Not Applicable
Not Applicable
1. Field of Invention
This invention relates to the design and construction of structures, specifically to structures with prefabricated deck units.
2. Prior Art
Full-depth precast concrete deck has gained popularity as an accelerated construction method. Use of full-depth precast concrete deck allows for the deck concrete and reinforcement to be placed in a controlled environment, improving the quality of the deck. Since the units are prefabricated, they can be delivered to a site and erected quickly.
Structures using full-depth precast concrete deck typically consist of a plurality of longitudinally spaced concrete deck units supported by longitudinal load-carrying members. This member or members is usually a single girder or multiple girders.
This member or members can be comprised of various materials including steel, concrete, wood or fiber-reinforced plastic.
To improve deck durability, it is important to have a pre-compression force across deck joints to minimize the propensity of the deck to crack under loading.
Currently, such pre-compression force is supplied via standard post-tensioning systems, which utilize post-tensioning tendons or bars within ducts. US Federal Highway Administration technical report (#FHWA-IF-09-010) and Precast/Prestressed Concrete institute State-of-the-Art Report on Full-Depth Precast Concrete Bridge Deck Panels (SOA-01-1911) provide a comprehensive summary of current engineering practice using precast deck units, showing that all current precast deck systems with longitudinal compression utilize post-tensioning systems in the deck. Other patent references, such as U.S. Pat. No. 7,475,446, U.S. Pat. No. 7,461,427, and U.S. Pat. No. 5,457,839, teach various methods of using post-tensioning systems to provide deck compression. However, using standard post-tensioning details carries with it the disadvantage of requiring additional cost and time to construct. This invention provides a more economical solution.
U.S. Pat. No. 7,475,446 B1, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, using a method to transfer longitudinal compression to the deck units under the following conditions:
The proposed method discussed herein also provides a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, but 65 applies the following differing conditions from those presented in U.S. Pat. No. 7,475,446:
Therefore, the method proposed herein eliminates the need for special end deck units to be fabricated and allows for a substantially reduced quantity of tensioned structural elements to be employed versus that presented in U.S. Pat. No. 7,475,446.
U.S. application Ser. No. 12/857,713, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via post-tensioning external to the deck, using a method to transfer longitudinal compression to the deck units under the following condition:
The proposed method discussed herein also provides a solution to introduce precompression force across deck joints via post-tensioning external to the deck, but applies the following differing condition from those presented in U.S. application Ser. No. 12/857,713:
Therefore, the method proposed herein does not require post-tensioning tendons running along or within the majority of the length of the supporting girders to provide longitudinal compression to the deck panels, as presented in U.S. application Ser. No. 12/857,713.
U.S. application Ser. No. 12/963,233, by the present inventor, teaches a solution to introduce pre-compression force across deck joints via tensioning the supporting girders themselves under the following condition:
The proposed method discussed herein also provides a solution to introduce pre-compression force across deck joints via tensioning the supporting girders themselves, but applies the following differing condition from those presented in U.S. application Ser. No. 12/963,233:
Therefore, the method proposed herein does not require the use of jacks placed within gaps in the deck as presented in U.S. application Ser. No. 12/963,233.
Accordingly, several objects and advantages of the present invention are to provide a structural system that:
Further objects and advantages will become apparent from a consideration of the ensuing description and drawings.
In accordance with the present invention a structural construction system comprises prefabricated deck units spaced along longitudinal load-carrying members. Axial compression of these prefabricated deck units is produced by external tensioned elements anchored in anchor assemblies integrated with the longitudinal load carrying members at intermediate support locations. The prefabricated deck panels are fitted with means to react against the longitudinal load-carrying members.
A preferred embodiment of the bridge construction system of the present invention is illustrated in
However, those features comprising the structural construction system mentioned in the preferred embodiment and the substructure and span arrangement mentioned above can have various embodiments not mentioned in the preferred embodiment, as discussed in detail hereinafter and as will become apparent from a consideration of the ensuing description and drawings.
Steel girders 11 are placed on and supported by abutments 12 and pier 13. Steel girders 11 are of fabricated plate girders, but may be of any suitable structural shape, such as tub girders, rolled beams, trusses, etc. Bearing stiffeners 51 typical to such support configurations are provided. A gap 22 between the girder ends at the pier 13 is provided to allow for relative movement between the steel girders 11 of each span. On top of girders 11, a plurality of leveling devices is placed to support the precast deck units 18 that also allows for relative longitudinal motion between girders 11 and the precast concrete deck units 18. In the preferred embodiment, the leveling devices are comprised of shims, however leveling bolts or other devices that can provide support for the deck and allow for relative longitudinal motion between girders 11 and the precast concrete deck units 18 can be used. As will be evident from the description hereinafter, this allowance for relative motion will allow for the precast concrete deck units to be compressed by reacting to the tensioning of girders 11. Shims may be of steel, plastic, elastomeric materials, teflon-based or teflon-impregnated materials, etc.
A plurality of voids 28, similar to those used in conventional precast deck placement, are provided in deck units 18 above girders 11 to allow for mechanical connection of deck units 18 to girders 11 while shear connectors voids 28 are grouted. Haunches 30 will also be grouted at the same time as the shear connector voids 28. Shear connectors shall be detailed to allow relative motion between precast concrete deck units 18 and girders 11 during the precast concrete deck unit erection process and prior to grouting, as hereinafter described. In the preferred embodiment, shear connectors are shear studs 26 welded to the girders 11.
Deck joints 20 between adjacent precast concrete deck units can be of the match-cast type, with or without epoxy, or cast-in-place using concrete, grout or other suitable jointing materials. In the preferred embodiment, match-cast epoxy joints are used.
In the preferred embodiment, anchor assemblies 34 are fabricated with the girders at the ends of the girders supported on the pier 13, as shown in
In the preferred embodiment, the girder connection at the pier location is simply supported for dead load and continuous for live load. This is achieved by making the girder bottom flange connection at pier after all dead loads are applied to the structure.
Alternate embodiments for the present invention are described hereinafter:
The preferred embodiment in the context of the example bridge is illustrated hereinafter.
Abutments 12 and pier 13 are constructed. Girders 11 are erected with anchor assemblies 34 pre-installed. A gap 22 between the girder ends at the pier 13 is provided to allow for relative movement between the steel girders 11 of each span.
The girder top elevation is then surveyed and the shim thickness at each supporting point calculated so as to provide the correct setting elevations for deck units. Shims are placed on top of the girders. Post-tensioning bars 33 are installed within the anchor assemblies 34 in conjunction with bearing plates 36 and nuts 38. Post-tensioning bars 33 are not stressed at this stage.
Precast deck units 18 are erected, placing one unit adjacent to the previously erected one and applying epoxy to the adjacent faces of the two units. Means is employed to provide a certain amount of compression over the epoxy joint (typically at 40 psi, similar to segmental bridge construction) to ensure the joint is properly set. This process is repeated until all deck units 18 are installed.
After all deck units are installed, deck connection units 32 are made composite with the supporting girders by grouting the shear connector voids 28 and the haunches 30 relative to the deck connection units. The post-tensioning bars 33 are then stressed. The nuts 38 are tightened against the bearing plates 36 and anchor plates 37 in conjunction with the stressing operations to lock in the stress in the post-tensioning bars 33.
After the stressing of the post-tensioning bars 33, shear connector voids 28 and haunches of all remaining deck units are grouted.
As an option, the girder bottom flange connection at the median pier 13 may then made so that the girder connection at pier location will function as continuous under subsequently applied loads. This is accomplished by placing high strength filler 54 between the bottom flange connection plates 52.
The operational description above is particular to the preferred embodiment of the present invention in the context of the two-span bridge heretofore defined. Alternate materials, member shapes, connection types at the median piers, means of stressing, etc. can be used in employing the structural construction system of the present invention.
The present invention provides a structural system that eliminates many of the drawbacks found in current precast deck construction associated with standard longitudinal post-tensioning. Notably, it offers an alternate to provide pre-compression across joints of precast deck units without employment of post-tensioning tendons and associated ducts in the deck. This significantly reduces the cost and time of construction required.
Beyond simply providing a system that eliminates the drawbacks in current precast deck construction, the present invention can potentially increase the load carrying capacity of longitudinal load-carrying members by employing appropriate connection details at the median pier, and correct construction steps. In the preferred embodiment, the stressing of the post-tensioning bars introduces a negative moment at the midspan of the girders, which offsets part of the girder moment under service load.
In conclusion, the present invention provides a structural construction system utilizing prefabricated deck units that is durable, easy to construct and cost-effective. The present invention can accommodate a variety of structural configurations and can be rapidly constructed.
Although the description above contains many specificities, these should not be construed as limiting the scope of the invention but as merely providing illustrations of some of the presently preferred embodiments of this invention. For example, as illustrated and described herein, the present invention can accommodate a variety of jacking methods and details, a variety of girder connection methods, and a variety of shapes and materials for longitudinal load-carrying members.
Thus the scope of the invention should be determined by the appended claims and their legal equivalents, rather than by the examples given.
This application claims the benefit of U.S. Provisional Application No. 61/449,713, filed Mar. 6, 2011 by the present inventor.
Number | Date | Country | |
---|---|---|---|
61449713 | Mar 2011 | US |