The invention relates to methods and apparatus for constructing buildings, in particular buildings constructed using modular units.
In the construction industry modular buildings are becoming more popular due to their ability to be constructed on site in shorter timeframes than traditional multi-storey construction. Modular construction involves building and preparing a building module offsite in a factory before transporting and installing the module at an installation location. Despite the time saving benefits of modular construction techniques there is a constant pursuit to improve these methods of construction with the aim of achieving time savings and cost savings in the overall construction of the building.
It is in light of these pursuits for efficiencies in current the construction of modular buildings that the invention was conceived.
The invention provides a method of constructing a modular multi-storey building including: assembling first and second building modules in a vertical arrangement at an installation location to form a multi-storey building structure, wherein temporary support members between the first and second building modules vertically support at least part of the second building module above the first building module; installing a permanent support structure and connecting it to the first and second building modules to vertically support the second building module above the first building module; and removing the temporary support members.
By providing a method in which the temporary support members can be removed it is possible to salvage and reuse building materials, such as steel supports, that becomes redundant once permanent support structures are installed.
The term building module is intended to refer to a construction unit that is created off site, for example in a factory setting, and is transported on site to be assembled with other building modules to construct a multi-storey building. The building module could include a basic form comprising a base and a frame fixed to the base that forms the ‘bones’ of walls and a ceiling.
Alternatively, the building module may comprise a unit in an almost finished state including base, walls, ceiling and even fixtures. Further still, the building module may include a construction falling between the basic and the almost finished forms discussed above.
In an embodiment the method includes at least partially constructing the first building module at a first location before assembling the first and second building modules at the installation location. The temporary support members may be attached to the first building module at the first location. A bracket may be attached to one or more of the temporary support members. A wall structure may be attached to the bracket. The bracket may be attached to the second building module.
In an embodiment the permanent support structure is installed after the second building module has been assembled at the installation location.
By providing a method in which the second building module can be installed before the permanent support structure is installed the installation of building modules can be decoupled from the supply of the permanent support structures.
In an embodiment a third building module is assembled above the second building module before the permanent support structure is connected to the first and second building modules. The third building module may be assembled above the second building module using temporary support members.
In an embodiment a concrete slab is cast to form a base of the first building module. In an embodiment a concrete slab is cast to form a base of the second building module. The base of the second building module may be cast to include a steel beam at least partially embedded into the base of the second building module. The steel beam of the base of the second building module may be located on a locator on one or more of the temporary support members.
In an embodiment concrete is poured to connect the first building module to the permanent support member. In an embodiment concrete is poured to connect the second building module to the permanent support member.
In an embodiment a tripod-type temporary support member is attached to the first building module. In an embodiment the temporary support members are re-used.
Also described herein is a method of constructing a modular building including the steps of:
The invention also provides a formwork assembly comprising: a first bracket having an elongate body, the elongate body having an attaching section to attach the first bracket to a building structure and a supporting section, the supporting section having a supporting means; a second bracket having an attaching section to attach the second bracket to a building structure and a supporting section, the supporting section having a supporting means; and a mesh made from reinforcing steel bar, the mesh being supported by the supporting means of the first bracket and the supporting means of the second bracket.
In an embodiment the supporting means are open ended slots. The open ended slots may be angled downwards. The horizontal sections of the mesh may be located in the open ended slots. The opened ended slots in the first and second brackets may be spaced apart so that each horizontal section of the mesh has a corresponding slot.
In an embodiment the first and second brackets are attached to a single common building structure. The common building structure may be a building module.
In an embodiment described herein there is a method of constructing a modular building including the steps of:
A bracket can be attached to the second end of the temporary support member, and the second building module can be attached to the temporary support member via the bracket.
An aperture in the bracket can be aligned with a bracket locator on the temporary support member when attaching a bracket to the second end of the temporary support member.
The base of the first building module can be constructed at a first location, and then transported from the first location to an installation location, where the building module is installed. The temporary support member can be attached to the base of the first building module before the first building module is transported to the installation location.
A wall panel can be attached to the first building module. Preferably the wall panel is attached to the base and the bracket. The wall panel can be attached before the first building module is transported to an installation location.
A height of the temporary support member can be adjusted to a desired height after the temporary support member has been attached to the base of the first building module.
The temporary support member can be detached from the bracket when removing the temporary support structure.
A mesh locator bracket can be installed to the first building module. A prefabricated concrete panel can be installed to connect the first building module to the second building module. Concrete can be poured at the installation location to connect the prefabricated concrete panel to connect the first and second building modules.
The second building module can be installed directly above the first building module. The temporary support members can be reused.
In an embodiment described herein there is a method of constructing a modular building including the steps of:
By providing a method in which a second building module is installed before a prefabricated panel is installed to support the second building module the installation of building modules can be decoupled from the supply of walls and other permanent support structures.
The first building module can be part of a first level of the modular building and the second building module is part of a second level of the modular building, and wherein all of the building modules for the first and the second levels are installed before step e) is performed. The base of the first building module can be constructed at a first location, and then transported from the first location to an installation location, where the building module is installed.
Before step e) is performed a third building module can be installed at the installation location so that at least part of the third building module is supported by a second support member, the second support member being attached to the second building module so that at least part of the third building module is supported by the second support member.
Step e) can include pouring concrete at the installation location to connect the prefabricated panel to the first building module. Preferably the prefabricated panel is a prefabricated concrete panel. Step e) can include lowering the prefabricated panel into position between the first building module and the second building module by crane.
The support member can be a temporary support member. The temporary support member can be a temporary support member as described above.
An embodiment, incorporating all aspects of the invention, will now be described by way of example only with reference to the accompanying drawings in which;
The inventor has realised that once the building modules have been installed on site and concrete structure (walls and columns) have been created or erected, the columns traditionally mounted on the base in the factory and that form a permanent part of the finished building, which columns are often formed of steel, can in fact become redundant as the building can be engineered to make the columns non-load bearing. The load in such a building is instead taken by the concrete structure, not the steel columns. The concrete structure can include concrete cores (for lift and stair wells) and shear walls (internal and external).
Accordingly, the method described herein is directed to a technique of providing structural integrity to a building module when required, without sacrificing or wasting structural components, which can be expensive.
In its basic form the method involves assembling building modules in a horizontal and/or vertical arrangement to form a building structure, wherein the modules include temporary supports, such as columns, to be able to support the modules on the next level above or a roof structure above. In describing the temporary support of modules, it is understood that the temporary supports also support the formwork used to install the permanent support structures. This could include the creation of concrete components used to connect and stitch together the modules. Once the modules are in place permanent support members are installed to connect between the lower module and the upper module (or roof) and the temporary support columns are removed (and can be re-used). Permanent supports can include the installation of pre-fabricated load bearing panels, such as concrete panels, or the in situ creation of concrete walls, including core and shear walls, through pouring or spraying (‘shotcreting’) wet concrete and allowing it to dry. Alternatively, the permanent support members could be steel braced walls, or any other suitable permanent structure.
The temporary support members could include the provision and changeover of more than one type of support structure. For example, if the building module is installed on site comprising a pre-formed base with upstanding steel columns attached thereto, after a second module is placed on top and held spaced above via the steel columns, a removable temporary support (such as the tripod-type discussed further below) for supporting the structure during construction (eg. concrete application) could be positioned between the first and second modules to support the upper module and to support formwork used (in a sacrificial or temporary way) in the in-situ forming of concrete elements including columns, panels or beams. The in-situ concrete elements could form part of the exterior façade of the building, or could form part of a concrete core, or could be the elements laterally and vertically connecting together the building modules.
Once the temporary supports are in place, the steel columns, which served to support the building module during transportation to site and erection, may then be removed (for re-use). The permanent structure is then installed by placement/pouring/spraying, and once the permanent structure, including concrete elements, is set and capable of bearing the load of the upper module, the temporary supports can be removed (and re-used).
Alternatively, it may be suitable to do away with steel columns altogether and instead use only one kind of removable temporary purpose-built support during construction of the multiple levels and installation of the permanent supports. A further alternative could be to employ a combination of temporary steel columns as well as the further temporary purpose-built supports.
Broadly, and referring to
It will be appreciated that the temporary support member in the form of a tripod 30 in the described embodiment, acts to space the second building module from the first building module during construction. In this way the second building module, and formwork between the modules, is located in the correct position by the temporary support member until the permanent support member(s) is installed or applied on site. It is the permanent support members that provide the structural integrity to the building. Thereafter the temporary support member may be removed.
It is envisaged that the base 21 of the first building module 20 could be constructed at a first location, and then moved, for example by being transported from the first location to an installation location, where the building module is installed. The first location may be a factory or a warehouse where the initial components of the first building module may be more easily assembled in an assembly line fashion, in order to assist in shortening overall construction time on site at the installation location. It is envisaged that the tripod 30 could be attached to the first building module 20 either before or after the first building module 20 is transported from the first location to an installation location.
Alternatively, if there is room on the building site, an assembly area may be allocated, for example, in an area that is designated as a courtyard or garden in the finished building. In this example the first building module 20 can be constructed on the building site in a designated assembly area before being moved into position, for example by a crane, and installed. Again, is envisaged that the tripod 30 could be attached to the first building module 20 either before or after the first building module 20 is positioned in an installation location. It will be understood that locating the assembly area, or factory, on the building site will help reduce transportation costs.
Referring to
The main shaft 33 extends from the first end 31 of the tripod 30 to the second end 32 of the tripod 30. The main shaft 33 is substantially straight along its entire length so that in use the main shaft 33 is substantially vertical when attached to a building module so that it can support a load, usually of at least one storey above, if not more. The two auxiliary legs 34, 35 are spaced 90 degrees from each other about the axial direction of the main shaft 33. In other words, the auxiliary legs 34, 35 lie in orthogonal planes.
A locator plate 60 is attached at the top of the main shaft 33. The locator plate 60 is attached to the top by fasteners, such as bolts, but it could be welded thereto. The locator plate 60 is used to assist in aligning a second building module 120 above the first building module 20. The locator plate 60 has a locator, shown as a protrusion, and more specifically shown as locator pin 62 that extends away from the face of the locator plate 60. The tip 63 of the locator pin 62 convergingly tapers as it extends away from the locator plate 60. In other words, the tip 63 of the locator pin 62 narrows as it extends away from the location plate 60. The locator pin 60 has a cylindrical base 64 that is wider than the tip 63 of the pin 62. The narrower tapered end of the locating pin 62 makes initial positioning of the second building module 120, while the wider base of the locating pin 62 ensures accurate alignment of the second building module 120 on top of the locator plate 60.
The method described above may therefore include attaching an angle bracket 40 to the second end 31 of the tripod 30 by aligning a locating aperture 42 in the angle bracket 40 with a bracket locator, such as bolt 61, on the locating plate 60.
While the tripod spacing depends on the building characteristics, it is envisaged that the spacing between tripods could be less than 8 meters. Alternatively, the spacing between tripods could be less than 6 meters, or between 1 and 3 meters. The spacing is also dependent on the additional structures that the tripods will need to support. For example, if the tripods will also support a façade wall the spacing may be less than if the supports only need to support a second building module above the tripod.
While the angle bracket 40 was discussed as extending across multiple tripods 30, it is envisaged that there could instead be multiple angle brackets 40 with one attached to each tripod 30.
Referring to
It is, however, understood that the slab may be created without a perimeter prefabricated channel steel beams. As shown in
Once the concrete slab has set the base 21 is removed from the construction bed/table and one or more tripods 30 are placed in position on the upper side 23 of the concrete floor 22 (as shown in
Once the height of all of the tripods 30 has been set the angle bracket 40 is located on the locator plates 60 of the tripods 30, which are at the second end 32 of the tripod 30. Once the angle bracket 40 is in position the angle bracket 40 is secured to the tripod 30 by the clamp nuts 68.
A wall structure, such as a wall panel, and shown as façade wall 70, can be attached to the building module 20 at this stage. To attach the façade wall 70 a façade bracket 72 is fixed to the steel beam 24 of the module base 21, for example by bolts or rivets. A façade wall bracket 74 is attached to a lower end 71 of the façade wall 70 to allow connection to the façade bracket 72. The façade wall 70 has alignment means, shown as alignment bracket 76, located at the upper end 73 of the façade wall 70. The alignment bracket 76 has a channel 77. The façade wall 70 can be lowered into position so that the façade wall bracket 74 contacts and rests on the façade wall bracket 72, and so that the secondary section 43 of the angle bracket 40 is located in the channel 77 of the alignment bracket 76.
It is envisaged that the tripods 30 and the wall structure(s) or wall panel(s) could be attached to the module/base either before or after the first building module is transported to the installation location.
By installing the angle bracket 40 and outer walls to the building module 20 before the module is moved into the installation position the building site can operate with increased safety. This is because the installation of the outer walls removes the live edge of the building site, thereby eliminating a live edge for workers to fall from. In addition, by removing the live edge the construction process also becomes more efficient as there is no need for external barriers to be installed around the building before workers can enter the worksite.
After the angle bracket(s) 40 have been installed on the tripods 30 the first building module 20 is transported from the warehouse to an installation location, such as a building site. The first building module 20 is then installed at the building site (either on the ground floor or above another building module already installed).
The second building module 120 may be installed directly above the first building module 20, as shown in
After the second building module 120 is attached to the angle bracket 40 a permanent support member, such as pre-fabricated concrete wall 80, is installed and connected to the first building module 20 and the second building module 120. The permanent support member acts to support at least part of the second building module 120 above the first building module 20. It is envisaged that the permanent support member could be internal structural walls that are built on site. For example, the internal structural walls could be pre-fabricated concrete walls that are installed after the second building module has been installed.
Referring to
The permanent support structure is then attached to the first and second building modules 20, 120 so that the permanent support structure supports the second building module 120. This may be achieved by, for example, pouring concrete to connect the first building module 20 and the second building module 120 to the permanent support member. Alternatively, the permanent support structure may be bolted to the building modules 20, 120, for example through the steel beams 24, 124.
As discussed above, the permanent support structure may comprise other forms. For example the support structures may be defined by in situ preparation of core or shear walls using wet concrete that has been poured or sprayed.
Adjacent building modules in a single level can be ‘stitched’ together, in other words joined together by in situ wet joint connections of concrete, to create a finished floor structure. The in situ formed joints, preferably in the form of beams, are structural joints that contribute to the structural integrity of the building and therefore reduce the amount of vertical support required in the vicinity of the beams. Further information regarding ‘stitching’ methods can be found in co-pending international patent application no PCT/AU2017/050546, which also claims priority from Australian provisional application no. 2016902460 filed on 23 Jun. 2016 titled “METHODS AND APPARATUS FOR CONSTRUCTING BUILDINGS”, and from Australian provisional application no. 2016903025 filed on 1 Aug. 2016 and titled “METHOD FOR CONSTRUCTING A CONCRETE FLOOR IN A MULTISTOREY BUILDING”. The description and teachings of that co-pending international patent application is incorporated herein by reference to save reproducing that entire specification herein.
After the permanent support structure is installed the angle bracket 40 is detached from the tripod 30. This is achieved by rotating the clamp nuts 68 out of position so that the angle bracket 40 is free and remains part of the permanent structure. The height of the tripod 30 is then reduced and the bolts removed from the feet 36. The tripod 30 is then removed so that the permanent support member supports the second building module 120. The tripod 30 can then be reused for the next building module. Referring to
Using temporary support structures, such as the tripods 30, is particularly suitable for tall buildings where concrete walls and columns are needed (smaller buildings can rely more heavily on steel structures), but is still entirely applicable to smaller structures. Suitability can be based on two main reasons: the first being that the building modules require a minimum level of reinforcement and stiffness in order to be transported and/or assembled on site, which later becomes redundant once the concrete walls and columns are in place. The temporary support structures reduce the amount of redundant steel used, thereby making the build more cost effective and more conscious of the environment.
The second reason of the suitability of the presently described method and system is that using temporary support structures decouples the installation of building modules from the installation of the concrete walls and columns, which will often take longer to do as concrete often needs to be poured/sprayed then allowed to set (which can take a week to set).
A benefit of decoupling these processes is that it allows the construction of the building to progress if there are reasons that concrete cannot be poured (due to delays or adverse weather conditions etc.). This can allow a modular building to be completed more quickly by not needing to wait for each level to be fully completed and dried before the modules of the next level can be installed.
It is envisaged that multiple levels could be installed before the permanent support structures are installed. For example, it is envisaged that a build could advance five floors higher than the last permanent support structures before the build would need to stop and wait for permanent support structures to be installed.
It will be understood that in order to decouple the pouring of concrete from the installation of modular building modules on successive level the support members do not need to be temporary support member that are replaced. In other words, the temporary support members could be permanent support members, or they could be support members that become redundant when the building is finished.
Referring to
As described above, it is envisaged that multiple levels could be installed before the permanent support structures are installed. For example, a second support member, such as a tripod 130, may be attached to the second building module 120, and a third building module (not shown) may be installed at the installation location so that at least part of the third building module is supported by the tripod 130.
In a similar way to that described for the second building module 120, a permanent support structure can be installed to permanently support the third building module above the second building module. The tripods 130 can then be removed from between the second building module 120 and the third building module. It is also envisaged that the third building module could be installed above the second building module 120 before a permanent support structure such as pre-fabricated concrete wall 80, or an in-situ poured/sprayed wall, is installed and/or connected to the first and second building modules 20, 120, and therefore before the tripods 30 between the first building module 20 and the second building module 120 have been removed.
It is understood that reference to “installing” a permanent support structure includes within its scope both the placement of a prefabricated structure, such as a wall 80, or the in-situ creation of a permanent support structure by the application of concrete (by pouring or shotcreteing) to create a column, beam or wall.
It is envisaged that instead of attaching a façade wall 70 to the first building module 20 (as described above) a prefabricated concrete wall could also be attached to the first building module 20. Alternatively, the outer wall could be constructed on site as a shotcrete wall. If a shotcrete wall is desired a bracket for supporting a mesh made from reinforcing steel bar (rebar) may be installed on the first building module 20 to reinforce the concrete wall, either before or after transporting the first building module 20 to the installation location.
Referring to
It is envisaged that splice bars (not shown) made from rebar (splice rebar) could be removably attached to the rebar mesh 150. The splice bars can have a bent section at one end of the splice bar that allows the splice bar to be hooked onto the rebar mesh 150. The splice bars could be temporarily attached to the rebar mesh 150 in other ways during transportation (e.g. tied down), however the hooked splice bars provide a quick and easy solution for attachment. The splice bars may be hooked onto the rebar mesh 150 in the warehouse when the rebar mesh 150 is located in the rebar brackets 140. This ensures that the splice bars are ready to be used on site once the first building module is installed. Alternatively, the rebar mesh 150 and splice bars may be installed once the first building module 20 has been installed at an installation location.
By using the rebar brackets 140 and the rebar mesh 150 there is no need to weld the rebar mesh 150 to other parts of the partially built building structure (welding is more expensive and time intensive than splicing). This is advantageous as it can reduce the amount of time taken to construct a shotcrete wall. There is also no need for a construction worker to hold and locate the rebar, which is required when attaching mesh rebar in more conventional buildings. This allows larger sections of rebar mesh to be used when utilising the rebar brackets 140. It is envisaged that the rebar bracket 140 and the rebar mesh 150 could also be used to assist in constructing internal walls. Shutters may also be installed on the module 20 to allow concrete walls to be poured, rather than using a shotcrete process.
While the supporting means is described as slots, it is envisaged that the supporting means could be any other suitable supporting member, such as a hook. In addition, while the rebar mesh 150 has been described as extending between two rebar brackets that extend from the angle bracket 40 to the steel beam 24, it is envisaged that one or more of the brackets would not extend from the angle bracket 40 to the steel beam 24, and may be suspended from the angle bracket alone or attached to the steel beam alone. It is also envisaged that instead of the wall being a shotcrete wall, the wall may be a poured wall.
It is to be understood that, if any prior art publication is referred to herein, such reference does not constitute an admission that the publication forms a part of the common general knowledge in the art, in Australia or any other country
In the claims which follow and in the preceding description of the invention, except where the context requires otherwise due to express language or necessary implication, the word “comprise” or variations such as “comprises” or “comprising” is used in an inclusive sense, i.e. to specify the presence of the stated features but not to preclude the presence or addition of further features in various embodiments of the invention.
Number | Date | Country | Kind |
---|---|---|---|
2016902460 | Jun 2016 | AU | national |
2016903025 | Aug 2016 | AU | national |
Filing Document | Filing Date | Country | Kind |
---|---|---|---|
PCT/AU2017/050064 | 1/27/2017 | WO |
Publishing Document | Publishing Date | Country | Kind |
---|---|---|---|
WO2017/219064 | 12/28/2017 | WO | A |
Number | Name | Date | Kind |
---|---|---|---|
3300943 | Owens | Jan 1967 | A |
3568380 | Stucky | Mar 1971 | A |
3613325 | Yee | Oct 1971 | A |
3918222 | Bahramian | Nov 1975 | A |
4023315 | Stucky | May 1977 | A |
4147009 | Watry | Apr 1979 | A |
4221098 | Mayer et al. | Sep 1980 | A |
4435927 | Umezu | Mar 1984 | A |
4443985 | Moreno | Apr 1984 | A |
4470227 | Bigelow, Jr. | Sep 1984 | A |
4546530 | Rizk | Oct 1985 | A |
5224321 | Fearn | Jul 1993 | A |
6223480 | Khoo | May 2001 | B1 |
6625943 | Renner | Sep 2003 | B1 |
6651393 | Don | Nov 2003 | B2 |
7581709 | Gillespie | Sep 2009 | B2 |
8291675 | Tikhovskiy | Oct 2012 | B2 |
8336276 | Tikhovskiy | Dec 2012 | B2 |
9371648 | Tikhovskiy | Jun 2016 | B1 |
9487943 | Bui | Nov 2016 | B2 |
10066390 | Pospisil | Sep 2018 | B2 |
10260224 | Jazzar | Apr 2019 | B1 |
10501948 | Lizarazu Zaldua | Dec 2019 | B2 |
20120167502 | Tikhovskiy | Jul 2012 | A1 |
20130055671 | Bruce | Mar 2013 | A1 |
20130305629 | Stephenson | Nov 2013 | A1 |
20140298745 | Rechenmacher | Oct 2014 | A1 |
20150308096 | Merhi et al. | Oct 2015 | A1 |
20160251853 | Rubel | Sep 2016 | A1 |
20210376261 | Boudreault | Dec 2021 | A1 |
Number | Date | Country |
---|---|---|
933376 | Sep 1973 | CA |
110439259 | Nov 2019 | CN |
102016012237 | Jul 2018 | DE |
1184521 | Mar 2002 | EP |
2901820 | Dec 2007 | FR |
1101597 | Jan 1968 | GB |
1271024 | Apr 1972 | GB |
1350599 | Apr 1974 | GB |
100873846 | Dec 2008 | KR |
20130083100 | Jul 2013 | KR |
2376424 | Dec 2009 | RU |
2005108700 | Nov 2005 | WO |
2011106842 | Sep 2011 | WO |
2012045149 | Apr 2012 | WO |
WO-2012070281 | May 2012 | WO |
WO-2017093221 | Jun 2017 | WO |
WO-2017093221 | Jun 2017 | WO |
WO-2019034279 | Feb 2019 | WO |
Entry |
---|
International Search Report for Application No. PCT/AU2017/050064 dated Jun. 30, 2017 (5 pages). |
International Preliminary Report on Patentability for Application No. PCT/AU2017/050064 dated Oct. 22, 2018 (85 pages). |
International Search Report for related Application No. PCT/AU2017/050063 dated May 4, 2017 (4 Pages). |
International Search Report for related Application No. PCT/AU2017/050546 dated Sep. 29, 2017 (5 Pages). |
Examination Report issued from the Australian Patent Office for related Application No. 2017282720 dated Dec. 13, 2021 (5 Pages). |
Examination Report issued from the Australian Patent Office for related Application No. 2017280086 dated Dec. 21, 2021 (4 Pages). |
Number | Date | Country | |
---|---|---|---|
20190211544 A1 | Jul 2019 | US |