Claims
- 1. A method of molding cementitious material comprising:
- charging wet cementitious material into a molding mold;
- disposing a first mold frame about the wet cementitious material;
- charging filler material under air permeable conditions directly onto the wet cementitious material;
- disposing a shield layer which is impermeable over the filler material;
- fixing the filler material under reduced pressure caused by suction applied through a source of suction to form a hardening mold;
- retaining the cementitious material on the hardening mold; and
- permitting the cementitious material is set upon the hardening mold.
- 2. The method according to claim 1 further comprising:
- detaching the molding mold after the cementitious material has set so as not to deform the cementitious material; and
- permitting the molded cementitious material to harden on the hardening mold.
- 3. The method according to claim 1 wherein the molded cementitious material is detached from the hardening mold by applying compressed air to the filler material.
- 4. The method according to claim 1 wherein the filler material is moist sand.
- 5. The method according to claim 1 wherein the cementitious material charged into the molding mold is a slurry of water and water settable inorganic material selected from the group of portland cement, slag cement, alumina cement, Roman cement, natural cement, hydraulic lime, magnesia cement, lime, gypsum and mixtures thereof with or without an aggregate or a fibrous reinforced material.
- 6. The method according to claim 1 wherein the cementitious material contains glass fiber.
- 7. The method according to claim 1 wherein said first mold frame has one or more open faces covered with an air impermeable film.
- 8. The method according to claim 1 further comprising prior to said step of disposing said first mold frame about the cementitious material;
- disposing a first shield layer over a master model;
- disposing a second mold frame about the master model;
- disposing filler material within the second mold frame;
- disposing a second shield layer which is impermeable over the filler material;
- operatively connecting the filler material to a source of suction through means of a filter to fix the filler material under a reduced pressure condition to form the molding mold;
- turning the mold frame, the master model, the filler material and the first and second shield layers upside down; and,
- removing the master model.
- 9. The method according to claim 8 wherein the molded cementitious material is detached from either the molding and/or the hardening mold by applying compressed air to the filler material and/or the additional filler material.
- 10. A method of molding a wet cementitious material comprising:
- charging a slurry of wet cementitious material into a molding mold;
- placing a frame, equipped with a filter connected to a suction pump around the molding mold;
- charging a filler material directly onto the wet cementitious material;
- disposing a shield layer which is impermeable to cover the filler material;
- fixing the filler material within the frame under a reduced pressure condition caused by suction through the filter to form a hardening mold;
- detaching the molded cementitious material from the molding mold and retaining the molded cementitious material with respect to the hardening mold; and
- discontinuing the reduced pressure within the frame after the mold cementitious material has set.
- 11. A method of molding a cementitious material comprising:
- placing a first frame, equipped with a first filter connected to a suction pump, around a master model having a first shield layer thereon;
- charging first filler material into the first frame to cover the first filter under permeable conditions;
- disposing a second shield layer which is impermeable to cover the first filler material;
- turning upside down the master model, the first and second shield layers, the first frame and the first filler material;
- fixing the first filler material under a reduced pressure condition caused by suction through the first filter to form a first mold;
- removing the master model;
- charging a slurry of cementitious material into the first mold;
- placing a second frame, equipped with a second filter connected to the suction pump, upon the first frame;
- charging a second filler material onto the cementitious material;
- disposing a third shield layer which is impermeable to cover the second filler material;
- fixing the second filler material within the second frame under a reduced pressure condition caused by suction through the second filter to form a second mold;
- detaching the molded cementitious material from the first mold and retaining the molded cementitious material with respect to the second mold; and
- discontinuing the reduced pressure within the second frame after the molded cementitious material has set.
Priority Claims (2)
Number |
Date |
Country |
Kind |
50-19429 |
Feb 1975 |
JPX |
|
50-19430 |
Feb 1975 |
JPX |
|
Parent Case Info
This is a continuation, of application Ser. No. 659,081 filed Feb. 18, 1976 now abandoned.
US Referenced Citations (6)
Continuations (1)
|
Number |
Date |
Country |
Parent |
659081 |
Feb 1976 |
|