Claims
- 1. A method of drilling a flowline below the surface, the method comprising the steps of:
establishing a first sight relief hole and a second sight relief hole along the linear path; positioning a directional drilling machine on the surface, the directional drilling machine having a boring stem; boring a first portion of a pilot hole from the surface to the first sight relief hole; determining the elevation of the tool at the first sight relief hole; and adjusting the position of the tool at the first sight relief hole to a first desired depth; boring a second portion of the pilot hole from the first sight relief hole to the second sight relief hole; determining the elevation of the tool at the second sight relief hole. adjusting the position of the boring tool to a second desired depth.
- 2. The method of claim 1 further comprising reaming the pilot hole and locating the pipe.
- 3. The method of claim 1 wherein the position of the boring tool is determined by placing a measuring device within the first or second sight relief hole and measuring the depth of the tool.
- 4. The method of claim 3 wherein the depth of the tool is measured with reference to a laser beam, the laser beam emitted from a transit located on the surface.
- 5. The method of claim 4 wherein each sight relief hole is generally vertical.
- 6. The method of claim 1 further comprising:
establishing a third sight relief hole; boring a third portion of the pilot hole to the third sight relief hole; determining the position of the boring tool at the third sight relief hole, and adjusting the position of the boring tool.
- 7. The method of claim 6 wherein the second sight relief hole is equidistant from the first and third sight relief holes.
- 8. A method for directionally boring a flowline, the method comprising the steps of:
establishing a number of sight relief holes along the desired path of the bore; directionally drilling a pilot hole; reaming the material around the pilot hole to define a bore, the bore filled at least partially filled with a slurry of the reamed material, and pulling a pipe into the bore wherein a portion of the slurry is displaced into the sight relief holes so that pressure does not develop around the pipe.
- 9. The method of claim 8 wherein the sight relief holes are generally vertical.
- 10. The method of claim 9 wherein the sight relief holes are spaced at equal distances from one another.
- 11. The method of claim 10 wherein the diameter of each sight relief hole is greater or smaller than the diameter of the bore.
- 12. The method of claim 8 wherein directionally drilling the pilot hole includes checking the depth of the pilot hole at each sight relief hole prior to drilling to the next sight relief hole on the linear path.
CROSS-REFERENCE TO RELATED APPLICATIONS
[0001] This application claims priority of U.S. Provisional Application No. 60/201,387, filed May 3, 2000.