The present invention generally relates to systems and methods for moving large temporary buildings, including fabric structure buildings which can be used to remediate waste sites.
The remediation of contaminated waste sites (e.g., manufactured gas plant (MPG) remediation) involves such conventional techniques as excavation and off-site disposal of wastes, chemical fixation, soil washing, in-situ thermal treatment, incineration of excavated soil and other technologies. In some instances, a large temporary building, resembling a large tent, is erected over a first area of the site, and clean-up activities are carried out inside the tent to contain fugitive air emissions. The size of the tent-like building can vary, e.g., from 20-40 meters or more wide and 20-60 meters or more long. After clean-up of the first area is finished, the tent is disassembled, moved to a second area of the site, and re-assembled so that clean-up can continue. This procedure is repeated until all areas of the site have been remediated. The process of disassembling the temporary building, moving it from one site area to another, and then re-assembling the building, is time-consuming, typically taking six or seven weeks. As a result, completion of the clean-up is delayed. Moreover, resources on the site, such as remediation equipment and personnel, consulting personnel, and air monitoring equipment and personnel, remain largely idle during the delay, which unavoidably increases overhead costs.
There is a need, therefore, for a more efficient way to move large temporary buildings.
This invention is directed to, among other things, a method of moving a large temporary building from a first location to a second location. The building has a first side and a second side opposite the first side, a frame, and a cover supported by the frame. The method comprises the steps of connecting a plurality of leading dollies to the frame of the building at the first side of the building, each dolly comprising a platform with caster wheels and a lifting device on the platform. Another step of the method involves connecting a plurality of trailing dollies to the frame of the building at the second side of the building, each trailing dolly comprising a platform with caster wheels and a lifting device on the platform. At least two of the leading dollies are connected by a substantially rigid connector. The method also involves operating the lifting devices on the leading and trailing dollies to lift the building for transport, and applying a force to roll the dollies and the lifted building from the first location to the second location. The lifting devices on the leading and trailing dollies are operated to lower the building at the second location.
This invention is also directed to a transport system for moving a large temporary building of the type described in the previous paragraph from a first location to a second location. The transport system comprises a plurality of first dollies, each first dolly comprising a platform with caster wheels and a lifting device on the platform for lifting the first side of the building prior to moving the building. A substantially rigid connector is provided for rigidly connecting two of the first dollies. The system also includes a plurality of second dollies, each second dolly comprising a platform with caster wheels and a lifting device on the platform for lifting the second side of the building prior to moving the building. Each of the lifting devices comprises a lifting structure and a lifting mechanism on the platform for raising and lowering the lifting structure relative to the platform. A least one fastening device is provided for fastening each lifting structure of the first and second dollies to the frame of the building at a respective side of the building whereby the building may be lifted, rolled on the dollies from the first location to the second location, and lowered.
This invention is also directed to a method of remediating a contaminated waste site. The method involves installing a temporary building at a first location on the site, the temporary building comprising a frame and a cover, and remediating the site inside the temporary building at the first location. The method further comprises lifting the temporary building while it remains erect, moving the temporary building while it remains erect to a second location on the site, lowering the temporary building while it remains erect to place it on the site, and remediating the site inside the temporary building at the second location. The lifting, moving and lowering of the temporary building is accomplished by connecting a plurality of leading dollies to a first side of the temporary building and a plurality of trailing dollies to a second side of the temporary building, operating the dollies to lift respective first and second sides of the temporary building, applying a motive force to the leading dollies to roll the dollies and the temporary building from the first location to the second location, and operating the dollies to lower respective first and second sides of the temporary building.
Other objects and features will be in part apparent and in part pointed out hereinafter.
Corresponding reference characters indicate corresponding parts throughout the drawings.
Referring to
In general, the structure 30 is erected by raising a first arch 50 of the frame 38 to an upright position, raising a second arch 50 of the frame to an upright position in which it is parallel to the first arch and spaced from the first arch by a distance corresponding to the width of one bay 54 of the building, and connecting the two upright arches by the purlins 52 and any other accompanying framework (e.g., criss-crossing cables). Additional arches 50 and purlins 52 are successively added to the structure until the frame 38 is complete. The cover sections 46 are then attached to the arches to complete the roof of the structure. Assembly of the structure also includes attaching gable ends (not shown) to the ends 36 of the structure and installing the necessary doors and other openings (e.g., vents and exhaust ports), not shown. The structure is disassembled by reversing these steps. The assembly and disassembly process is time-consuming and labor-intensive. By way of example, the process of moving the building from one location to another by disassembling the components, transporting the components, and then reassembling the components can take 6 to 7 weeks.
The transport system 20 is used to transport the temporary building 30 from one location to another while the building remains erect, that is, without first disassembling the entire building. As a result, substantial time and expense can be saved. In general, the transport system comprises a plurality of first dollies, each generally designated 60 in
Referring to
The platform 94 comprises a metal structure including a cross beam 130 of inverted channel shape fastened to the swivel plates 116 of the two caster-wheel assemblies 90. The arrangement is such that the caster wheels 100 of the two assemblies are independently rotatable about their respective axes 120 relative to the platform 94 and to one another. The platform 94 also includes a cantilever beam 134 attached to the cross beam 130 and projecting from the trailing side of the platform. The caster-wheel assemblies 90 and platform 94 may have other configurations without departing from this invention.
Referring to
Similarly, an upper cantilever structure 188 is secured (e.g., welded) to the upper tube 166 and includes two generally parallel upper arms 190 attached to a frame member 192 rigidly secured to the upper tube 166. The upper arms 190 extend generally horizontally above the lower arms 170 and are spaced apart a distance generally corresponding to the width of an arch 50 of the frame 38. The ends of the upper arms 190 have holes 196 for receiving fasteners 198 (e.g., bolts) to releasably fasten the arms to opposite sides of the arch when the arch is received between the arms (see
The upper cantilever structure 188, including the upper arms 190, is vertically movable independent of the lower cantilever structure 168 by sliding the upper tube 166 up and down in the guide post 150, so that the upper arms 190 can be fastened to the arch 50 at a suitable location above the lower arms 170. The upper cantilever structure 188 also includes two vertical spacer members 200 rigidly attached at their upper ends to the upper arms 190. The spacer members 200 have lower ends positioned for contact with respective lower arms 170 to maintain a minimum spacing between the upper and lower arms. The lifting structure 140 may have other configurations within this invention.
It will be observed that the lower and upper tubes 164, 166 and the lower and upper cantilever structures 168, 188 are removable from the guide post 150. This construction allows the dolly 60 to be more readily used in the field and more readily disassembled for convenient transport and storage.
The lifting mechanism 142 of each leading dolly comprises at least one and desirably two cylinder mechanisms, each of which is also designated 142. (The use of two cylinder mechanisms may help prevent binding of the telescoping parts during a lifting operation.) In the illustrated embodiment, the cylinder mechanisms 142 are mounted on the platform 94 on opposite sides of the guide post 150 as the dolly is viewed in
Referring to
Referring to
The platform 252 comprises a metal structure including a cross beam 258 of inverted channel shape fastened to the swivel plates 278 of the two caster-wheel assemblies 250. The arrangement is such that the caster wheels 260 of the two assemblies are independently rotatable about their respective axes 282 relative to the platform 252 and to one another. The caster-wheel assemblies 250 and platform 252 may have other configurations without departing from this invention.
The lifting device 256 on each trailing dolly 70 comprises a lifting structure, generally designated 290, and a lifting mechanism 294 on the platform 252 for raising and lowering the lifting structure relative to the platform. The lifting structure 290 comprises a guide post 296 having a lower end attached to the platform 252, and a lift frame 300 mounting for sliding movement up and down relative to the guide post. In the illustrated embodiment, the guide post 296 is a metal tube of rectangular (square) cross section. The lift frame 300 comprises a lower tube 304 of similar cross-sectional shape capable of sliding on the outside of guide post 296 and an upper tube 308 of similar cross-sectional shape movable on the inside of the guide post. A lower cantilever structure 312 is secured (e.g., welded) to the lower tube 304 and includes two parallel lower arms 316 attached to a frame member 320 rigidly affixed to the lower tube 304. The lower arms 316 extend generally horizontally and are spaced apart a distance generally corresponding to the width of an arch 50 of the frame 38. Mounting plates 324 at the ends of the arms 316 have holes 326 for receiving fasteners 330 (e.g., bolts in
Similarly, an upper cantilever structure 332 is secured (e.g., welded) to the upper tube 308 and includes two parallel upper arms 334 attached to a frame member 338 rigidly affixed to the upper tube 308. The upper arms 334 extend generally horizontally above the lower arms 316 and are spaced apart a distance generally corresponding to the width of an arch 50 of the frame 38. The ends of the arms 338 have holes 342 for receiving fasteners 346 (e.g., bolts in
The upper cantilever structure 332 of the trailing dolly 70, including the upper arms 334, is vertically movable relative to the lower cantilever structure 312 by sliding the upper tube 308 up and down inside the guide post 296, so that the upper arms 334 can be fastened to the arch 50 at a suitable location above the lower arms 316. The upper cantilever structure 330 also includes two vertical spacer members 360 rigidly attached at their upper ends to the upper arms. The spacer members 360 have lower ends positioned for contact with respective lower arms 316 to maintain a minimum spacing between the upper and lower arms. The lifting structure 290 may have other configurations within this invention.
It will be observed that the lower and upper cantilever structures 312, 332 and lower and upper tubes 304, 308 are removable from the guide post 296. This construction allows the dolly 70 to be readily disassembled for more convenient transport and storage.
The lifting mechanism 294 of each trailing dolly 70 comprises at least one and desirably two cylinder mechanisms, each of which is also designated 294. In the illustrated embodiment, the cylinder mechanisms 294 are mounted on the platform 252 on opposite sides of the guide post 296 as the dolly is viewed in
Referring to
Referring to
The transport system also includes a plurality of spreader bars, each generally designated 440, for reinforcing the frame 38 of the building 30 at locations adjacent the connections between the arches 50 and the lifting devices 96, 256 on the dollies 60, 70. One such spreader bar 440 is shown in
As shown in
Referring to
Referring to
The process for moving a building 30 using the transport system 20 will now be described. The spreader bars 440 are placed in position between adjacent arches 50 and fastened to the arches at locations adjacent (e.g., below) the connections to be made between the lower arms of the dollies 60, 70 and the arches. With the spreader bars in place, the pusher bar assemblies 80 and leading dollies 60 are moved into respective positions adjacent the arches at the leading side 32 of the building 30, as described below. The inside anchor pins anchoring the foot plates 56 to the ground are removed before the dollies are 60, 70 are moved into position.
Each pusher-bar assembly 80 is positioned by inserting the forks 422 of a suitable forklift into the beams 420 of the assembly and moving the assembly into a position generally adjacent a respective spreader bar at the leading side 32 of the building. Two leading dollies 60 are then rolled (e.g., by hand) to positions in which the end sections 406 of the pusher bar 400 are received in respective tubular socket members 410 of the two dollies, as shown in
The trailing dollies 70 are connected to respective arches 50 at the trailing side 34 of the building by rolling the dollies into positions in which their lower and upper arms 316, 334 are adjacent the arches. Suitable fastener holes are drilled in the arches to receive the fasteners 326, 342 which will secure the trailing dollies 70 to the arches. If desired, these holes can be drilled before moving the dollies into position. Each dolly 70 is connected to a respective arch 50 by fastening the lower arms 316 to the arch 50 using fasteners 326 (
With the leading and trailing dollies 60, 70 in position and fastened to respective arches 50 at the leading and trailing sides 32, 34 of the building 30, the one or more forklifts to be used in moving the building are moved into a position in which their respective forks 422 are received in the beams 420 of respective pusher bar assemblies 80. A suitable connecting member (e.g., a cable 520 tightened by a ratchet mechanism 524;
To ensure smooth travel during structure movement, the ground surface over which the dollies are to roll may be leveled. (Typically, this step will be the first step in preparing for the move.) Plywood runways may be placed on the ground along the travel path of the leading and trailing dollies. For non-linear travel, the rate of travel should be reduced so that spotters used during the relocation process can better ensure that plywood placement is along the projected travel path. A leap-frog placement approach may generally be utilized prior to reaching end-point.
The leading and trailing dollies 60, 70 are connected using the time members 480 and accompanying shackles 496, 498, 500, turnbuckles 494 and tow members 488, 490.
With the components of the transport system 20 in place as described above, the outside anchor pins anchoring the foot plates 56 to the ground are removed, and the lifting mechanisms 142, 294 of the leading and trailing dollies 60, 70 are operated to lift the leading and trailing sides 32, 34 of the building an appropriate distance (e.g., four to six inches) above the ground, or the runways if they are used, for transport of the building to a new location. The lifting process should not be carried out in bad weather conditions, such as when wind speeds are excessive (e.g., over eight mph).
The specific order of the steps described above can be varied.
The forklifts are then operated in unison to push the pusher assemblies 80 for applying the motive force necessary to roll the leading and trailing dollies 60, 70 in the desired direction and thus move the building. The application of a sufficient amount of force will cause the leading dollies 60 to roll in a direction generally perpendicular to a line defined by the leading dollies or at a suitable angle off perpendicular. The caster wheels 100, 260 of the dollies automatically swivel to allow rolling movement in the desired direction. For safety reasons, and to avoid undue stress and strain on the building, the speed of transport is typically a relatively slow creeping movement (e.g., four mph or less).
When the building 30 is moved to its new location, the cylinder mechanisms 142, 294 of the dollies 60, 70 are operated to lower the building to the ground, and the crew makes any necessary adjustments to the building frame 38 before installing the outer anchor pins to anchor the foot plates 56 to the ground to stabilize the structure. After the building has been squared and secured to the ground, the tie members 480 are removed from the dollies; the tension members 520 connecting the pusher bars 400 and fork frames are disconnected; the forklifts are disconnected from the pusher bar assemblies 80 by removing the forks 422 from the beams 420; the pusher bar assemblies are disconnected from the leading dollies 60; the spreader bars 440 are removed; and the upper and lower arms of the dollies are unfastened from their respective arches 50. The inner anchor pins are then installed. The specific order of these steps can be varied.
If desired, the temporary building 30 can be partially disassembled to divide it into separate erect sections 30A, 30B, (
The above transport system 20 can be used for moving most types of large temporary tension-fabric structure buildings, and particularly a large rectangular-shaped temporary building sized to cover a planar ground area of at least 500 square meters. In one example, the temporary building 30 has an overall length of about 35 meters, an overall width of about 36 meters, and an overall height of about 14 meters, and the building has seven bays 54 defined by arches 50 spaced at center-to-center intervals of about five meters. These dimensions may vary, e.g., lengths of 15-75+ meters, widths of 10.5-15 meters, and heights of 10-20 meters.
The above transport system 20 has particular (albeit not exclusive) application for transporting large tent-like structures used for the remediation of waste sites. In general, the process for remediating such a waste site in accordance with this invention comprises the following steps: (i) installing the temporary building at a first location on the site; (ii) remediating the site inside the temporary building at the first location (using conventional techniques) and backfilling the excavation; (iii) preparing the site and building 30 for relocation; (iv) lifting the temporary building while it is erect; (v) moving the temporary building while it remains erect to a second location on the site; (vi) lowering the temporary building while it remains erect to place it on the site, and (vii) remediating the site inside the temporary building at the second location. In accordance with this invention, the lifting, moving and lowering of the temporary building (steps (iv), (v) and (vi) above) involves connecting a plurality of leading dollies (e.g., dollies 60) to a first side of the building and a plurality of trailing dollies (e.g., trailing dollies 70) to a second side of the building, operating the dollies to lift respective first and second sides of the building, applying a motive force to the leading dollies to roll the dollies and the temporary building from the first location to the second location, and operating the dollies to lower respective first and second sides of the building. The leading and trailing dollies used in this process can be of the type described above (i.e., leading dollies 60 and trailing dollies 70).
In certain embodiments described above, the leading dollies 60 are pushed by one or more motor vehicles (e.g., forklift trucks) located inside the building to provide the motive force necessary to move the building 30 from one location to another. One advantage of pushing from inside the building is that the building can be moved to a location immediately adjacent to (e.g., abutting) a wall, structure or other boundary. However, it is contemplated that the building can be moved by applying a pulling (rather than pushing) force using one or more motor vehicles located outside the building. For example, cables could be attached to the leading dolly 60 and the trailing dolly at one side 36 of the building, and these cables could be pulled by one or more motor vehicles outside the building in a direction generally perpendicular to the arches 50. Regardless of the direction of movement, the caster wheels 100, 260 will rotate to align with the direction of movement.
When introducing elements of the present invention or the preferred embodiments(s) thereof, the articles “a”, “an”, “the” and “said” are intended to mean that there are one or more of the elements. The terms “comprising”, “including” and “having” are intended to be inclusive and mean that there may be additional elements other than the listed elements.
In view of the above, it will be seen that the several objects of the invention are achieved and other advantageous results attained.
As various changes could be made in the above constructions and methods without departing from the scope of the invention, it is intended that all matter contained in the above description and shown in the accompanying drawings shall be interpreted as illustrative and not in a limiting sense.
Number | Name | Date | Kind |
---|---|---|---|
2357633 | Cowgill, Jr. | Sep 1944 | A |
2575572 | Wickstrum | Nov 1951 | A |
3599808 | Bisson | Aug 1971 | A |
3653527 | Seymour | Apr 1972 | A |
3767071 | Harbers | Oct 1973 | A |
3887204 | Austin | Jun 1975 | A |
3990532 | Robinson | Nov 1976 | A |
4044854 | Schmitt | Aug 1977 | A |
4065892 | Lawrence | Jan 1978 | A |
4123038 | Meyers | Oct 1978 | A |
4128973 | Robinson | Dec 1978 | A |
5035537 | Rose | Jul 1991 | A |
5201152 | Heffner | Apr 1993 | A |
5356452 | Fahey | Oct 1994 | A |
5361550 | Kaden | Nov 1994 | A |
5387074 | Brown | Feb 1995 | A |
5417539 | van der Wal | May 1995 | A |
5461832 | Smith | Oct 1995 | A |
5511908 | Van Valkenburgh | Apr 1996 | A |
5622864 | Buchanan | Apr 1997 | A |
5639936 | Corte | Jun 1997 | A |
5655734 | Dahl | Aug 1997 | A |
5700109 | Hund | Dec 1997 | A |
5716186 | Jensen | Feb 1998 | A |
5863510 | Pozniak | Jan 1999 | A |
5868940 | Gurfinkel | Feb 1999 | A |
6027295 | Geppert | Feb 2000 | A |
6668496 | Clapp | Dec 2003 | B1 |
6763633 | Cote | Jul 2004 | B2 |
6846144 | Justice | Jan 2005 | B2 |
7021014 | Wolfe | Apr 2006 | B1 |
7159888 | Sutton | Jan 2007 | B1 |
7165370 | Wolfe | Jan 2007 | B1 |
7452173 | Rhodes | Nov 2008 | B2 |
20040052616 | Stanley | Mar 2004 | A1 |
20040160084 | Mason | Aug 2004 | A1 |
20050212243 | Terry | Sep 2005 | A1 |
20050223665 | Maas | Oct 2005 | A1 |
20070113488 | Wilson | May 2007 | A1 |
20070137115 | Towell | Jun 2007 | A1 |
20070266650 | Cohen | Nov 2007 | A1 |
20080111327 | Rhodes | May 2008 | A1 |
20080164078 | Rhodes | Jul 2008 | A1 |
20080184658 | Rhodes | Aug 2008 | A1 |
20090067952 | Rhodes | Mar 2009 | A1 |
Number | Date | Country | |
---|---|---|---|
20110076102 A1 | Mar 2011 | US |