The invention relates to a method of making a seamless hot-finished steel pipe.
Following the invention by the brothers Mannesmann to produce a thick-walled hollow tubular ingot from a heated billet, many different proposals have been suggested to stretch this hollow tubular ingot in a same hot-working step at same temperature. Keywords include the continuous rolling process, the rotary-forged process, the piercing mill process, and the Pilger step-by-step rolling process (Stahlrohr-Handbuch [Steel Pipe Handbook], 10. ed; Vulkan-Verlag Essen, 1986, III. Manufacturing Processes).
All mentioned processes have their benefits for different size ranges and materials, whereby combinations are possible as well. The continuous rolling process and the piercing mill process are applicable for the size range of 5″ to 18″, the Pilger-mill process is applicable for the size range of up to 26″. When a thicker wall in the range of >30 mm is involved, the continuous rolling process and the piercing mill process are less suitable while the Pilger-mill process, although not encountering any problems with the wall thickness, exhibits a production cycle that is slower. A drawback common to all mentioned processes is the more or less long modification times during a change in size.
The three stages piercing- stretching- reduction-rolling are a characteristic for the production of seamless pipes from a heated billet (H. Biller, Das Walzen nahtloser Rohre—Probleme der Verfahrensauswahl [Rolling of Seamless Tubes—Problems of Process Selection], Stahl und Eisen 106 (1986), No. 9, pages 431-437).
For some time, attempts have been made to save a step in order to lower production and assembly costs. These attempts have shown little success to date.
DE 1 906 961 A1 discloses a method of making seamless tubes from hollow bodies produced by continuous casting. In this known process, the cast strand is divided and the respective section is initially stretched with the assistance of an internal tool and rolling by hot forging. Thereafter, the pre-stretched section is rolled to a tube (shell) by a continuous rolling train, and a finished pipe is made thereform through subsequent stretch-reduction. This proposed process should be applied for mass production of pipes of small diameter from hollow bodies made through continuous casting. The proposal is intended to overcome the problem of excessive strain of the skew rolls during initial stretching.
It is an object of the invention to provide a production method for seamless hot-finished steel pipes, which has superior yield and productivity than known methods for the size range of 5″ to 30″ outer diameter and wall thicknesses ≧0.1×outer diameter for the range of 5″ to <16″ outer diameter or >40 mm wall thickness for the range of 16″ to 30″ outer diameter, but also for small lot sizes.
Based on the preamble, this object is attained by a method of making a seamless hot-finished steel pipe, in which originating from a billet heated to a shaping temperature, a first shaping produces through a piercing step a thick-walled hollow ingot which is subsequently elongated in a second shaping step at same temperature through rolling accompanied by a change in diameter and wall thickness to form a tube (shell), and from which a finished pipe is produced in a third shaping step through reduction rolling, wherein the second and third shaping steps defined by rolling are replaced by one shaping step in the form of a radial forging process, using an internal tool inserted in the hollow ingot and at least two forging jaws of a forging machine which act on the outer surface area of the hollow ingot, wherein the hollow ingot is turned and axially advanced in a clocked manner in the idle stroke phase of the forging laws.
According to the teaching of the invention, the previously known second and third shaping steps defined by rolling (stretch-rolling and reduction-rolling) are replaced by one shaping step in the form of a radial forging process, using an internal tool pushed into the hollow ingot and at least two forging jaws of a forging machine for acting on the outer surface area of the hollow ingot, whereby a turning and axial advance of the hollow ingot is clocked in the idle stroke phase of the forging jaws. Depending on the type of control, the turning and axial advance of the hollow ingot may be executed simultaneously or time-staggered.
The proposed method has the advantage of allowing an optimal production also of thick-walled tubes while keeping retrofitting times low. Similar to Pilger-milling, the stretching process produces through forging a high elongation also of very thick-walled tubes. As a result, also thick-walled pipes of great pipe length can be produced. A further advantage is the possibility to eliminate the need for the downstream sizing mill, which is otherwise necessary in the majority of applications, because now the thus-produced hot-finished pipe has the finished pipe quality after the stretching process through forging.
The proposed forging process is especially effective and of beneficial quality, when using, instead of two, a total of four forging jaws which act in one plane upon the outer surface area of the hollow ingot in synchronism. It may be advantageous for a better distribution, in particular of the thermal stress, to move the internal tool during forging in a same direction or in opposition to the axial advance.
At great stretch rate (>4) and slight wall thickness (<30 mm), it may be required to apply a separating agent and lubricant, e.g. on phosphate or graphite basis, prior to forging. This prevents the forged hollow ingot from caking together with the internal tool.
The first shaping step may selectively be a hole punching or piercing by means of skew rolls. Following hole punching, the bottom is severed or pierced. Separation may be realized by flame cutting or hot sawing. The hollow ingot produced by hole punching or piercing by means of skew rolls may be forged directly or pre-stretched by a subsequent skew rolling, before receiving the final pipe size through forging.
In this procedure, separation or piercing of the bottom may be omitted after hole punching. A two-high rolling mill or three-high rolling mill is used for skew rolling. Descaling of the outer and/or inner surface is beneficial depending on the preliminary process.
After the normal finishing steps, such as sizing, visual inspection, labeling, etc, the forged finished pipe is either ready for immediate delivery or undergoes, as previously, a heat treatment and/or a non-destructive test. Heat treatment may involve normalizing or tempering. Leveling may be required depending on the demand for straightness. Depending on the delivery demands, it may also be necessary to grind the outer surface or treat it by another suitable material-removing process to eliminate slight unevenness caused by the forging process.
The starting billet being used is either a section of a continuously cast bar, preferably a round cast bar or cast billet (ingot). Depending of the applied piercing process, materials that are difficult to shape, it may be required to pre-shape the cast through rolling or forging. Heating of the initial billet is carried out in a known manner in a rotary hearth furnace or a rocker bar type furnace. When large weights are involved, the use of other heat furnaces, such as, e.g., pit furnaces, is also conceivable.
The device for carrying out the method is characterized by a radial forging machine having a forging stand and at least two forging jaws which are replaceably arranged in the forging stand. The rotary movement as well as the axial advance of the hollow ingot is realized by a manipulator on the entry side as well as on the exit side. To minimize the possible need for leveling, it has proven advantageous to arrange a guide between manipulator and forging stand at least one the exit side. This should ensure that the forged finished pipe leaving the forging stand is substantially held truly axial.
In principle, the forging process is possible with straight forging jaws; however, the surface quality is significantly improved when each forging jaw includes on the side facing the workpiece a narrowing entry portion which terminates in a smoothing part, when viewed in length section. Viewed in cross section, the entry zone is curved concavely, with the radius being always greater in the respective cross section plane than the actual radius of the engaged hollow ingot. The greater curvature in the cross section plane results in a clamping effect. It is however not necessary to provide a separate set of forging jaws for each entry diameter of the hollow ingot; Rather, one set is able to cover a range of different entry diameters.
The inner diameter as well as the inner contour as viewed along the length of the forged finished pipe is essentially determined primarily by the type of internal tool, preferably in the form of a cylindrical mandrel.
The use of a slightly conical mandrel increases the clearance between the forged finished pipe and the internal tool so that the withdrawal of the finished pipe from the internal tool is facilitated. The conicity should, however, be only slight because otherwise the wall thickness, as viewed over the length, would inadmissibly alter.
The use of a stepped mandrel could be useful for the production of axles with thickened ends. Depending on the type of gradation, it may also be possible to make several axles from a hollow ingot. Singling could subsequently be carried out.
A further field of application would be the production of threaded pipes in the form of an integral connection. There would also be the option to directly forge the socket in so-called socket pipes instead separately.
The method according to the invention will be described in greater detail with reference to two schematic illustrations.
It is shown in
In this exemplified embodiment, the piercing unit is designed as skew rolling mill 4 with two skew rolls 5, 5′, and includes an internal tool, comprised of a piercing mandrel 6 and a holding rod 7. As piercing by means of skew rolls is generally known, a more detailed discussion is omitted. Following the piercing step and possible removal of a bottom of the billet 1, the hollow ingot 8 may be descaled on the inside and outside.
Piercing the billet 1 produces a hollow ingot 8 which is fed via a transverse transport 9 to the forging machine 10. The subsequent stretching process by way of radial forging combines in accordance with the invention the otherwise typical second and third shaping steps, in lieu of the otherwise typical rolling process, be it a continuous rolling process, piercing process, or Pilger step-by-step rolling process with subsequent reduction rolls.
After insertion of the internal tool 11, preferably in the form of a cylindrical mandrel, the hollow ingot 8 is transported by a manipulator 13 on the entry side longitudinally through the forging stand 14 and turned at the same time. This rotation and the axial advance of the hollow ingot 8 is clocked in the idle stroke phase of the forging jaws either simultaneously or time-staggered. A guide 29 is provided on the entry side of the forging stand 14 for guiding the hollow ingot 8 during its advance.
On the exit side, a second manipulator 12 receives later the finished pipe 16 in order to allow conclusion of the forging process. The forging unit is shown here only schematically and includes unillustrated forging jaws which embrace the hollow ingot 8 and act upon the outer surface area in order to elongate the hollow ingot 8 through reduction of the outer diameter as well as of the wall thickness As shown in
After the stretching process through forging, the hot-finished pipe 16 is transported to the finishing line according to arrow 15 to make it ready for shipment. Finishing includes typically a sizing to length, visual inspection, labeling, and depending on demand a preceding heat treatment and/or a non-destructive test. For space-saving reasons, the hot-finished pipe 16 is shown shorter as it would be according to the elongation.
By way of example, the operating sequence shown in
The hollow ingot 8 exiting the piercing unit is fed via a transverse transport 9 to the entry side of the elongator 17. Skew rolling per-stretches the hollow ingot 8 and a hollow ingot 8′ with reduced wall thickness is produced. The diameter of the hollow ingot 8′ may be the same, smaller, or greater after initial stretching.
Subsequently, the hollow ingot 8′ can be descaled and is fed via a transverse transport 9′ to the forging machine 10, already described with reference to
By way of example, the operating sequence shown in
After passing through the elongator, a hollow ingot 8′ is produced with the dimensions of 480 mm outer diameter×120 mm wall thickness and a length of 5.8 m.
After the stretching process through forging, the hot-finished pipe 16 has an outer diameter of 339.7 mm with a wall thickness of 75 mm and a length of 12.6 m.
The curved arrow 24 as well as the axial arrow 25 are intended to emphasize that the hollow ingot 8′ is rotated and axially advanced during the idle stroke of the forging jaws 21-21′″.
In length section, each forging jaw 21-21′″ has a predominantly conically designed entry portion 26 which terminates in a smoothing part 27. The entry part 26 may also be curved slightly convex.
As shown in cross section (
The movement arrows 28, depicted in
Number | Date | Country | Kind |
---|---|---|---|
10 2004 052 406 | Oct 2004 | DE | national |
10 2005 052 178 | Oct 2005 | DE | national |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/DE2005/001944 | 10/25/2005 | WO | 00 | 10/27/2008 |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2006/045301 | 5/4/2006 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
1497467 | Aiken, Jr. | Jun 1924 | A |
3036696 | Zimpel | May 1962 | A |
3893321 | Braunwieser | Jul 1975 | A |
4157026 | Braunwieser | Jun 1979 | A |
4190887 | Yoshiwara et al. | Feb 1980 | A |
4578974 | Pozsgay et al. | Apr 1986 | A |
4899570 | Mills et al. | Feb 1990 | A |
6024808 | Kondo et al. | Feb 2000 | A |
6799357 | Webb et al. | Oct 2004 | B2 |
Number | Date | Country |
---|---|---|
1 906 961 | Jun 1971 | DE |
0 610 509 | Aug 1994 | EP |
873 988 | Aug 1961 | GB |
62 197237 | Aug 1987 | JP |
1 634 355 | Mar 1991 | SU |
Number | Date | Country | |
---|---|---|---|