As its title suggests, this description refers to a foundation extension procedure, of the type used in the extension of large structures, and especially its use in the reinforcement of existing wind turbine farms, founded in the earth or onshore, also known as repowering, which uses an overlaid beams structure on the existing foundation and bonded to it, supported by new, smaller peripheral foundations, creating a new foundation capable of supporting a larger structure, which uses the old foundation as ballast.
This invention relates to the construction of foundations on existing foundations, especially for the repowering of wind turbines with foundations in the earth.
There are currently a large number of wind farms, many of them located in adequate regions for the production of electrical energy generated by the wind because of their environmental properties. These wind farms already count with infrastructures in place, such as roads or access paths, buried pipelines for power lines, and power lines and transformer stations to transport the electricity generated. The term “repowering” refers to all activities related to the use and optimisation of the wind turbine capacities in a wind farm with new equipment or components. In recent years, the development of wind turbines has undergone numerous technological advances. Today's wind turbines achieve efficiency levels of more than 98%, resulting in a significant increase in energy production, several times higher than that of wind turbines of a few years ago. They are also equipped with additional technical features such as wireless connection or intelligent algorithms to calculate the optimal operating point to increase the efficiency of the system. The third issue is the rapid increase in the installed power of each wind turbine, which has grown from 300-600 kW to 3.500 kW in 20 years.
This creates a demand to repower existing wind farms, replacing existing wind turbines by newer wind turbines, with new technologies, with an increased power and with higher energy production capabilities and bigger, which need a stronger foundation to withstand higher stresses.
In many cases, the repowering requires the dismantling of the wind turbines, the excavation and dismantling, demolition and complete removal of the previous foundation, an extremely expensive and time-consuming procedure, so that it was often decided to install the wind turbines elsewhere, leaving the previous site and causing great environmental impact.
To solve this situation and make use of the previous foundation, there are known procedures, such as those described in the patents ES-2493722 “Procedimiento de ejecución de un aerogenerador para repotenciar un parque eólico existente y aerogenerador obtenido”, KR20190101219 “Wind turbine Re-powering Foundation structures” and KR20200057954 “Wind turbine structure for retrofitting spread footing in partial repowering and construction method for the same”, which carry out a large excavation around the already existing foundation, and build a new foundation around and on top of it, using conventional methods, achieving a new, stronger foundation. This presents many disadvantages, mainly due to the large excavations and earthworks required, as well as the need to use a large amount of concrete and metal reinforcement or rebar, as well as a large cross-section. The connection of this rebar with the existing foundation is very manual, slow and expensive to execute and with a questionable quality guarantee. All this implies expensive costs and a long construction time. We must add that, for a correct harden, the concreting work must be done continuously, without interruptions, requiring a stable supply of a high volume of concrete, which in many regions or countries is difficult or impossible to obtain. Extreme temperature conditions, both cold and hot weather, e.g. in desert areas, complicate the harden of the concrete because of the chemical reaction, and many optimal wind energy sites are in forests or semi-deserts because of the strong thermal winds.
Another additional problem is that the necessary excavation requires the creation of ramps for the heavy machinery to excavate to such a great depth, increasing the working time. The bottom of the excavation also needs to be levelled and smoothed.
All this causes that the usual time for excavation, preparation, concreting and hardening takes several weeks, which, multiplied by the large number of wind turbines in each wind farm, results in very expensive costs.
There are some foundation types known because of their capability to solve some of the above-mentioned problems of large excavations, high volume of concrete and use of rebar, such as the one described in ES2764468 “Cimentación para torres eólicas”, which proposes the use of precast concrete beams combined with small basements, these beams being structurally bonded in the central part of the foundation by means of joining and supporting elements of the tower, but this presents the disadvantage that it is not foreseen nor is it possible to build on an existing foundation, nor to reuse it, and it also has the disadvantage of requiring in some cases the construction of a structure with ballast or weight functions, made on site with concrete in the area where the beams are joined.
In order to solve the existing problem of extending and enlarging foundations, especially in the case of repowering of existing onshore wind turbine farms, it has been developed the foundation extension procedure of the present invention, which uses a structure of beams overlaid on the existing foundation and joined to it, supported by new smaller peripheral foundations, creating a new foundation suitable for a larger structure, which uses the old foundation as a ballast in its central part.
For this purpose, the procedure comprises
The peripheral foundations phase and the dismantling phase of the elements of the old structure can be carried out in any order, or even simultaneously. Preferably, the peripheral foundations phase shall be carried out first, followed by the disassembly phase of the elements of the old structure, in order to reduce as much as possible the downtime of the old turbine in the case of wind turbines. The following phase of precast concrete beams assembly on the peripheral foundations and the existing foundation will always be carried out after the previous two phases.
After that, the new structure (such as for example, a wind turbine tower) will be placed on the anchorages provided in the new foundation.
The peripheral foundations will preferably be a multiple quantity of independent foundations, although it is foreseen that, alternatively, they may be joined together to form a single peripheral structure.
The phase of construction of peripheral foundations comprises preferably
The phase of precast concrete beams assembly on the peripheral foundations and the existing foundation and bonding with the existing foundation comprises
It is foreseen that the procedure may include an additional phase, to be carried out after the third or fourth phase, of setting precast concrete enclosures for auxiliary functions in the space among beams, under the height of the upper layer.
A final optional additional phase is also foreseen, of total or partial covering of the existing beams, concreted elements and enclosures or connection boxes, with the earth extracted from the excavation of the digs.
The preferred use of this foundation extension procedure is the repowering of wind farms, to replace a wind turbine with another more powerful and with higher production, without dismantling the previous foundation.
This foundation extension procedure provides multiple advantages over those currently available, the main one is that it allows a quick and economical assembly of a new, bigger and stronger foundation without the dismantling of the existing foundation, mounting the new structure or wind turbine exactly on the same location.
Another advantage is that, by mounting the new structure or wind turbine exactly on the same location, the existing infrastructure for the previous structure or wind turbine, such as access paths, power supply ducts, maintenance facilities, etc., can be reused, avoiding the need to rebuild them, with the consequent savings in construction times and costs.
It should be noted that this procedure can be carried out, if necessary, with the rest of the wind turbine park in operation, without compromising its production.
It should be also noted that the procedure described, by joining the central part of the beams to the existing foundations, uses it as ballast, avoiding the need to build other additional concrete structures, occasionally filled with ballast stone, to act as ballast and reducing the volume of material required in the new foundation.
It is important to highlight that there is a minimum environmental impact, both by reusing both the existing foundations and most of the complementary infrastructures in the case of wind turbines, and by avoiding the large excavations required in the ampliation of foundations to create a conventional foundation from an existing one, which is a common method nowadays.
Another important advantage is that this procedure makes easier the repowering of wind turbines, enabling the profits of the best sites for their location, which is where the old wind farms are located, replacing them with plants with larger wind turbines, with much more electricity production.
This achieves a new, larger and more resistant foundation, with a minimum environmental impact and completely integrated into the environment thanks to the possibility of reusing the earth from the digs to cover it, forming an artificial mound to minimise the visual impact.
Another of the most important advantages to be highlighted is that thanks to the use of a large number of precast concrete parts, the on-site work time is greatly reduced compared to conventional procedures.
Another advantage is that is foreseen the integration of precast concrete enclosures for auxiliary functions in the space among beams, under the height of the upper layer, enabling the solution to the problem of setting, in the case of wind turbines, new larger transformers required by the greater power of the new wind turbine.
One more advantage is that the use of small basement footings provides an enormous saving in both the amount of concrete and the amount of reinforcing steel used, which implies both a significant economic saving and the possibility of implementation in regions or countries with problems of supply or manufacture of concrete or reinforcing steel in such quantities.
As a consequence of the above mentioned, the problems of the supply demand of a large quantity of concrete continuously and uninterruptedly, characteristic in large conventional foundations for its correct hardening, can be avoided. It also allows the use of conventional, pre-assembled rebar reinforcement without the need for costly and specialised on site reinforcement prior to concreting.
Another important advantage is that the excavation required is much smaller in both volume and depth, without the need for ramps for the heavy machinery as is usual in the case of conventional foundations, that need several metres depth. This results in considerable time and cost savings.
Another advantage of the present invention is that, unlike conventional methods, the bottom of the footings does not need to be perfectly levelled and smoothed, which also results in additional savings in time and costs.
It should also be noted that this procedure allows the wind turbine tower to be raised to a height of 3 to 5 metres above its normal height, reaching greater heights without modifying the tower and therefore using better the wind resource, which means a greater energy generation.
Another of the most important advantages of the use of precast elements is that the overall construction time of the foundation is significantly reduced from the usual 3 to 4 weeks with the conventional methods to a maximum of 1 week.
For a better understanding of the purpose of the present invention, the annexed drawing shows a practical and preferred embodiment of a foundation extension process.
In this drawing,
The setting-up and features of the invention can be better understood with the following description made with reference to the attached drawings.
As can be seen in
The peripheral foundations (3, 4, 5) phase and the dismantling phase of the elements (1) of the old structure can be carried out in any order, or even simultaneously. Preferably, the peripheral foundations (3, 4, 5) phase shall be carried out first, followed by the disassembly phase of the elements (1) of the old structure, in order to reduce as much as possible the downtime of the old turbine in the case of wind turbines. The following phase of precast concrete beams assembly (9a, 9b, 9c) on the peripheral foundations (3, 4, 5) and the existing foundation (2) will always be carried out after the previous two phases.
After that, the new structure (such as for example, a wind turbine tower) will be placed on the anchorages provided.
The peripheral foundations (3, 4, 5) are preferably a multiple quantity of independent foundations, although it is foreseen that, alternatively, they may be joined together to form a single peripheral structure.
Preferably, the peripheral foundations (3, 4, 5) phase includes
The basement footings (5) of reduced size will preferably be precast, although alternatively they can be also cast on site.
The second phase of partial backfilling (4) of the digs (3) will preferably be carried out with cleaning and levelling concrete, and more preferably with concrete of HL-20 type. The backfilling will preferably be carried out up to a level of 2 m below the base of the wind turbine tower.
An alternative embodiment is foreseen in which the peripheral foundation construction phase (3, 4, 5) includes the construction of piles equipped with support elements.
The assembly phase of precast concrete beams (9a, 9b, 9c) on the peripheral foundations and the existing foundation (2), and bonding with the existing foundation (2) comprises:
In an alternative embodiment, the aforementioned fourth phase can be executed after the aforementioned sixth phase.
The precast concrete beams (9a, 9b, 9c) used in this phase are at least three, arranged horizontally in a radial alignment, the outermost end(s) of which are each supported on a precast concrete basement footing (5) by means of a support element (6) in the upper central part of mentioned footing (5), and are also fixed by means of multiple anchorages (7) between the outer end of the beam (9a, 9b, 9c) and the footing (5), being the different beams joined together in the central part of the foundation by means of connections. In a preferred embodiment, the beam (9a) is approximately twice as long as the beams (9b, 9c), in which case the inner ends of the beams (9b, 9c), arranged perpendicularly to the previously mentioned one, are joined to the central part of the beam (9a), forming a plantar cross structure.
The methods of joining of beams (9a, 9b, 9c) used in this phase include the use of joining methods chosen from the group formed by threaded rods, brackets, reinforcement endings for concreting in housings of another beam, tongue and groove joints and post-tensioning strands.
The fixing of the canal (11) and the central connection point among the beams (9a, 9b, 9c) with the existing foundation (2) is preferably carried out by means of the pre-existing anchor rods (12) in the existing foundation (2), where the old existing elements (1) were fixed. Alternatively, this can be executed or supplemented by the use of connection methods chosen from the group formed by threaded rods, brackets, reinforcement endings for concreting in housings of another element, tongue and groove joints and post-tensioning strands.
We refer to the core as the whole set of elements that are built in the centre, among, over, around or under the beams (9a, 9b, 9c), including at least the canal (11), its concreting (16), the upper layer (15) and the anchors (14) for the new tower or structure.
It is foreseen that the procedure may include an additional phase, which can be carried out after the third phase, of placing precast concrete enclosures in the area among the beams (9a, 9b, 9c), under the height of the upper layer (15). These precast concrete enclosures can be in one piece or made up of several pieces and are intended to contain the wind turbine's electrical transformer in its chaos, or other complementary elements for its operation.
A final optional additional phase is also foreseen, of total or partial covering of the existing beams (9a, 9b, 9c), concreted elements and enclosures or connection boxes, with the earth extracted from the excavation of the digs (3), creating an artificial mound to minimize the visual impact, enabling an easy integration in its environment.
The preferred use of this foundation extension procedure is the repowering of wind farms, to replace a wind turbine with another more powerful and with higher production, without dismantling the previous foundation.
The skilled person in the art will easily understand that you can combine features of different embodiments with features of other possible embodiments, provided that such a combination is technically possible.
All information referring to examples or embodiments is part of the description of the invention.