- 1. A method of erecting a building, comprising the steps of:
- assembling a concrete-pouring falsework by:
- assembling a plurality of panels formed with tubular members along edges thereof with the respective tubular members in mutually parallel relationship and having a plurality of slots therealong, said assembled panels defining a mold for walls and a roof of a building,
- positioning notched plates transversely across pairs of said tubular members such that each notched plate is positioned across two adjacent tubular members, which adjacent tubular members are each formed along an edge of two separate but adjacent panels, and
- inserting hooks in said slots of said tubular members so that hooks engage in notches of said plates and shanks of said hooks overlie said plates, thereby securing said panels together;
- casting concrete in said mold; and causing said concrete to set, thereby forming said walls and roof of said building in a single concrete-pouring operation.
CROSS REFERENCE TO RELATED APPLICATION
This application is a division of Ser. No. 892,121, filed July 30, 1986, now U.S. Pat. No. 4,693,445 issued Sept. 15, 1987.