The present invention relates to a method of reducing inflow of rock particles from an earth formation into a wellbore for the production of hydrocarbon fluid. Often the reservoir rock is loosely consolidated, so that it tends to disintegrate and flow into the wellbore under the influence of hydrocarbon fluid flowing through the pore spaces.
Such inflow of rock particles, generally referred to as sand production, is a frequently occurring problem in the industry of hydrocarbon fluid production, as the produced sand particles tend to erode production equipment such as tubings and valves. Conventional methods of sand control include the installation of supporting perforated liners or screens, which allow the hydrocarbon fluid to pass but exclude the sand particles. Also, gravel packs are installed between the liners or screens and the wellbore wall to control sand production. Although such liners, screens and gravel packs have often been successfully applied, there are potential drawbacks such as clogging of the perforations, screens or gravel packs leading to diminished fluid production. Hence there is a need for an improved method of sand control.
It is therefore an object of the invention to provide an improved method of reducing inflow of rock particles into a wellbore for the production of hydrocarbon fluid, which method overcomes the drawbacks of the prior art.
In accordance with the invention there is provided a method of reducing inflow of rock particles from an earth formation into a wellbore for the production of hydrocarbon fluid, the method comprising creating a zone of reduced compressive stiffness around the wellbore by removing rock material from the wall of the wellbore.
It is thereby achieved that stress concentrations in the rock material at, or adjacent to, the wellbore wall are relieved. Such stress concentrations are due to the presence of the wellbore in the rock formation, whereby the originally undisturbed stresses in the rock formation have become disturbed. The disturbed stresses include high shear stresses in the near wellbore region, which often lead to local failure of the rock formation thereby inducing sand production. By reducing the compressive stiffness in a zone around the wellbore, the relatively high shear stresses in the near-wellbore region are relieved so that the risk of local failure of the rock formation is reduced.
It is preferred that the step of removing rock material from the wellbore wall is carried out in an open-hole section of the wellbore, that is to say, an uncased section of the wellbore.
Suitably the step of removing rock material from the wellbore wall comprises removing rock material from at least one elongate section of the wellbore wall.
Preferably each elongate section has a longitudinal axis extending in axial direction of the wellbore.
It is to be understood that the elongate section does not need to extend parallel to the longitudinal axis of the wellbore, but can, for example, extend in the form of a helix along the wellbore wall.
Generally the earth formation surrounding the wellbore is subjected to stresses including first, second and third principal stresses. It is preferred that said elongate section extends radially in a direction substantially perpendicular to a selected one of said principal stresses.
Suitably said elongate section extends radially in a direction substantially perpendicular to the largest a selected one of said principal stresses.
In case the wellbore extends substantially vertically, it is preferred that said elongate section extends radially in a direction substantially perpendicular to the largest horizontal principal stress.
In case the wellbore extends substantially horizontally, it is preferred that said elongate section extends radially in a direction substantially perpendicular to the vertical principal stress.
Preferably said rock material is removed from the wellbore wall by creating a plurality of perforations in the wellbore wall, for example in the form of an array of perforations. The perforations are preferably closely spaced. Alternatively the rock material is removed by creating a slot in wellbore wall, for example a slot extending in axial direction of the wellbore.
Suitably the slot is wedge shaped in a cross-sectional plane of the wellbore, whereby the width of the slot decreases in radially outward direction.
The slots or perforations can be open (i.e. filled with gas or liquid) or filled with a flexible material.
The invention will be described hereinafter in more detail and by way of example, with reference to the accompanying drawings in which:
In the Figures, like reference signs relate to like components.
Referring to
In
In
In
In
In
During normal use the wellbore 1 is drilled to a depth near the hydrocarbon fluid containing formation zone 3, the casing 4 is installed, and cement is pumped between the casing 4 and the wellbore wall to form the layer of cement 7. Subsequently the wellbore 1 is further drilled through the formation zone 3. Before production of hydrocarbon fluid from formation zone 3 is commenced, the injection string 8 is lowered into the wellbore 1 such that the jet cutter 12 is located near the bottom of the wellbore 1 (
If the wellbore 1 extends substantially horizontally through the formation zone 3 (
In the embodiment shown in
In the embodiment shown in
An important effect of the slots 16, 32, 42 or the rows of perforations 24, is the formation of an annular zone 60 of reduced compressive stiffness around the wellbore 1, 30, 40. The thickness of the zone 60 is about equal to the depth of the slots 16, 32, 42 or the perforations of the rows 24. The compressive stiffness of the zone 60 is reduced because the slots 16, 32, 42 form open spaces between sections of rock 62, which open spaces allow some circumferential compression of the annular zone 60 under the effect of the governing formation stresses. As a result the stresses in the annular zone 60 sections of rock material 62 between the slots 16, 32, 42 are relieved somewhat. By the reduction of the stresses in the annular zone 60, the stresses in the rock material outside the annular zone 60 increase somewhat as schematically illustrated in
With the method of the invention it is achieved that the relatively high shear stresses near the wellbore wall are relaxed, so that the tendency of local failure of rock material near the wellbore wall is reduced. It will be appreciated that such reduced tendency of failure of rock material near the wellbore wall leads to a desired reduction of inflow of rock particles (sand particles) into the wellbore during the production of hydrocarbon fluid from the earth formation zone.
Instead of creating slots or rows of perforations, in the open-hole section of a wellbore, such slots or rows of perforations suitably can be formed in the rock formation behind a perforated liner or casing.
Instead of creating the slots using the jet cutter described hereinbefore, the slots can be created by a mechanical device such as a chain saw, or by an explosive charge.
Instead of the elongate section extending parallel to the longitudinal axis of the wellbore, or in the form of a helix along the wellbore wall, the elongate section can extend in a plane substantially perpendicular to the longitudinal axis of the wellbore. Thus, in such embodiment the elongate section has a circular shape.
Number | Date | Country | Kind |
---|---|---|---|
03257143.2 | Nov 2003 | EP | regional |
Filing Document | Filing Date | Country | Kind | 371c Date |
---|---|---|---|---|
PCT/EP04/52899 | 11/10/2004 | WO | 5/10/2006 |