Not applicable
This invention relates to building fatigue resistant foundations for supporting columns, towers and structures under heavy cyclical loads such as for onshore and offshore wind turbine towers. Wind turbine support structures are subjected to high cyclical loading with the number of load cycles up to 109. Therefore, the fatigue design becomes more important for concrete construction and the influence of multi-stage and multi-axial fatigue loading have to be considered. Studies have recommended modification of the design rules for concrete construction of wind turbine foundations in order to consider the influence of multi-axial loading.
Wind turbine manufacturers have successfully developed large wind turbines with rated power ranging from 1.5 to 10 MW, for onshore and offshore installations. The E-126 model turbine by Enercon with a 7 MW rated power required a 29 meter diameter circular foundation with 1,400 cubic meters of concrete and 120 tons of rebar. The RePower 5M turbine with a 5 MW rated power required a 23 meter diameter circular foundation with 1,300 cubic meters of concrete and 180 tons of rebar. The task of building such large foundations is monumental and requires a great deal of construction planning and logistics. The proposed foundation designs and their associated construction methods provide cost-effective solutions for such challenging foundation projects.
Some wind turbine installations that have been constructed in the last 10 years in the US and. Europe have encountered structural problems stemming from thermal cracking during construction, or from fatigue cracking requiring repairs. The present invention improves the geometry of the foundation in order to enhance dissipation conditions for the typical temperature rise due to heat of hydration after casting and also provides a cost effective fatigue resistant design.
Conventional gravity style foundations for large wind turbines usually comprise a large, thick, horizontal, heavily reinforced cast in situ concrete base; and a vertical cast in situ cylindrical pedestal installed over the base. There are several problems typically encountered during the construction of such foundations.
Fatigue resistance of such conventional footings is achieved by over sizing the structural concrete elements and the reinforcing elements such that the resulting stress amplitudes are small enough for the structural elements to pass fatigue design checks.
The main problem is the monumental task of managing large continuous concrete pours, which require sophisticated planning and coordination in order to pour large amounts of concrete per footing, in one continuous pour, without having any cold joints within the pour.
Another problem is logistics coordinating with multiple local batch plants the delivery plan of the large number of concrete trucks to the job site in a timely and organized manner.
A further problem is the complexity of installing the rebar assembly into the foundation which requires assembling two layers of steel reinforcing meshes that are two to six feet apart across the full area of the foundation, while maintaining a strict geometric layout and specific spacing. This rebar assembly is made of extremely long and heavy rebar which requires the use of a crane in addition to multiple workers to install all the components of the assembly. The rebar often exceeds forty feet in length, thus requiring special oversized shipments which are very expensive and usually require special permits. The installation of the rebar is a labor intensive and time consuming task requiring a large number of well trained rebar placing workers.
Another important problem is the fact that the majority of the construction process consists of field work which can easily be compromised by weather conditions and other site conditions.
Another problem is thermal cracking of concrete due to overheating of the concrete mass. When concrete is cast in massive sections, the temperature can reach high levels and the risk of thermal cracking becomes very high. Thermal cracking often compromises the structural integrity of foundations as reported in many projects in Europe and North America.
Multi-cell caissons used in offshore installations always lack multi-axial post-tensioning elements and their fatigue resistance relies completely on heavily reinforced oversized concrete elements which involves expensive and labor intensive construction.
It is desired to have a cost-effective foundation which reduces the amount of construction material used in the construction of wind turbines. This can be accomplished by the use of concrete rib stiffeners, with a cast in place slab on grade element and a central pedestal to build an integral foundation that will behave structurally as a monolithic foundation structure. Other concrete components can be included such as secondary and perimeter beams, diaphragms, or intermediate stiffeners and rib stiffened or flat slab sections. The foundation system may use prefabricated components including rebar meshes and cages, a pedestal cage assembly, precut post-tensioning strands, preassembled strand bundles, precut post-tensioning duct sections and prefabricated concrete forms.
The present invention pertains to a fatigue resistant foundation for wind towers which comprises a plurality of components, namely a central vertical pedestal, a substantially horizontal continuous bottom support slab with a stiffened perimeter, a plurality of radial reinforcing ribs, also referred to herein as girders or cantilevered girders, extending radially outwardly from the pedestal and a three-dimensional network of vertical, horizontal, diagonal, radial and circumferential post-tensioning elements embedded in the footing that keeps all the structural elements under heavy multi-axial post compression, which reduces stress amplitudes and deflections and allows the foundation to have a desirable combination of high stiffness and superior fatigue resistance while improving heat dissipation conditions during construction by having a small ratio of concrete mass to surface area thus eliminating the risk of thermal cracking due to heat of hydration.
Although the application is written with a wind turbine tower as the column being supported by the foundation, any tower or column can be used on the foundation including but not limited to, antennas, chimneys, stacks, distillation columns, water towers, electric power lines, bridges, buildings, or any other structure using a column.
In one embodiment of the invention a wind turbine foundation has a plurality of components, namely a central vertical pedestal, a substantially horizontal bottom support slab, and a plurality of radial reinforcing ribs extending radially outwardly from the pedestal, the ribs are prefabricated and transported to job site, but the pedestal and support slab are poured in situ at the site out of concrete. The prefabricated ribs 16 are equipped with load transfer mechanisms, for shear force and bending moment, along the conjunctions with the cast in situ support slab, pedestal and perimeter beams. The prefabricated ribs are also equipped at their inner ends with load transfer mechanisms, for shear force and bending moment, along the conjunctions with the cast in situ pedestal. The ribs are arranged in a circumferentially spaced manner around the outer diameter of the pedestal cage assembly before or after slab reinforcing steel is installed. Forms are then arranged for the pedestal and support slab. The support slab is cast in situ by pouring concrete into the forms and then pedestal concrete is poured into the pedestal form over the slab. When the concrete cures the support slab 20 is united to the prefabricated ribs 16 and the ribs 16 are also united to the pedestal 10. The final result is a continuous monolithic polygon or circular shaped foundation wherein loads are carried across the structure vertically and laterally through a continuous structure by the doweled and spliced reinforcing steel bars which are integrally cast into the pedestal 10, ribs 16 and support slab 20. The combination of the high stiffness of the ribs 16, solid pedestal 10 and continuous slab 20 construction across the pedestal 10, and through or under ribs 16, allows the slab 20 to behave structurally as a continuous slab over multiple rigid supports resulting in small bending and shear stresses in the slab 20, reducing deflections and increasing the stiffness of the foundation 100, improving fatigue conditions as well as allowing for the benefits of an economical design. Support slab reinforcing steel covers the entire footprint of the foundation and extends, without interruption, across the slab area and into the pedestal 10 to improve the structural performance of the foundation 100 under different loading conditions. Perimeter beams 190 or thickened slab edges 21 around the perimeter add stiffness and strength to the foundation 100 and provide the benefits of a two-way slab system. Circumferential post-tensioning of the slab edge 21 is used to increase the structural capacity of the ribs 16 and the pedestal 10 by creating eccentric post-compression force in the ribs 16 and by reducing stress amplitudes in the slab 20, ribs 16 and pedestal 10.
The foundation of the present invention substantially reduces the amount of concrete used in a wind turbine foundations of spread footing style, simplifies the placement of rebar and concrete in the foundation, allows for labor and time savings and shortens the foundation construction schedule when compared to conventional foundation designs.
This invention provides the wind energy industry with a foundation system suitable for utility scale wind turbines including 1.5 MW through 10 MW or larger turbines, wherein the amount of cast in situ concrete work is limited, and the number of concrete trucks required for the foundation is kept to a smaller and more manageable level, and the amount of rebar used in the foundation is around 60% less than conventional footings.
The present invention uses prefabricated components that meet size and weight limits for standard ground freight shipping on typical roads and highways, without resorting to special permitting for oversize or overweight shipments, keeping in mind that the foundation width for large turbines can easily exceed sixty feet.
One embodiment of the invention uses specific combinations of precast components with cast in situ components designed to speed up construction without compromising the rigidity and structural continuity and optimization of the foundation. The combination of high strength, high stiffness prefabricated ribs, solid pedestal construction and continuous slab construction across the pedestal, and through or under the ribs, allows the slab to behave structurally as a continuous slab under multiple rigid supports resulting in small bending and shear stresses in the slab, reducing deflections and increasing the stiffness of the foundation, substantially reducing fatigue as well as allowing for the benefits of rapid construction and economical design.
The present invention improves the geometry of the foundation in order to enhance dissipation conditions for the heat of hydration due to the typical temperature rise after casting. This design feature is achieved by reducing the thickness of the support slab and the ratio of concrete mass to surface area, thus reducing the risk of thermal cracking and protecting the structural integrity of the foundations.
The present invention optimizes the design support slab by configuring slab reinforcing to span between supporting ribs, and allowing it to continue under or across the ribs. Each slab panel may be triangular or pie-shaped and is prestressed along all three sides such that a multi-axial prestress is generated in each slab panel. Slab panels with radial and perimeter post tensioning elements form a robust horizontal trussed diaphragm and as a result, the required slab thickness is optimized and the amount of cast in situ concrete is reduced.
The present invention reduces the maximum rebar length for field installation to approximately half the conventional length, to roughly 7.6 meters (twenty five feet), which is significantly shorter when compared to conventional footing that may requires 15.2 to 18.3 meters (fifty to sixty foot) long reinforcing bars.
The present invention allows rib dowels, or post tensioning tendons, extending inwardly into the pedestal at one end, to continue without interruption between distal ends of the foundation. As a result each pair of ribs 16 on opposite ends of the pedestal 10 will behave structurally as one continuous beam across the width of the foundation 100.
The present invention reduces fatigue for concrete and rebar in the foundation by minimizing stress concentrations through appropriately configured connections and component geometry. The solid and deep construction of the pedestal allows for great reduction of stresses across the pedestal and at the conjunctions between the pedestal and the surrounding slab and ribs. Dowels from the ribs into the pedestal are relatively deep to reduce stresses in the surface zone of the pedestal and can be paired with corresponding dowels extending from the opposite end of the foundation. The solid pedestal offers desirable bearing conditions for the tower base plate and improves the geometry as needed to minimize fatigue.
The present invention employs prestressing and/or post tensioning techniques in order to maximize the performance of the foundation, and to extend its life span. Besides the vertical tensioning of anchor bolts, tensioning of horizontal and diagonal tendons are employed along the length of the concrete ribs and across the pedestal. Further, perimeter and radial post tensioning elements embedded in the slab are employed. Post-tensioning of the ribs is designed in an eccentric manner to counter balance and reduce the stresses from the dead loads on the foundation. This can be accomplished by setting an eccentric post tensioning load pattern in the ribs with higher axial force at the bottom than at the top of the rib. The circumferential post tensioning load in the slab provides additional desirable eccentric prestressing of the ribs and the pedestal and helps increase rib load capacity and rib fatigue resistance.
An object of this invention is to provide the wind energy industry with a short construction time, reliable, and cost effective foundation system suitable for most wind energy projects, including projects using the largest utility scale turbines and tallest towers, while providing a foundation lifespan that is longer than conventional foundation systems.
Another object of this invention is to reduce the cost of wind energy projects by realizing savings in the areas of reducing concrete and rebar quantity, reducing concrete trucking service, decreasing concrete pouring and finishing, improving logistics, and reducing man-hours and crane operations.
It is the object of this invention to provide a foundation suitable for large wind turbines including utility scale turbines ranging from 1.5 MW to 10 MW and larger, wherein the amount of cast in situ concrete work is limited and the number of concrete trucks and the amount of rebar required for the foundation is reduced to a manageable level when compared to conventional gravity style foundations.
Another object of this invention is to improve dissipation conditions for the heat of hydration and the typical temperature rise after casting. This goal is achieved by reducing the ratio of concrete mass to surface area. When concrete is cast in massive sections for wind tower foundations, temperatures can reach high levels and the risk of thermal cracking becomes very high unless cooling techniques or special admixtures are applied. Thermal cracking often compromises the structural integrity of the foundations.
A further object of one embodiment of this invention is to improve foundation structural properties due to fabrication of some structural components in a fully controlled environment of a precast concrete plant or a suitable facility at or near the project site and to utilize and benefit from advancement in concrete construction in areas such as concrete admixtures, special cements and fiber reinforcement.
Still another object of this invention is to utilize desirable features and benefits associated with mass production of precast concrete such as high reliability and uniform consistency and high compressive strength.
Another important object of this invention is to minimize chances for errors in bar placement, spacing and layout by providing pre-marked spacing for splicing slab rebar with existing dowels extending from ribs.
A further object of this invention is to use light weight, small diameter, short and easy to handle rebar for the cast in situ concrete.
A further object of this invention is to provide the wind energy industry with a solution for all weather foundation construction.
Still another object of this invention is to improve safety and accessibility around foundations under construction, and reduce hazardous conditions for construction crews.
A further object of this invention is to increase productivity and increase the number of footings that can be built in a given time frame using the same number of workers, when compared to conventional foundation designs built under similar conditions.
Another object of this invention is to employ prestressing and/or post tensioning techniques in order to maximize the performance of the foundation, improve its fatigue resistance and extend its life span.
Another object of this invention is to provide the wind energy industry with reliable and readily available designs, and optionally, prefabricated components, for every wind energy project, wherein foundation designs are pre-approved by and coordinated with turbine manufactures and certification agencies.
A further object of this invention is to use standard designs to reduce engineering work and simplify the permitting process, as well as improve the project construction schedule.
Still another object of this invention is to speedup construction by using many prefabricated components including rebar meshes and cages, bolt cage assemblies, pre-cut post-tensioning strands, preassembled post-tensioning bundles, pre-cut post-tensioning duct sections and prefabricated concrete forms and optionally, precast ribs.
It is also the object of this invention to provide wind energy developers with the ability to select pre-approved complete foundation designs for wind turbine foundations based on project and site variables including turbine model and tower height; site geotechnical characteristics; and desired foundation styles such as gravity, anchored or piling support foundations.
Another object of this invention is to provide foundation contractors with the convenience and economy of using commercially available prefabricated components with complete assembly and detail drawings that can be delivered to any project site with short lead times.
A further object of this invention is to improve the quality and productivity of foundation construction due to experience gained from practicing standard construction techniques with repetitive production steps.
Still another object of his invention is to produce foundation designs suitable for shallow and deep offshore installations.
Another object of this invention is to use the modular foundation system for other tower structures such as chimneys, stacks, distillation columns, telecommunication towers, and water towers.
Yet another object of the invention is to improve tower base bearing resistance in concrete pedestals supporting wind towers such that it becomes possible to build the pedestal and the foundation with concrete having the same compressive strength without increasing the diameter of the pedestal.
Another object of the invention is to build wind tower foundations in one continuous concrete pour.
Another object of the invention is to independently produce prefabricated components for offshore foundations to be assembled on a barge without having the critical path of completing a first component before a second component can be constructed.
Other objects, advantages and novel features of the present invention will become apparent from the following description of the preferred embodiments when considered in conjunction with the accompanying drawings.
The present invention pertains to a wind turbine foundation. The foundation comprises a plurality of components, namely a central vertical pedestal, a substantially horizontal bottom support slab, and a plurality of radial reinforcing ribs extending radially outwardly from the pedestal. The ribs may be prefabricated and transported to job site, but the pedestal and support slab are poured in situ at the site out of concrete. Alternatively the ribs may be cast in situ.
The present invention pertains to a fatigue resistant foundation 100 for wind towers which comprises a plurality of components, namely a central vertical pedestal 10, a substantially horizontal continuous bottom support slab 20 with a stiffened perimeter 21, a plurality of radial reinforcing ribs 16 extending radially outwardly from the pedestal 10 and a three-dimensional network of vertical 56, horizontal 110, 111, 112, diagonal 58b, 58c, radial 58 and circumferential 59 post-tensioning elements embedded in the footing that keeps all the structural elements under heavy multi-axial post compression, which reduces the stress amplitudes and deflections and allows the foundation 100 to have a desirable combination of high stiffness and superior fatigue resistance while improving heat dissipation conditions during construction by having a small ratio of concrete mass to surface area thus eliminating the risk of thermal cracking due to the heat of hydration.
A construction site is prepared by excavation, with flattening and preparation of soil for the foundation 100. The foundation 100 may be set on pilings 400, on piers 180, or have anchors 404 (soil anchors or rock anchors 404 or micro-piles 401 or other types) in a conventional manner.
The present invention ensures good contact between foundation 100 and soil, or sub-base 14a, by casting.
The foundation 100 is cast against prepared soil, a crushed stone sub-base 14a, a mud slab 14 or a membrane sheet in case of offshore foundations assembled on a barge or in dry docks. Known grouting and leveling techniques under precast elements can be employed for ensuring plumb installation and good soil contact.
In one embodiment of the invention, the foundation 100 may be set on a mud slab 14 or on compacted granular fill. The mud slab 14 is often a thin plain concrete layer intended to provide a clean and level base for the foundation installation. After the foundation site has been prepared, a plurality of three or more precast stiffener ribs 16 are placed on the mud slab 14 or compacted granular fill inside of the excavation pit 12. The precast concrete stiffener ribs 16 may have means for leveling or other leveling techniques can be employed for level and plumb installation. If desired, grouting techniques can be used to ensure complete rib base contact with the mud slab 14 or sub-base. The precast concrete ribs 16 may have bases 21 with left shear key 38 and/or shear connectors and right shear key 36 and/or shear connectors. The precast concrete stiffener ribs 16 may also have a vertical shear key 34. The shear keys 34, 36 and 38 and associated dowels 40, 42 and 46 are to ensure continuous connections, with complete transfer of shear and bending loads, between the precast concrete rib stiffener 16 and the cast in place concrete which is to be poured into the foundation 100 to form the bottom support slab 20. The precast concrete stiffener ribs 16 have upper dowels 40 and lower. dowels 42 extending on the right and left sides of the base 21 which interconnect with and spliced to upper mesh rebar 22 and lower mesh rebar 24 installed between the ribs 16 and connected to dowels 40, 42 to form reinforcement for the slab 20 and pedestal 10 of foundation 100 when the concrete is poured. The rib 16 has dowels 46 radially entering the pedestal 10 in the center of the foundation 100.
Doweling of rebar between the ribs 16 and foundation components can be achieved with rebar dowels extending from the prefabricated elements or by using rebar couplers, bar extenders or any mechanical rebar splicing system.
Arrays of grout or epoxy filled sleeves 42b arranged in the slab 20 could receive corresponding arrays of vertical dowels 42a extending from the bottom of prefabricated ribs 16 or perimeter beams 190 or other prefabricated components.
Shear keys, or shear transfer mechanisms, can be replaced with, or combined with, corbels or shear studs, or other shear connectors such as angled rebar or embedded steel shapes 34a.
In another embodiment an array of steel beams 16s, are encased into the web of the rib 16 and extend inwardly into the pedestal cavity at the inner most end of ribs, and serve as a suitable shear force transfer mechanism between the rib 16 and the pedestal 10.
In another embodiment, the foundation 100 comprises a steel frame 16f fully encased in concrete and has a central tower receiving a metal cylinder 56b fixed to an array of radially extending steel girders 16s encased in concrete beams 16, 21, 190 and rigidly connected at their outer ends to an array of perimeter beams 190 encased in the concrete foundation 100 and a reinforced concrete slab-on-grade 20 covering the foot print of the foundation 100 and connected to the steel frame.
In one embodiment the ribs 16 may be treated with concrete bonding agent along surfaces where cast in place concrete is received.
In another embodiment the foundation 100 may be provided with drains 23 around the perimeter and the top surface of the slab 20 is slightly sloped towards the drains 23 such that water is drained away from foundation 100.
In another embodiment, when foundations are installed in sites prone to seismic activities and elevated water tables, the slab may have holes to prevent soil liquefaction during seismic events.
In another embodiment the ribs 16 or other foundation elements may be covered or coated with protective material for extending the life span of the footing.
In another embodiment the ribs 16 are placed on the mud slab 14 first and then the pedestal cage 50 made of an array of rebar, preferably Z or C shaped rebar and circumferential rebar is assembled around anchor bolt assembly 60. Alternatively the pedestal cage 50 is assembled first or a preassembled pedestal cage 50 dropped into place first and then the ribs 16 with dowels 46 are slid into place so that dowels 46 and shear connectors 34, 34a fit between the elements of pedestal cage 50 rebar assembly.
The precast concrete stiffener rib 16 has lifting lugs 32 to help place the stiffener rib 16 into the excavated construction area. The base of the ribs may have a flat bottom surface such that the ribs may stand on their own on the mud slab 14 or compacted granular fill or during transportation from a precast plant to the foundation site. The precast concrete stiffener ribs 16 have prestressing elements 58 running through the ribs 16 radially from the outside of the ribs 16 and through pedestal 10. The radial prestressing elements 58 (or post tensioning elements) may be anchored to the opposite side of the pedestal 10 or optionally run through the opposing precast concrete stiffener rib 16 on the other side of the pedestal 10 and anchored at the end of the opposite rib 16. Once the ribs 16 and the pedestal cage 50 are in place, the dowels 46 extending radially inward from ribs 16 may be connected to, or spliced with, corresponding dowels arranged in the pedestal cage 50. Inside of pedestal cage 50 are additional rebar dowels 48 which will facilitate the continuity of the structural components through the pedestal 10 as well as resist bearing, shear and bending loads.
Also inside of pedestal reinforcement cage 50 is a bolt assembly 60 comprising a bolt template 52 an embedment ring 54 and anchor bolts 56 protected by a PVC sleeve 57 or wrapped with a material to prevent bonding between the anchor bolts 56 and concrete to be poured. The anchor bolts 56 have a top portion which is used to attach the base flange 301a of a tower or column to the pedestal 10. A grout trough template 52 at the bottom of the bolt template 52 may be used to create a grout trough 90 to ensure a good connection of the tower or column to the pedestal 10. The grout trough 90 will be formed by removing the bolt template 52 from the anchor bolts 56 after the concrete has been poured. Radial dowels 46, prestressing elements 58 or shear connectors 34 at the inner end 16c of ribs 16 should be spaced to clear anchor bolts 56 and other reinforcement arranged in pedestal cage 50.
In a preferred embodiment, for fully cast in place foundations, slab forms 17 may sit directly on the mud slab and rib forms 16b are supported and kept elevated above slab 20 elevation by means of adjustable and reusable support legs 16y arranged in the rib forms 16b. Small footings or thickened mud slab areas could be used under rib 16 form support legs. Pedestal forms 102 can be supported by rib forms 16b or by separate support legs.
When ribs 16 are prefabricated, the bolt assembly 60 is held in place and the anchor bolts 56 are can be properly oriented by an alignment apparatus 130. The alignment apparatus 130 has a central post 132 with arms 134 attached perpendicularly to the center post 132 and having legs 136 for attachment to the top of the ribs 16 to provide added stability and proper bolt template 52 alignment during construction. The legs 136 have an adjustable height relative to the arms 134. The arms 134 may have braces 138 attached to the central post 132 for holding the arms 134 straight. The central post 132 may also have central post support 135 to support the central post 132. The alignment apparatus 130 also has adjustable support members 140 for attachment between the arms 134 and the bolt template 52 to align the anchor bolts 56 so they are upright. The alignment apparatus 130 can support the bolt assembly 60 without the central post 132 by relying on the legs 136 supported by ribs 16, which allows the lower portion of the central post 132 to be removed if desired, Alignment apparatus 130 can be used as a template to ensure proper location, elevation and orientation of ribs 16.
The ribs 16 can be of any shape or size depending on the specifications of the tower and loads thereon. For example, the cross-section of the ribs 16 may be trapezoidal, rectangular, T shaped or I beam shaped. The ribs 16 may be triangular prisms as shown in
Ribs 16, or rib forms 16b, may have means for receiving and supporting perimeter forms 18, such as bolts or threaded inserts for receiving and supporting the pedestal forms 102. The ribs 16, or rib forms 16b, may also have attachment means 15 for holding base forms 17. The pedestal forms 102 may be equipped with platform sections for allowing access around the pedestal and the rest of the footing.
With all the rebar 22, 24, ribs 16, pedestal 10, bolt assembly frame 80 and optional alignment apparatus 130 in place concrete forms may be attached such that concrete can be poured to form the pedestal 10 and slab 20 of the foundation 100. Pedestal forms 102 may attach to the ribs 16, or rib forms 16b, by bolts 18 or by any other means. Similarly, the base perimeter forms 17 may be attached to the ribs 16, or rib forms 16b, by bolts 15 or by any other means. Alternatively, the base perimeter forms 17 may be supported to the ground or the mud slab.
With all the parts assembled all the rebar in place and the duct for the prestressing tendons, or prestressing elements of the foundation in place, concrete is then poured into the pedestal 10 and between the ribs 16. The pouring of the concrete can be accomplished quickly and the slab areas between the ribs 16 can be finished as the pedestal 10 concrete is still being poured. The concrete may be used to build the pedestal 10 and the slab 20 in one pour. Alternatively, the base for the entire slab 20 foot print of the footing can be poured in a first pour then the pedestal 10 can be formed in a second pour.
When a bonded multi-strand post tensioning system is used in the foundation 100, the prefabricated components are fitted with ducts and anchor hardware according to design specifications. The cast in place components will be fitted with matching ducts to facilitate the continuity of tendons across the foundation 100. After the jacking of tendons, duct grouting is carried out as required. If the un-bonded, bundled mono-strand system is employed, no duct or grouting is required.
The structural load capacity of the foundation 100 is increased significantly by the combination of radial 58 (or diametric) and circumferential post tensioning 59. Circumferential post tensioning 59 creates a desirable symmetric bi-axial post compression in the slab 20. Circumferential post tensioning 59 is applied at an elevation well below the neutral axes 16n of the ribs 16 thus creating eccentric post compression in the ribs 16 and the pedestal 10 and resulting in increased nominal moment and shear capacity of the ribs 16 as well as improvement in multi-axial fatigue resistant of the pedestal 10, ribs 16 and the slab 20. Radial or diametric post tensioning elements 58 extend from rib 16 to opposite rib 16 across the pedestal 10. Radial post-tensioning is applied with an eccentric load pattern, with higher. post compression below the neutral axis 16n of the rib 16. When all the prestressing elements are jacked, the foundation 100 is kept under heavy multi-axial eccentric post compression stress, thus increasing rib 16 structural capacity to resist soil support reaction and providing low deflections, high stiffness and low stress amplitudes resulting in high fatigue resistance and high durability of the slab 20. Backfill 13 is added over the slab 20 for increased stability and stiffness of the foundation 100.
After the concrete sets, post tensioning is carried out and the foundation 100 is backfilled with compacted granular fill 13 to stabilize the foundation 100 against overturning.
Alternately, the bolt assembly 60 can be replaced by a tower section 56b embedded in pedestal 10 concrete. The embedded section 56b having means 56c for receiving a tower base 301 by means of a bolted connection arranged at the top of the section 56b The embedded metal cylindrical tower section 56b encased in pedestal 10 concrete is provided with holes 56h for rebar and post tensioning tendons 58 to extend through the metal cylinder 56b. Post tensioning 58 tendons can extend through holes 56h arranged in the cylinder and across the pedestal 10, through the ribs 16 to be anchored on distal ends of the foundation.
Pedestal 10 can be any size or shape, round, triangular, square, polygon or other shape depending on the specifications of the tower and loads thereon. The ribs 16 can be in any pattern around the pedestal 10. In one embodiment shown in
Pre-assembled reinforcement sections (meshes) of the slab 20 components can be lowered into place in the slab 20 to speedup construction. All rebar dowel or metal shear connectors extending through construction joints may be galvanized or Epoxy coated to prevent corrosion. The use of mechanical couplers in the foundation 100 may be limited or avoided. Specified mechanical couplers must be tested and certified for the number of load cycles in the life span of the foundation 100.
In another preferred embodiment, the ribs 16 are cast in place in reusable rib forms 16b. The ribs 16 are cast in place jointly with the pedestal 10 in one continuous pour over the slab 20. Optionally, the ribs 16, the pedestal 10 and the slab 20 are all jointly cast in one pour. All rib internal components including rebar assembly with dowels and prestressing elements are placed inside the forms, then cast in place concrete is poured into the rib forms 16b as well as into pedestal 10 and slab 20 forms.
Rib reinforcing cages 16rc can be assembled above grade and lowered into the foundation in one or more sections.
In a preferred embodiment, rib forms 16b with internal rib reinforcing cages 16rc are preassembled and lowered into the foundation by cranes to mesh with slab reinforcing sections 22, 24 already placed in the foundation. The radial reinforcing pattern 22 of the slab 20 enables the meshing rib dowels 42 between slab reinforcing 22, 24 without geometric interference.
Ribs 16 can also be made in segments 16sg and eventually united by means of doweling or by using segmented post-tensioned construction techniques. Rib anchor zone 16x with anchor trumpets 16t and hardware can be prefabricated separately of higher strength concrete than the rest of the rib 16.
As shown in
The foundation 100 pertains to a hybrid gravity based and rock anchored foundation. Ribs 16 can be made with arrangement, mechanisms and connectors for receiving piles 400 or micro-piles 401 or anchors 404 in different configurations. Vertical through holes 16g in the ribs 16 can provide means for receiving a pile 400, micro pile 401 or an anchor 404. Bearing elements 404b and grouting are arranged on top of each rib 16 to establish the required structural connection. An array of bearing plates 404b with tensioning nuts 404c on each soil/rock anchor may be used to compress the foundation 100 against supporting soil. Vertical through holes 16g with corrugations 404h for the anchor 404 extend through the foundation 100. Bearing plates 404b with tensioning nuts 404c can be placed on top of the pedestal 10 or in the foundation 100. If desired ribs 16 may have piers 180 extending vertically from the ribs 16 and the top of the pier elevation is raised to a higher elevation to make anchor bolts 404a accessible for tensioning and testing. Typical rock or soil anchor construction and pouting methods can be utilized. Another option is to house rock anchor bolts 404a and hearing plates 404b and tensioning nuts 404c in accessible corrosion protection compartments above the foundation 100.
In another embodiment as shown in
The prefabricated components can be molded at a facility under controlled conditions for good quality concrete setting and controlled rebar spacing which is superior to what can be obtained on a job site and at a lower cost. The ribs 16, acting as deep stiff horizontal cantilever support, allow the base of the foundation slabs to have a relatively small thickness using less cast in place concrete and rebar thus lowering the cost for each foundation.
Alternatively, as shown in
Cast in situ concrete can be shielded from extreme weather, including heat, cold, rain and snow, by simply extending blankets, covers or shields between ribs 16 during construction, and then using heaters or fans as required to regulate the temperature and humidity of the concrete to allow for proper setting and curing conditions.
Another embodiment of the present invention pertains to a leveling technique that simplifies the tower base leveling process and shortens the number of steps required for grouting under a tower base. The bolt template 52 is provided at the very top of the bolt assembly 60 with at least three sets of additional bolts 53 and corresponding threaded bolt inserts 53h suitable for embedment in the concrete. Such leveling bolts 53 and inserts 53b will be located outside or inside the bolt circle 60a of tower base, but directly under tower base flange 301a. This allows for continuity of grout bed 90a construction and provides an easy access to leveling bolts 53. Small cutouts at leveling bolt locations may be used. Another benefit of this leveling technique is having the ability to apply continuous grout bed 90a that is free of cold joints, under the tower base flange 301a in one session as well as having the ability to tension all anchor bolts 56 in one work session.
In another embodiment the onshore foundation may have a pedestal 10 that is rigidly connected to vertical concrete stem 11 that is fixed to a tower base of a wind tower. The pedestal and the stem are vertically prestressed with vertical post tensioning elements extending through the height of the foundation. The stem is fitted with an array of bolts 60 for receiving and supporting the tower base 301.
The foundation design, as shown in
The integral piers 180 can extend above final grade elevation, while the top of pedestal 10 may stay below final grade elevation. For this foundation style, pedestal elevation may be depressed and tower receiving components may not be required in the pedestal 10. This configuration may also be used in offshore applications wherein a prefabricated gravity foundation 100 is connected to lattice tower structure 200 that is fitted with a wind tower receiving component at its top. The foundation 100 will be installed over prepared seabed and filled with a suitable backfilling material 13, and surrounded with scour protection 13b.
As shown in
In another embodiment as shown in
Vertical prestressing of the pedestal 10 can be carried out independently of tower receiving elements. A pedestal 10 may have an array of vertical post tensioning elements 56 that does not connect to a tower 300, and an embedded tower section 56b bolted to a tower structure 300.
Radial post-tensioning 58, extending across the foundation 100, in pairs of ribs 16, allows for the desirable structural continuity and the direct transfer of loads from downwind ribs 16 into the pedestal 10 and then into the opposing upwind ribs 16. Radial and circumferential post compression stresses in the slab 20 and/or perimeter beams 190 allows for a desirable reduction in stress amplitudes the structural continuity between slab 20 spans and/or perimeter beam 190 spans, across the ribs 16, thus creating a desirable load sharing mechanism between adjacent ribs 16 by forcing more ribs 16 to be engaged in resisting tower loads.
The invention pertains to a durable, high-stiffness, fatigue-resistant foundation structure 100 for onshore wind tower installations which comprises: 1. a central pedestal 10 that is made of cast-in-place concrete with concentric vertical prestressing elements 56, 70 and eccentric multi-axial horizontal and/or radial post-tensioning elements 58a, 58b, 58c; 2. an array of cast-in-place eccentrically post-tensioned radial ribs 16; 3. a cast-in-place slab 20 with heavily post-tensioned thickened slab edge 21.
All components are made of high strength reinforced concrete and are rigidly connected to each other to behave as a monolithic spread foundation structure. The structural components are rigidly connected with arrays of rebar dowels 42, 46 (passive reinforcing) and/or post-tensioning elements extending through the conjunctions. The slab 20 functions as a two-way slab system that is free of construction joints across the footprint of the foundation and spans continuously over multiple ribs 16. Perimeter post tensioning 59a or circumferential post tensioning 59 of the slab 20 is applied at an elevation well below the neutral axes 16n of the ribs 16 to cause eccentric loading of the ribs 16 and the pedestal 10. Radial post-tensioning elements 58 with an eccentric load pattern, with higher post compression at the bottom of the rib, extend from rib end 16x to the opposite rib end 16x across the pedestal 10, or to the opposite end of the pedestal 10. When all the prestressing elements are jacked, the foundation 100 is kept under heavy multi-axial eccentric post compression stress, thus increasing rib 16 structural capacity to resist soil support reaction and providing low deflections, high stiffness and low stress amplitudes resulting in high fatigue resistant and high durability. Backfill 13 is added over the slab 20 for increased stability and stiffness of the foundation 100.
Soil support reaction under the slab 20 is transferred from the slab 20 to the ribs 16 and thickened slab edge 21 (or perimeter beams 190) as in two-way slab systems with more load distribution going to the ribs 16 in the primary span. Perimeter 112 or circumferential 59 post-tensioning is applied, generally in the orientation of the primary span that effectively reduces stress amplitudes and deflections in the slab 20 by keeping the slab 20 under heavy post-compression in the directions of primary slab spans 20s1, and secondary slab span 20s2 around the foundation. The size, distribution, eccentricity and location of post tensioning elements 58 in the ribs 16 and the slab 20 are used to dictate the natural frequencies of the foundation 100 to be in a safe range relative to operating frequencies of the wind generator according to turbine manufacturer recommendations.
The 3-dimensional post-tensioning network in the foundation keep all the structural components (Pedestal 10, ribs 16, slab 20, thickened slab edges 21 (or integral edge beams)) under multi-axial post compression confinement resulting in lower stress range amplitudes thus yielding higher stiffness, more effective crack control, lower deflections and improved fatigue resistance. Superior fatigue resistance and long lifespan are achieved by keeping most of the structural elements of the foundation 100 under multi-axial compression while resisting operating loads or even during normal and abnormal extreme loads from the supported structure (wind power generator).
In a preferred embodiment, rib post-tensioning requirements are reduced by engaging fully developed bar dowels 46 from the rib 16 into the pedestal connection as well as extending fully developed radial rebar dowels 22r, 24r of the slab 20 into the pedestal 10, thus allowing passive reinforcing to participate in the connection especially under extreme loads. A radial slab reinforcing pattern with tapered rib width is very cost effective as the rib 16 to pedestal 10 connection benefits from a large number of top and bottom radial slab reinforcing bars 22, 24 participating in said connection, as the rib width widens, thus reducing the number of bottom post-tensioning strands 58a required for the connection.
The structural configuration of the foundation 100 reduces the overall cumulative deflections in the structure under tower loads and significantly improves the rotational stiffness of the foundation 100 which is a key factor in determining the size of foundations in wind turbine installations. The rotational stiffness is also improved by the interlocking between the surrounding soil (after backfilling) and the multiple surfaces and vertical faces of the foundation structure. The horizontal stiffness is improved by the passive earth pressure on the multiple surfaces of the structure. Both rotational and horizontal stiffness achieved by this design are much higher than conventional tapered inverted-T gravity spread footings especially for onshore foundations installed below grade in an excavated pit because of the increased interlocking surface area and increased passive earth pressure and increased friction on the multiple faces of the fatigue resistant foundation 100.
The solid-core pedestal 10 comprises a continuous reinforcing cage 50 and a tower receiving component 56, such as anchor-bolt assembly 60, with a cylindrical array of bond protected high strength post-tensioning bolts 56, for connecting to wind tower base flange 301a. In another embodiment and the tower receiving component may comprise an embedded cylindrical metal tower section 56b with means 56c for connecting to a tower section such as a flange 56c with bolt holes 56d for receiving bolts 301b at its top and with an array of holes 56h to allow the passing of rebar 46 and post tension tendons 58. The embedded tower section 56b is also fitted with conventional bearing flanges 56e and ring stiffeners for interlocking with the pedestal concrete. The anchor bolt assembly 60 ensures structural continuity between the tower 300 and the pedestal 10. The post-tensioning forces of the anchor bolts 56 are selected to insure that the tower base flange 301a remains in contact with the pedestal 10 under extreme normal and abnormal load conditions. The bolt assembly 60 includes, at its bottom end, a bearing element 54 that may consist of an embedment ring plate 54 that is made of segments that are welded together.
As shown in
As shown in
The rib's thickness 16th can be gradually increased at the connection to the pedestal 10 to increase rib flexural, shear and torsional capacity and enhance pedestal confinement 16m. The post-tensioning requirements can be reduced by engaging dowels 46 at the rib-to-pedestal connection and by extending fully developed radial dowels 46, 22r, 24r from the rib 16 and the slab 20 deep into the pedestal 10, thus allowing passive reinforcing to participate in the connection.
In another embodiment, as shown in
The foundation may have a circular or polygonal foot print. The thickened slab edge 21 (or perimeter beam 190 may extend above or below the foundation. A shallow perimeter beam 190 profile should be selected for ease of backfilling and improved accessibility for roller compactors during the backfilling of the foundation 100. A thickened slab ring beam 21 may be designed to be at an offset distance away from the slab edge allowing the slab segment, outside the ring, to behave as a cantilever. This configuration reduces slab 20 span and deflections as well as the volume of concrete required in the foundation 100.
As shown in
In a preferred embodiment, as shown in
Ribs 16 may have thickened flanges, at their connection to the pedestal 10 that may also house post tensioning anchors for tendons 58 extending from ribs 16 on the opposite side of pedestal 10. The ribs 16 may also have post tensioning anchors along their sides or tops if tendon curtailment methods are applied in the design. The ribs 16 may also have embedded loop anchors if looping of tendons is used in the design. Loop anchors 70 could also be used in the pedestal 10 to support and vertically prestress precast concrete towers 300b, or concrete stems 11.
As shown in
In another embodiment, as shown in
Alternately, as shown in
In another embodiment circumferential post tensioning may be made with multiple tiers of tendons 59, in this case anchor block 21a locations or ring anchor 59b locations for each tier may be staggered around the perimeter of the foundation 100p to reduce stress concentration. Corrosion protection must be provided at anchor locations. Perimeter post-tensioning 112, or circumferential post-tensioning 59 can be made with bundled, un-bonded mono-strands without encapsulation.
The foundation may be made with a network of prestressed concrete elements that can be structurally analyzed, with the strut and tie method. A three-dimensional structure made of an array of vertically and horizontally oriented truss-girders joined at the center may be used, with major tension chords reinforced with prestressing tendons, based on both upwind and downwind load cases. The tension forces in the structure are resisted largely by prestressing elements and passive reinforcing. Compression forces are resisted largely by the concrete elements. The structure can be analyzed as a circumferential array of vertically oriented trusses that are fixed at their inner ends 16c to the central pedestal 10 and are laterally stabilized at their bottom by a horizontal trussed diaphragm formed by perimeter post tensioning 59a, in the slab 20 or perimeter beam 190, and radial bottom tendons 58 in the ribs 16 or the slab 20.
In another embodiment, as shown in
In another preferred embodiment the construction of the foundation 100 may utilize pre-assembled slab perimeter reinforcing cages 21c, built in segments with overlapping spliced bars at their ends, and each having an array of shear resisting vertical ties 21vt and flexure resisting horizontal bars 21h as well as anchor zone reinforcing. Slab perimeter cages 21c or perimeter beam reinforcing cages, 190c can be preassembled and then placed in the foundation.
As shown in
Anchor zones, as shown in
The pedestal 10, as shown in
Upper 22 and lower 24 slab reinforcing meshes may have any pattern such as a square grid, a circular array with radial pattern or overlapping pie-shaped segments. Additionally, there may be an array of slab reinforcing 22, 24 locally arranged beneath the ribs 16 oriented parallel to the ribs 16 and extending into the pedestal 10 to facilitate composite action. The slab 20 may also be reinforced with post-tensioning elements in any pattern including radial, circumferential, perimeter or a square grid.
The foundation may utilize many prefabricated components including rebar meshes and cages, pedestal cage assembly, pre-cut post-tensioning strands, preassembled post-tensioning bundles, pre-cut post-tensioning duct sections and prefabricated concrete forms.
Reusable rib forms 16b may be utilized to form the foundation perimeter 100p, the ribs 16 and the pedestal 10. Forms can be made to be segmented, universal, expandable and adjustable to work for different foundation sizes. Rib forms 16b can be made with adjustable supports 16y to elevate the forms above the wet slab 20 concrete during construction if the foundation is built in one pour. Rib forms 16b may sit directly on the hardened concrete slab 20 if the foundation is built in two pours. Rib forms 16b may be made with two side-panels of stiffened non-stick plates and an array of adjustable horizontal spacers between the panels to maintain proper geometry and resist the lateral pressure of wet concrete. Rib forms 16b and pedestal forms 102 may be fitted with lifting lugs 32 or means for receiving and supporting ladders, catwalks 95 and work platforms 95 to allow for access around the foundation 100. The forms may have means for securing post-tension anchors and hardware at specific spacing during construction. The forms may also have means for hanging and supporting rib reinforcing cages.
The foundation 100 may be supported on piles 400, or micro-piles 401 or piers 402 or rammed-aggregate piers 405. The foundation 100 may receive rock (or soil) anchors 404 in a conventional manner.
A construction site is prepared by excavation, grading and compaction soil for the foundation. The foundation 100 may be set on a mud slab 14 or on compacted granular fill. The mud slab 14 is a thin plain concrete layer intended to provide a clean and level base for foundation installation.
In one embodiment, as shown in
When the concrete hardens to a specific strength, the post-tension elements are jacked and grouted as required. The tower base flange 301 is then attached to the pedestal 10 and grouted, and the tower anchor bolts 56 are tensioned after the grout reaches sufficient strength.
In a preferred embodiment, as shown in
In another embodiment, slab post-tensioning can be arranged at any combination of perimeter, radial, diametric, or other patterns.
In another embodiment, composite action is further facilitated with radially oriented, reinforcing bars 24r1 locally arranged in the slab 20, beneath the ribs 16, and extended deep into the pedestal 10, in addition to an array of vertical dowels 42 extending between the rib and the slab 20 that function as shear connectors.
In a preferred embodiment, as shown in
In a preferred embodiment, the rib 16 extends vertically from the bottom of the foundation 100 to an elevation near the bottom of the tower base flange 301 to enable the ribs 16 to participate in resisting bearing loads under the tower base flange 301 by increasing the area of the cross-section involved in bearing resistance under the tower base flange 301 and increasing the permissible bearing strength under the base flange 301 or the grout bed 90a and by increasing the bearing area measured at the surrounding faces of the concrete. The geometric configuration and the improvement in bearing resistance, allow concrete with only one relatively low compressive-strength for the entire foundation structure. In contrast, high bearing stresses under the tower base flange 301 in conventional gravity spread footings, requires concrete with higher compressive strength for the pedestal 10 and a lower compressive strength for the slab 20.
The proximity of inner rib ends 16c to the tower base flange 301 allows the inner zones of the ribs 16 to remain under vertical compression stresses caused by vertical post-tensioning forces between embedment ring 54 and tower base flange 301. The vertical compression stress zones in the distal ends of the pedestal 10x improves the confinement conditions and fatigue resistance in the rib inner zones 16c.
Bonded and grouted multi-strand in some applications may be too expensive and take too long to install as it requires an additional step of grouting and may not be economical for some onshore installations. It may then be preferable to use un-bonded, encapsulated mono-strands, arranged in bundles and installed in the foundation reinforcing prior to concrete casting, which reduces construction costs and improves the construction schedule.
In a preferred embodiment post-tensioning in the foundation 100 is made eccentric, to create cambers in the foundation 100 that could result in reduced deflections and improved foundation-soil contact. As an example, the eccentric prestressing of the ribs 16 creates a convex shaped camber in the foundation 100 that helps reduce the deflections under turbine weight and operating loads. Similarly, cambers can be used in perimeter beams 190 and slab sections to reduce slab deflections and improve foundation-soil contact conditions by ensuring a more uniform bearing pressure under the foundation thus allowing for an optimized foundation footprint with more uniform pressure over the effective bearing area.
The vertical profile (elevation) of circumferential tendons 59 in the foundation 100 may be varied at mid spans and under supporting ribs 16 to optimize their utilization.
In another embodiment a gradual transition of geometry at the conjunction of the structural elements is employed to prevent stress concentration and fatigue related problems. As an example, the use of fillets and curved transition ft is desirable at the conjunctions between ribs 16, pedestal 10 and the slab 20.
In a preferred embodiment, the inner ends of the ribs 16 are tapered to a wider cross-section as the rib 16 connects to the pedestal 10, in order to satisfy the high flexural, torsional and shear demands at the inner zone of the ribs 16, and to distribute the multi-axial compression over large surface area to help reduce splitting and bursting reinforcing on the side of the pedestal 10.
In another embodiment low relaxation post-tensioning strands are used to reduce post tension losses over time. Concrete accelerators and plasticizers and other admixtures may be utilized in the concrete mix design. The small thickness of the structural elements may allow for on-site steam curing of the concrete.
A hollow pedestal 10 cross-section may be used, however it can be problematic. A hollow pedestal above the frost depth where there is elevated water table may be problematic. In another embodiment the cross-section of the rib may change and dimensions along its length may change. For example, the section may start rectangular and gradually a top flange may be enlarged to reduce stresses in the upper zone of the rib.
In another embodiment the pedestal 10 may have an enlarged cross-section at the top followed by a transition into a smaller cross-section below. The upper enlarged cross-section may help improve hearing strength at the top of the pedestal below the tower base flange 301a, the bearing washer plate 404b, and the high strength grout bed 90a according to American Concrete Institute design guidelines.
The present invention pertains to a foundation design that overcomes the thermal cracking problem stemming from heat of hydration, in large foundation pours, by using a structural configuration coupled with post-tensioning techniques that reduce the thickness of the structural elements, while increasing the surface area of the concrete pour, thus improving heat dissipation conditions and causing a the ratio of concrete mass to surface area to be roughly 40% to 50% less than in conventional design for inverted T foundations for the same turbine under the same loading and geotechnical conditions.
As shown in
The present invention improves safety and accessibility around foundations during construction and reduces hazardous conditions for construction crews. This goal is achieved by using reusable form sections 102 that are fitted with platform sections for forming an access platform around the foundation. The form may also connect to at least one access ramp extending beyond the edge of the foundation. The platform and the ramp are fitted with a slip-resistant walking surface and the elevated ramps are provided with guardrails and designed to applicable industry safety standards. Further, the relatively thin slab thickness minimizes the risk of worker injury during construction.
A transformer pad can be supported on precast concrete posts extending vertically from the foundation.
Pedestal forms 102 may have openings for running electrical and communication conduits there through thus preventing problems stemming from randomly placing the conduits in areas that could compromise the structural design.
The ribs 16 may have means for receiving and supporting prefabricated trays (or electrical duct banks) for housing power and communication cables.
The foundation design can also be adapted for offshore wind turbine projects. In this case the foundation 100 may be assembled on a barge or dry dock then transported or floated to its destination and lowered into a prepared seabed location. The foundation can be weighed down in place by backfilling it with suitable material. The offshore foundation 100 may be configured to receive any type of offshore piers 404, suction piers 403, piles 400, micro-piles 401, anchors 404 or any combination of the above.
In another embodiment of the invention as shown in
The offshore foundation 100 is constructed on a barge or in a dry dock and then floated or transported to an offshore installation site and lowered to be placed over a prepared sea bed. A suitable backfill material 13 is placed over the foundation 100 to stabilize the foundation against overturning. Scour protection measures 13b are provided around the foundation. The foundation may be built with marine cement and marine grout and kept under heavy multi-axial horizontal and vertical prestress using bonded and grouted post tensioning systems rated for double corrosion protection and suitable for a marine environment.
In another embodiment as shown in
When the concrete sets, the precast components will become integral with a cast-in-place components. Radial post-tensioning tendons extend from the distal end of one rib through the rib and the pedestal to the distal end of the opposite rib. Vertical post-tensioning is arranged in the pedestal 10 as well. The stem 11 and the ice cone 11b may also benefit from circumferential post-tensioning 59t.
The pedestal 10 has means for receiving and supporting a tower 300 or pylon. The upper portion of the pedestal 10 (the stem 11) may be made in multiple consecutive cast in situ pours, depending on its height. Alternatively, the stem 11 may be made by joining precast segments with circumferential 59t and vertical 70 post-tensioning to form the stem 11 as in segmented concrete tower construction.
In another embodiment of the invention, as shown in
In another embodiment of the offshore foundation comprises the following elements as shown in
When the concrete sets, the pre-cast components will become integral with the cast-in-place components. Radial post-tensioning tendons extend from rib ends 16x to the opposite rib ends 16x across the pedestal 10. Vertical post-tensioning is arranged in the pedestal 10 as well. The structural behavior is improved by the added compression in all ribs 16, edge beams 190, slab 20 and center pedestal 10.
The lattice tower 200, preferably incorporating 3-dimensional trusses 200tr, transfers the pylon loads down to the concrete foundation 100. The lattice tower 200 may get connected to the concrete foundation prior to transportation or it can be connected to the foundation at final offshore installation site.
In another embodiment of the invention as shown in
In another embodiment of the invention, as shown in
Piles 400, Micro-piles 401 or piers 402 or suction piers 403 or anchors 404 can be used with the offshore foundation 100 in a similar manner as previously described in the application. In this case vertical sleeves will be arranged in the foundation to receive an array of piles 400 or anchors 404 extending through the foundation, to allow for additional loading capacity and improve the stability of the foundation. Piles 400 are secured to the foundation by filling the sleeves with marine grout.
Under some conditions, the use of piles 400, piers 402 or suction piers 403 or anchors 404 may eliminate the slab 20 and/or the perimeter beams 190 from the design. In another embodiment shown in
Obviously, many modifications and variations of the present invention are possible in light of the above teachings. It is therefore to be understood that, within the scope of the invention.
This application is a continuation of Ser. No. 15/916,724, filed Mar. 9, 2018, which is a continuation of Ser. No. 15/530,081 filed Dec. 1, 2016, which is a continuation of application Ser. No. 15/137,157 filed Apr. 25, 2016 now U.S. Pat. No. 9,534,405 issued Jan. 3, 2017, which is a continuation of application Ser. No. 14/748,241 filed Jun. 24, 2015 now U.S. Pat. No. 9,347,197 issued May 24, 2016, which is a continuation of application Ser. No. 14/176,160 filed Feb. 10, 2014 now U.S. Pat. No. 9,096,985 issued Jul. 4, 2015, which is a continuation of application Ser. No. 13/319,083 filed Jul. 5, 2010 now U.S. Pat. No. 8,661,752 issued Mar. 4, 2014, which claims the benefit of provisional applications 61/215,430 filed May 5, 2009, 61/269,800 filed Jun. 29, 2009, 61/284,901 filed Dec. 28, 2009, 61/339,550 filed Mar. 5, 2010 and claims priority from PCT/US/2010/041006 and is a continuation-in-part of patent application Ser. No. 12/774,727 filed May 6, 2010, which is a continuation-in-part of patent application Ser. No. 11/859,588 filed Sep. 21, 2007 which claims the benefit of provisional applications 60/826,452 filed Sep. 21, 2006 and 60/954,502 filed Aug. 7, 2007.
Number | Name | Date | Kind |
---|---|---|---|
4911585 | Vidal et al. | Mar 1990 | A |
6672023 | Henderson | Jan 2004 | B2 |
9938685 | Krause | Apr 2018 | B2 |
20070181767 | Wobben | Aug 2007 | A1 |
Number | Date | Country |
---|---|---|
7637601 | Mar 1977 | DE |
3336655 | Apr 1985 | DE |
Number | Date | Country | |
---|---|---|---|
20190263020 A1 | Aug 2019 | US |
Number | Date | Country | |
---|---|---|---|
61339550 | Mar 2010 | US | |
61284901 | Dec 2009 | US | |
61269800 | Jun 2009 | US | |
61215430 | May 2009 | US | |
60954502 | Aug 2007 | US | |
60826452 | Sep 2006 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 15916724 | Mar 2018 | US |
Child | 16407692 | US | |
Parent | 15530081 | Dec 2016 | US |
Child | 15916724 | US | |
Parent | 15137157 | Apr 2016 | US |
Child | 15530081 | US | |
Parent | 14748241 | Jun 2015 | US |
Child | 15137157 | US | |
Parent | 14176160 | Feb 2014 | US |
Child | 14748241 | US | |
Parent | 13319083 | US | |
Child | 14176160 | US |
Number | Date | Country | |
---|---|---|---|
Parent | 12774727 | May 2010 | US |
Child | 13319083 | US | |
Parent | 11859588 | Sep 2007 | US |
Child | 12774727 | US |