The present invention relates to a method for the assembly of frustoconical concrete towers which allows the use of low-capacity cranes, wherein a substructure is generated from the union of at least two of the segments that form each section so that said substructure is freestanding.
The invention further relates to a concrete tower assembled according the preceding method.
In the last twenty years the rated power of wind turbines has gradually increased by enlarging the diameter of their rotors, which in turn need taller towers. The increased height may imply that the tower should essentially comprise several sections throughout its entire height, placed one on top of the other to form the tower and which are in turn transportable by road or rail. For example, to build an 100 m-high tower, 5 20 m-sections stacked on top of each other may be used, such dimensions being transportable by road and rail.
Moreover, to ensure that the towers, although higher, are equally stable and rigid, one option is to increase the transverse dimensions of the tower gradually from the top to the base of the tower. This increase may involve new problems for the transportation of the sections and a common solution is to divide them into longitudinal modules. The dimensions of the longitudinal modules allow their transport by road or rail.
Logically, increasing the rated power of the wind turbines leads to an increase in weight and dimensions of all wind turbine components in general, so the following aspects are particularly relevant in connection with assembly costs:
Specifically, the weights of the full tower sections of a 3 MW wind turbine can exceed 200 t which places high requirements on assembly cranes.
The use of these cranes is expensive, first, because of availability problems entailing high daily rental costs: there is no large park of such cranes; and second, the high costs associated with their transport due to the large number of trucks required to move them. According to data shown in U.S. Pat. No. 8,011,098B2, the cost of renting a crane for tower assembly can amount to $ 80,000 per week, plus nearly $100,000 for transport (forty trucks or more).
Such high costs justify the pursuit of alternative means to build wind turbine towers. Various procedures that can be followed for the assembly of these towers include:
An object of the present invention is to provide a method of assembling concrete towers which reduces crane requirements for the first procedure, while simplifying the overall assembly process with respect to the second procedure.
Furthermore, the prior art shows that the concrete tower is often a conical section tower, particularly frustoconical to withstand the high torque in the base. Furthermore, in some tower designs segment height is much greater than tower height. This means that when the tower is conical, the segments are unstable when placed upright, because the horizontal projection of the centre of gravity is outside of the perimeter defined by the base of the segment.
These drawbacks are solved with the invention described below.
The present invention relates to a method for the assembly frustoconical concrete towers wherein subsets of sections are assembled and stacked on the rest of the tower, the said subsets being freestanding.
The invention also relates to a concrete tower obtained with the assembly method described below and which comprises at least two stacked annular sections in turn comprising at least three segments.
The frustoconical concrete tower assembly method comprises the following steps:
If the sections are solely formed by freestanding subsets, the preceding steps are repeated until all freestanding subsets forming all the sections of the concrete tower have been stacked.
If the sections are formed by freestanding subsets and remaining segments to complete the section of the concrete tower, the remaining segments also need to be stacked for each of the sections of the concrete tower.
Furthermore, to ensure adequate dimensional accuracy of the sections, the step of placing and positioning of at least one subset of a tower section comprises the following steps prior to the subset assembly step:
In addition, to ensure the same position as that achieved after the positioning step performed in the area near the base of the tower at ground level, of the remaining segments of the section that are not part of the subset relative to said subset, or of subsets relative to each other, once stacked, the method comprises, prior to the step of subset stacking and subsequent to the step of positioning each of the segments that form the tower section:
The method further comprises a step of provisional attachment between subsets or remaining segments and the lower section of the concrete tower once the step of stacking the assembled subset has been carried out and subsequent to the stage of control of relative positioning between segments described above.
The provisional attachment step is performed by means of temporary connections that can be executed by a three-point mooring of the surface in contact with the lower surface at the height of the horizontal joint defined between them or by means of struts to the area opposite the lower section.
The method further comprises a step of execution of the permanent connections between subsets, or between subsets and remaining segments, which takes place once completed the stacking of all subsets and remaining segments forming each section of concrete tower, which speeds up installation.
In a preferred embodiment of the invention, the method for the assembly of frustoconical concrete towers comprises the following steps:
The attachment between two segments (1, 11) may be permanent or provisional.
If the attachment is permanent (6), according to a first embodiment shown in
If the attachment is provisional, according to a second preferred embodiment shown in
Because, due to manufacturing tolerances, there may be differences between segments (1, 11), the resulting upper surface is not always flat or horizontal. In a preferred embodiment, the step of positioning the subset (4, 14) at height is performed by conducting a replica of the horizontal surface of the pre-assembly base (2, 12) on the upper surface of the immediately lower tower section prior to the step of stacking the assembled subset (4, 14), by means of shims placed in three points per subset (4, 14) and/or segment (1, 11), at predetermined angular positions which are the same for all sections, wherein said shims are fixed to the segments (1, 11), wherein verticality control wedges are placed in those same angular positions where the shims are placed. Therefore, the sum of the horizontal surface defined by the shims and that of the wedges makes it possible to replicate the position achieved in the pre-assembly base (2, 12), once subsets (4, 14) have been stacked.
Alternatively, when the subset (4, 14) is stacked, a check is made to verify that the centre of the subset (4, 14) coincides with the vertical axis of the tower, otherwise it is adjusted to match. Subsequently, the other subset (4) is stacked, for the case of two subsets (4) per section, or the remaining segments (11), and the following step to control relative positioning between segments is implemented:
The first of the subsets (4, 14) to be stacked will be the one incorporating a flight of steps required to access the upper part of the subset (4, 14) and thereby allow removal of the hook from a crane used to lift said subset (4, 14).
The steps of assembling and stacking the assembled subset (4) are repeated as many times for each of the sections forming the concrete tower, as number of subsets (4) in the section in the event that this section is formed by subsets (4) in which permanent attachment (6) has been carried out between segments (1) prior to stacking, as shown in
Subsequent to the step of stacking each of the subsets (4) of the section, the method comprises a step of attachment performed between the section subsets (4), for the embodiment shown in
Such provisional attachment elements (5, 15) between subsets (4), or subsets (14) and remaining segments (11) may include lugs and hydraulic jacks arranged in accessible areas of the subsets (4), or of the subsets (14) and the remaining segments (11), at least one in the upper area of the section such that it is accessible from the top.
Subsequent to the step of attachment performed between the subset (14) of the section and the remaining segments (11) of the section by arranging provisional attachment elements (15) for the embodiment shown in
The method further comprises a step of executing permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining segments (11), which are performed once all subsets (4, 14) and segments (11) which form all the sections of the concrete tower have been stacked and ensuring the proper positioning between them.
The method further comprises a step of provisional attachment between subsets or remaining segments and the lower section of the concrete tower once the step of stacking the assembled subset has been carried out.
The provisional attachment step is performed by means of provisional attachments that can be executed by mooring (20) at three points of the surface in contact with the lower surface at the height of the horizontal joint defined between them or with struts (21) taken to the opposite side of the lower section.
Preferably each of the sections is angularly staggered with respect to the lower section so that the permanent attachments (6, 16) do not run in a continuous line along the tower, improving the stability thereof.
Said step of executing the permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining segments (11), comprises a step of performing vertical concrete joints. In order that the mortar used in the vertical concrete joints is confined within an enclosed cavity, preassembled sealant elements or inflatable elements are placed along the vertical concrete joints as a formwork.
In turn, so that the mortar does not flow towards the horizontal joint between the sections, covers which inferiorly seal the vertical joints are arranged prior to the assembly of the upper section.
Preferably, the step of executing the permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining segments (11) is performed once a nacelle (7) of the wind turbine has been mounted.
Preferably, the method further comprises a step of executing permanent attachments (8, 18) between adjacent sections, which is performed subsequent to the step of executing permanent attachments (6, 16) between subsets (4), or between subsets (14) and the remaining segments (11), and more preferably, the step of executing the permanent attachments (8, 18) between adjacent sections is carried out from the highest section to the lowest section of the tower, wherein this step of execution of a permanent attachments (8, 18) between adjacent sections comprises a step of performing horizontal concrete joints.
Number | Date | Country | Kind |
---|---|---|---|
P201331892 | Dec 2013 | ES | national |