The present invention relates to a method of manufacturing a series of prefabricated prefinished volumetric construction (PPCV) modules; and to a method of assembling the same.
Prefinished-Prefabricated-Volumetric-Construction (PPVC) units are currently being used to quickly and efficiently construct buildings. This construction technique requires neighbouring units to be coupled together. Any such couplings need to ensure adequate structural continuity between adjacent modules. It is generally desirable to provide an effective and cost efficient module connection system.
It is desirable to construct PPVC modules such that the modules can be assembled with very small tolerances. It is also desirable to ensure that joined modules provide vertical and horizontal structural continuity.
It is generally desirable to overcome or ameliorate one or more of the above mentioned difficulties, or at least provide a useful alternative.
According to the present invention, there is provided a method of manufacturing a series of prefabricated prefinished volumetric construction (PPCV) modules, including the steps of:
Preferably, the method also includes the steps of:
Preferably, one or more vertically extending locking channels are cast into outer articular surfaces of the side walls of each module. The locking channels span an entire wall height of the walls of each module. The locking channels of each module are lipped. The lipped channels are coupled to studs of reinforcement bars installed in the walls of the modules during the casting step.
According to the present invention, there is also provided a method of assembling a plurality of prefabricated prefinished volumetric construction (PPCV) modules, each being formed in accordance with the above described method, including the steps of:
Preferably, the step of positioning includes arranging corresponding locking channels to overly one another to form combined locking conduits of vertical locks. The step of coupling includes the steps of pouring grout into the vertical locks. The locks ensure the horizontal mechanical continuity of the slabs of the modules to transfer horizontal forces to the various resisting members.
Preferably, the method includes the step of applying a compression force between the modules. The step of applying the compression force is achieved through installing a pre-stressing cable through the modules.
The above described methods preferably provide an effective and cost efficient module connection system.
The above described methods allow assembly of PPVC modules with very small tolerances. The joined modules preferably provide vertical and horizontal structural continuity.
Preferred embodiments of the present invention are hereafter described, by way of non-limiting example only, with reference to the accompanying drawing in which:
The series of prefabricated prefinished volumetric construction (PPCV) modules 10 shown in
With reference to
The casting rig 20 includes any suitable configuration that facilitates soft fit of each module such that they can slide to allow for removal (positioning key 66 needs to be disengaged). To reduce friction, the casting rig 20 is either fitted with rollers or sitting on Teflon™ pads. For illustrative purposes, the casting rig is below described with reference to the rig 20 including a metal plate 24 separated from a base section 26 by a plurality of angle bar members 28.
The plate 24 and the angle bar members 28 are preferably 8 mm thick. The casting rig 20 also includes a raised section 30 that sits on top of the metal plate 24. The raised section 30 is defined by additional metal plate 32 separated from the plate 24 by additional angled bar members 24. The raised section 30 acts to create a recess in a bottom section of the slab 12 so as to reduce the weight of the slab 12 and the amount of concrete needed to be used.
The metal plates 18a, 18b are preferably 3000 mm apart. Alternatively, the plates 18a, 18b can be separated by any suitable distance to meet the requirements of a particular project. The plates 18a, 18b are preferably 8 mm thick and have a height of 230 mm. Again, any other suitable dimensions are anticipated to suit the needs of a particular project.
The resultant slab 12 has a thickness of 230 mm at its edges and a thickness of 120 mm at its centre. Any other thicknesses can also be achieved to meet any particular requirement.
With reference to
With reference to
Following manufacture of the first module 10a in the series, the subsequent modules 10b, . . . are manufactured by following the steps set out below:
The side walls 14a, 14b of each module in the series 10 of modules are matched to corresponding side walls 14a, 14b of neighbouring modules in the series of modules 10.
As particularly shown in
The casting rig 20 includes an additional raised section 30 that sits on top of the metal plate 24. The raised section 30 is defined by additional metal plate 32 separated from the plate 24 by additional angled bar members 24. The additional raised section 30 acts to create a recess in a bottom section of the slab 12 so as to reduce the weight of the slab 12 and the amount of concrete needed to be used. Any other thicknesses can also be achieved to meet any particular requirement.
The resultant slab 12 has a thickness of 230 mm at its edges and a thickness of 120 mm at its centre.
With reference to
The close wall formwork panels are separated by a gap of 100 mm. This will be the resultant thickness of the walls. For a 250 mm wall 14a, 14b, the setup will be with 125 mm (half of the wall thickness).
Of course, any other suitable thickness for the walls can be used. Reinforcement bars are included in the formwork to strengthen the walls 14a, 14b. The concrete is poured into the formwork 36 of each wall 14a, 14b to a height of 3200 mm, for example. Alternatively, any suitable alternative height for the walls 14a, 14b can be used. The formwork 36 remains in place whilst the concrete sets.
With reference to
Finally, as shown in
In order to reduce the force required to separate the modules 10a, 10b, and in particular at the 100 mm thick wall area, the modules 10a, 10b preferably include polyethylene sheets 43. In this embodiment, the match cast surface for the walls 14b, 14a does not need to extend across the entire surface. Match cast is chiefly required at base 12 and top slab area 16, the vertical edges of the module 10 and around the vertical locks 50.
The first module 10a is taken away by a lifting module in the manner shown in
The above-described method improves upon issues relating to construction tolerance between elements by providing a perfect match when the elements are put back together. Furthermore, the above-described method ensures accurate finishing material continuity after erection.
The formwork is not described in detail. However, it is understood to include sophisticated formwork techniques, such as tunnel forms in which the walls and the ceiling slabs are poured simultaneously, could be used to speed up the fabrication process.
The method of assembling the plurality of PPCV modules 10, includes the steps of:
It is desirable for the two half-walls 14b, 14a of adjoining modules 10a, 10b to be a monolithic member with a width equal to the sum of the thickness of the single elements. The vertical locks 50 on adjoining modules 10a, 10b facilitate this function in the manner shown in
As particularly shown in
Studs 54 welded onto the steel section 56 forming the locks ensure the lock 50 is tied to the reinforcement bars 58a, 58b in each half wall 14a, 14b. To ensure the mechanical continuity of these locks 50, “C” channels 60 are inserted in the locks 50 and cement slurry 62 is poured into the internal volume to seal the various elements.
The lock 50 can also been formed using other types of steel sections 56 working in conjunction with grout 62. The grout 62 has the additional benefit of protecting the steel section against corrosion to ensure the system durability.
The locks 50 preferably span the entire wall height and form a mechanical connection between the two half-walls 14b, 14a of adjoining modules. The locks 50 replace the links or stirrups found in conventional reinforced concrete construction. The locks 50 also ensure the horizontal mechanical continuity of the slab 12 (diaphragm) that is required to transfer the horizontal forces to the various resisting members.
As shown in
In the following calculation note, in order to assess the performance of the lock 50, this effort is taken as 40 t/m2 (the magnitude of this effort is greatly overestimated).
It is also assumed that locks 50 are spaced 1 m center to center, giving a pulling effort of 0.4 MN/m.
Considering:
We get a tension stress in the steel member of:
This is to be compared to
s=235 MPa
We consider that the tension effort is transferred between the flat bar 70 and the U channel 56 by struts that are developing in the grout orientated with a 45° angle as shown in
Considering a pulling effort N of 0.4 MN, we can define the compressive stress in the grout as:
Where Ag is the strut sectional area:
Ag=0.032.cos.45°=0.0226 m2
This is to be compared to the compressive resistance to the grout 62 that we take as:
g=80 MPa
The friction stress between the steel surface and the grout is given by:
Where:
This is to be compared to the allowable shear stress:
Where:
As shown in
As shown in
The connector 57 are pre-positioned in the formwork before the module pouring. This sleeve 57 consist of a steel tube in which vertical rebars 58a from the upper and lower modules 10a, 10c are located and are abutting. The continuity is achieved by pouring grout that will transfer a load from the rebar 58a, to the sleeve 57, and then from the sleeve 57 to the other rebar 58a. The grouting is achieved by pumping grout in the injection port 61 that is located at the base of the connector, until it escape from the venting port that is located at the top of the connector. In our case, as the grouting will be performed for a series of connectors, we will connect the venting port to the injection port of the next connector.
Epoxy glue will be preferably be applied to the match cast surface. This has at least the following benefits:
With reference to
To ensure key 66 effectiveness for the accurate positioning of modules 10 in relation to one another, a compression force must be applied between the modules 10. This is achieved through a pre-stressing cable positioned in a duct 68 installed in the slab 12 of the module floor. Other methods can also be used to apply the force, such as using hydraulic jacks fixed on the roof of the modules already installed. This operation is done in order to achieve very accurate positioning of a module 10b in relation to an adjacent module 10a that is already placed. To be efficient, this compression force needs to be applied in order for the positioning key 66 to engage and displace the module 10b sideway if not align satisfactorily.
To facilitate easier separation of matched modules during the module construction phase, separation apparatus 100 can be inserted into the locking channels 52. As shown in
The balloons 106a, 106b are connected to a pneumatic or fluid pump which, when activated, cause the balloons 106a,106b to inflate outwardly in opposite directions from their respective recesses 104a, 104b. The inflating balloons 106a, 106b abut respective channels 52 and apply a force thereto in the direction in which they are inflating (i.e. away from their recesses 104a, 104b). Continued inflation thereby causes the channels 52 of the two module 10a, 10b to move in opposite directions and separate.
An alternative embodiment of the separation apparatus 100 is shown in
The pairs of jacks 114 are connected to a pump which, when activated, cause the jacks to expand outwardly in opposite directions. The expanding jacks 114 abut respective channels 52 and apply a force thereto in the direction in which they are expanding (i.e. away from the shaft 112). Continued expansion thereby causes the channels 52 of the two module 10a, 10b to move in opposite directions and separate.
Many modifications will be apparent to those skilled in the art without departing from the scope of the present invention
The reference to any prior art in this specification is not, and should not be taken as, an acknowledgment or any form of suggestion that the prior art forms part of the common general knowledge in Australia, Singapore or any other jurisdiction.
In this specification and the claims that follow, unless stated otherwise, the word “comprise” and its variations, such as “comprises” and “comprising”, imply the inclusion of a stated integer, step, or group of integers or steps, but not the exclusion of any other integer or step or group of integers or steps.
References in this specification to any prior publication, information derived from any said prior publication, or any known matter are not and should not be taken as an acknowledgement, admission or suggestion that said prior publication, or any information derived from this prior publication or known matter forms part of the common general knowledge in the field of endeavour to which the specification relates.
Number | Date | Country | Kind |
---|---|---|---|
10201603706Q | May 2016 | SG | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/SG2017/050219 | 4/20/2017 | WO | 00 |