal gap 26 delimited by a gap beginning 24 and a gap end 25.


Prior to lifting up the track panel 13, the supporting device 14 is rested on the track 15. Parallel to that, the gripping devices 17 are applied to the crane rails 4 in order to avoid a tilting of the gantry crane 5. This procedure of removing old track panels 13 is continued as desired until the renewal gap 26 has a chosen length. In the meantime, the removal of the old ballast takes place in the trackless renewal gap 26, for example by means of a two-way excavator.


After the renewal gap 26 has reached a desired maximum length, new ballast 19 pre-deposited on the work train 1 is introduced with the aid of the crane jib 9 into the gap end 25 of the renewal gap 26. For that purpose, a container 18 is seized by the gripping device 12 of the crane jib 9 and opened above the renewal gap 26 for evacuation. The discharged ballast 19 is graded by the already mentioned excavator.


As soon as the new ballast 19 has been graded for the length of a track panel, a new track panel 13 pre-deposited on the work train 1 is laid down upon the ballast 19 of the gap end 25 by means of the crane jib 9.


Subsequently, the work train 1 is moved on the new track panel 13 in the direction towards the renewal gap 26, after which the introduction of ballast and the subsequent placement of a new track panel 13 is repeated in the just described manner until the track 15 has been completely renewed in the area of the renewal gap 26.


Adjacent to the now eliminated renewal gap 26, the described method steps are repeated in that, by removal of old track panels, another new track gap 26 is created which is again closed step-by-step by new track panels for renewing the track 15.

Claims
  • 1-5. (canceled)
  • 6. A method for renewal of a track, the method comprising the following steps: a) picking up a plurality of old track panels by using a crane jib projecting over a track from a train end of an on-track work train, and placing the old track panels on the work train, to create a renewal gap delimited by a gap beginning and a gap end and to expose ballast;b) after the renewal gap has reached a desired maximum length, using the crane jib to introducing new ballast pre-deposited on the work train into the gap end of the renewal gap and grading the ballast;c) placing a new track panel pre-deposited on the work train upon the graded ballast at the gap end by using the crane jib; andd) moving the work train on the new track panel in a direction towards the renewal gap, and then repeating the introduction of ballast and the subsequent placement of a new track panel according to steps b) and c) until reaching the gap beginning.
  • 7. The method according to claim 6, which further comprises carrying out the step of introducing the new ballast using the crane jib by using containers to be emptied above the renewal gap.
  • 8. A work train for renewal of a track, the work train comprising: loading areas on the work train for storing old and new track panels;crane rails disposed on the work train;a gantry crane being movable on said crane rails in a longitudinal direction of the work train for transporting the track panels, said gantry crane having first and second crane ends being spaced from one another in the longitudinal direction of the work train;a crane jib having a first end pivotably fastened to said first crane end and a second end spaced from said gantry crane in the longitudinal direction of the work train;a panel gripping device disposed at said second end of said crane jib for seizing track panels; andvertically adjustable supporting devices disposed at said first crane end for supporting said gantry crane on the track.
  • 9. The work train according to claim 8, which further comprises counterweights disposed at said second crane end of said gantry crane.
  • 10. The work train according to claim 8, which further comprises rail gripping devices disposed at said second crane end of said gantry crane and being pivotable perpendicularly to the longitudinal direction of the work train, said rail gripping devices form-locking connecting said gantry crane to said crane rails in a vertical direction.
Priority Claims (1)
Number Date Country Kind
A 496/2014 Jun 2014 AT national
PCT Information
Filing Document Filing Date Country Kind
PCT/EP2015/001060 5/22/2015 WO 00